MANAGEMENT ORDERS; REVOCATION OR EXPIRY OF THE DCC LICENCE. 7.1. Without limiting the Contractor's other obligations under this Agreement, the Contractor shall: 7.1.1. promptly provide any co-operation, documentation, data, information or other assistance reasonably requested by: (a) the DCC or any person performing the functions or activities of DCC pursuant to a Management Order from time to time in relation DCC’s compliance with a Management Order; (b) the DCC from time to time in relation to the preparation, review and/or modification of the Business Handover Plan or; and (c) the DCC, the Authority and/or the Successor Licensee in relation to the handover of the Authorised Business from the DCC to the Successor Licensee; 7.1.2. ensure that appropriate representatives of the Contractor, including any representatives specifically identified by the DCC, the Authority and/or the Successor Licensee, attend any meetings with any of those persons that are requested from time to time in relation to: (a) any person performing the functions or activities of DCC pursuant to a Management Order; (b) the preparation, review and/or modification of the Business Handover Plan; or (c) the handover of the Authorised Business from the DCC to the Successor Licensee. 7.1.3. continue to perform the Services in accordance with this Agreement notwithstanding the handover of the Authorised Business from the DCC to the Successor Licensee. 7.2. To the extent that compliance by the Contractor with this paragraph 7 requires the Contractor to incur any material additional costs (being costs which it would not have otherwise incurred under this Agreement), then the Contractor may notify the DCC accordingly and the parties (acting reasonably) shall agree any necessary changes to the Contractor’s charges.
Appears in 2 contracts
Samples: Contractor Agreement, Terms and Conditions
MANAGEMENT ORDERS; REVOCATION OR EXPIRY OF THE DCC LICENCE. 7.1. Without limiting the Contractor's other obligations under this Agreement, the Contractor shall:
7.1.1. promptly provide any co-operation, documentation, data, information or other assistance reasonably requested by:
(a) the DCC or any person performing the functions or activities of DCC pursuant to a Management Order from time to time in relation DCC’s compliance with a Management Order;
(b) the DCC from time to time in relation to the preparation, review and/or modification of the Business Handover Plan or; and
(c) the DCC, the Authority and/or the Successor Licensee in relation to the handover of the Authorised Business from the DCC to the Successor Licensee;
7.1.2. ensure that appropriate representatives of the Contractor, including any representatives specifically identified by the DCC, the Authority and/or the Successor Licensee, attend any meetings with any of those persons that are requested from time to time in relation to:
(a) any person performing the functions or activities of DCC pursuant to a Management Order;
(b) the preparation, review and/or modification of the Business Handover Plan; or
(c) the handover of the Authorised Business from the DCC to the Successor Licensee.. DCCT0254 DCC Confidential Page 38 of 63
7.1.3. continue to perform the Services in accordance with this Agreement notwithstanding the handover of the Authorised Business from the DCC to the Successor Licensee.
7.2. To the extent that compliance by the Contractor with this paragraph 7 requires the Contractor to incur any material additional costs (being costs which it would not have otherwise incurred under this Agreement), then the Contractor may notify the DCC accordingly and the parties (acting reasonably) shall agree any necessary changes to the Contractor’s charges.
Appears in 1 contract
Samples: Provision of a Study to Demonstrate the Technology and Security Landscape for the Next 10 – 15 Years
MANAGEMENT ORDERS; REVOCATION OR EXPIRY OF THE DCC LICENCE. 7.1. 7.1 Without limiting the Contractor's other obligations under this Agreement, the Contractor shall:
7.1.1. 7.1.1 promptly provide any co-operation, documentation, data, information or other assistance reasonably requested by:
(a) 7.1.1.1 the DCC or any person performing the functions or activities of DCC pursuant to a Management Order from time to time in relation DCC’s compliance with a Management Order;
(b) 7.1.1.2 the DCC from time to time in relation to the preparation, review and/or modification of the Business Handover Plan or; and
(c) 7.1.1.3 the DCC, the Authority and/or the Successor Licensee in relation to the handover of the Authorised Business from the DCC to the Successor Licensee;
7.1.2. 7.1.2 ensure that appropriate representatives of the Contractor, including any representatives specifically identified by the DCC, the Authority and/or the Successor Licensee, attend any meetings with any of those persons that are requested from time to time in relation to:
(a) 7.1.2.1 any person performing the functions or activities of DCC pursuant to a Management Order;
(b) 7.1.2.2 the preparation, review and/or modification of the Business Handover Plan; or
(c) 7.1.2.3 the handover of the Authorised Business from the DCC to the Successor Licensee.
7.1.3. 7.1.3 continue to perform the Services in accordance with this Agreement notwithstanding the handover of the Authorised Business from the DCC to the Successor Licensee.
7.2. 7.2 To the extent that compliance by the Contractor with this paragraph 7 requires the Contractor to incur any material additional costs (being costs which it would not have otherwise incurred under this Agreement), then the Contractor may notify the DCC accordingly and the parties (acting reasonably) shall agree any necessary changes to the Contractor’s charges.