LONG RANGE PLAN AND FORECAST. 12.1 Contractor shall prepare and submit to GNPC the following: a) During Exploration Period, an Exploration Plan for each year commencing as of the Effective Date which shall contain the following information: i) Estimated Exploration Costs showing outlays for each of the years or the number of years agreed and covered by the Plan; ii) Details of seismic operations for each such year; iii) Details of drilling activities planned for each such year; iv) Details of infrastructure utilisation and requirements. The Exploration Plan shall be revised on each anniversary of the Effective Date. Contractor shall prepare and submit to GNPC the first Exploration Plan for the First Subperiod of twelve months of the Initial Exploration Period within sixty (60) days after the Effective Date and thereafter shall prepare and submit to GNPC no later than forty five (45) days before each anniversary of the Effective Date a revised Exploration Plan. b) In the event of a Development Plan being approved, the Contractor shall prepare a Development Forecast for each Calendar Year of the Development Period, which shall contain the following information: i) forecast of capital expenditure portions of Development and Production expenditures for each Calendar Year of the Development Period; ii) forecast of operating costs for each Calendar Year; iii) forecast of Petroleum production for each Calendar Year; iv) forecast of number and types of personnel employed in the Petroleum Operations in the Republic of Ghana; v) description of proposed Petroleum marketing arrangements; vi) description of main technologies employed; and vii) description of the working relationship of Contractor to GNPC. c) The Development forecast shall be revised at the beginning of each Calendar Year commencing as of the second year of the first Development forecast Contractor shall prepare and submit to GNPC the first Development forecast within one hundred and twenty (120) days of the date when the first Development Plan is approved by the Minister and Contractor commences the implementation of such plan and thereafter shall prepare and submit a revised Development Forecast to GNPC no later than thirty (30) days before each Calendar Year commencing as of the second year of the first Development forecast.
Appears in 2 contracts
Sources: Petroleum Agreement, Petroleum Agreement (Kosmos Energy Ltd.)
LONG RANGE PLAN AND FORECAST. 12.1 Contractor 31.22.1 Licensee shall prepare and submit to GNPC the Director General the following:
a) During Exploration Period, an Exploration Plan for each year commencing as of the Effective Date which shall contain the following information:
i) Estimated Exploration Costs showing outlays for each of the years or the number of years agreed and covered by the Plan;.
iib) Details of seismic operations for each such year;,
iiic) Details of drilling activities planned for each such year;
ivd) Details of infrastructure utilisation utilization and requirements. .
31.22.2 The Exploration Plan shall be revised on each anniversary of the Effective Date. Contractor Licensee shall prepare and submit to GNPC the Director General the first Exploration Plan for the First Subperiod of twelve months of the Initial Exploration Period of two (2) years within sixty (60) days after of the Effective Date and thereafter shall prepare and submit to GNPC The Director General no later than forty forty-five (45) days before each anniversary of the Effective Date a revised Exploration Plan.
ba) In the event of a Development Plan being approved, the Contractor Licensee shall prepare a Development Forecast for each Calendar Year calendar year of the Development Period, which shall contain the following information:
i) i. forecast of the capital expenditure portions of Development and Production expenditures for each Calendar Year of the Development Period;
ii) . forecast of operating costs for each Calendar Year;
iii) . forecast of Petroleum production for each Calendar Year;
iv) forecast of number and types of personnel employed in the Petroleum Operations in the Republic of Ghana;
v) description of proposed Petroleum marketing arrangements;
vi) . description of main technologies employed; and
vii) description of the working relationship of Contractor to GNPC.
cb) The Development forecast shall be revised at the beginning of each Calendar Year commencing as of the second year of the first Development forecast Contractor forecast. Licensee shall prepare and submit to GNPC the Director General the first Development forecast within one hundred and twenty (120) days of the date when the first Development Plan is approved by the Minister and Contractor commences the implementation of such plan and thereafter shall prepare and submit a revised Development Forecast to GNPC Director General no later than thirty forty-five (3045) days before each Calendar Year commencing as of the second year of the first Development forecast.
Appears in 2 contracts
Sources: Petroleum Licence Agreement, Petroleum Licence Agreement