Common use of Long Term Force Majeure Clause in Contracts

Long Term Force Majeure. If the Claiming Party is unable to deliver or accept delivery for reasons of Force Majeure and this inability lasts for more than ninety (90) consecutive calendar days or one hundred and eighty (180) calendar days in total in a calendar year, the other Party may, by notice in writing to the Claiming Party, and subject to the provisions of § 15.5 (Notification and Mitigation of Force Majeure), extend the period of release for such longer period and on so many occasions as may be specified by the other Party.

Appears in 7 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Long Term Force Majeure. If the Claiming Party is unable to deliver Deliver or accept delivery Delivery for reasons of Force Majeure and this inability lasts for more than ninety thirty (9030) consecutive calendar days or one hundred and eighty (180) calendar days in total in a calendar yeardays, the other Party may, by notice in writing to the Claiming Party, and subject to the provisions of § 15.5 6.3 (Notification and Mitigation of Force Majeure), extend the period of release for such longer period and on so many occasions as may be specified by the other Party.either:

Appears in 4 contracts

Samples: www.efet.org, www.efet.org, efet.org

Long Term Force Majeure. If the Claiming Party is unable to deliver or accept delivery for reasons of Force Majeure and this inability lasts for more than ninety (90) consecutive calendar days or one hundred and eighty (180) calendar days in total in a calendar year, the other Party may, by notice in writing to the Claiming Party, and subject to the provisions of § 15.5 (Notification and Mitigation of Force Majeure), extend the period of release released for such longer period and on so many occasions as may be specified by the other Party.

Appears in 1 contract

Samples: Power Purchase Agreement

Long Term Force Majeure. If the Claiming Party is unable to deliver Deliver or accept delivery Delivery for reasons of Force Majeure and this inability lasts for more than ninety thirty (9030) consecutive calendar days or one hundred and eighty (180) calendar days in total in a calendar yeardays, the other Party may, by notice in writing to the Claiming Party, and subject to the provisions of § 15.5 5.3 (Notification and Mitigation of Force Majeure), extend the period of release for such longer period and on so many occasions as may be specified by the other Party.either:

Appears in 1 contract

Samples: www.efet.org

AutoNDA by SimpleDocs

Long Term Force Majeure. If the Claiming Party is unable to deliver Deliver or accept delivery Delivery for reasons of Force Majeure and this inability lasts for more than ninety thirty (9030) consecutive calendar days or one hundred and eighty (180) calendar days in total in a calendar yeardays, the other Party may, by notice in writing to the Claiming Party, and subject to the provisions of § 15.5 6.3 (Notification and Mitigation of Force Majeure), extend the period of release for such longer period and on so many occasions as may be specified by the other Party.

Appears in 1 contract

Samples: recs.org

Long Term Force Majeure. If the Claiming Party is unable to deliver or accept delivery for reasons of Force Majeure and this inability lasts for more than ninety (90) consecutive calendar days or one hundred and eighty (180) calendar days in total in a calendar year, the other Party may, by notice in writing to the Claiming Party, and subject to the provisions of § 15.5 (Notification and Mitigation of Force Majeure), extend the period of release for such longer period and on so many occasions as may be specified by the other Party. 7.

Appears in 1 contract

Samples: efet.org