Management Plan. 9.1 The Implementation Agency shall provide the Nodal Agency or its nominated agency with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the MSA as a whole and in relation to the Project Implementation, and the Operation and Management SLA. (i) A detailed program of the transfer process that could be used in conjunction with a Replacement Implementation Agency including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer; (ii) plans for the communication with such of the Implementation Agency's sub contractors, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on the Nodal Agency’s operations as a result of undertaking the transfer; (iii) (if applicable) proposed arrangements for the segregation of the Implementation Agency's networks from the networks employed by Nodal Agency and identification of specific security tasks necessary at termination; (iv) Plans for provision of contingent support to Nodal Agency, and Replacement Implementation Agency for a reasonable period after transfer. 9.2 The Implementation Agency shall re-draft the Exit Management Plan annually thereafter to ensure that it is kept relevant and up to date. 9.3 Each Exit Management Plan shall be presented by the Implementation Agency to and approved by the Nodal Agency or its nominated agencies. 9.4 The terms of payment as stated in the Terms of Payment Schedule include the costs of the Implementation Agency complying with its obligations under this Schedule. 9.5 In the event of termination or expiry of MSA, and Project Implementation, each Party shall comply with the Exit Management Plan. 9.6 During the exit management period, the Implementation Agency shall use its best efforts to deliver the services. 9.7 Payments during the Exit Management period shall be made in accordance with the Terms of Payment Schedule. 9.8 This Exit Management plan shall be furnished in writing to the Nodal Agency or its nominated agencies within 90 days from the Effective Date of this Agreement. Governance Projects 52 | P a g e
Appears in 1 contract
Samples: Master Services Agreement
Management Plan. 9.1 The Implementation Agency shall provide the Nodal Agency or its nominated agency with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the MSA as a whole and in relation to the Project Implementation, and the Operation and Management SLA.
(i) A detailed program of the transfer process that could be used in conjunction with a Replacement Implementation Agency including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer;
(ii) plans for the communication with such of the Implementation Agency's sub contractors, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on the Nodal Agency’s operations as a result of undertaking the transfer;
(iii) (if applicable) proposed arrangements for the segregation of the Implementation Agency's networks from the networks employed by Nodal Agency and identification of specific security tasks necessary at termination;
(iv) Plans for provision of contingent support to Nodal Agency, and Replacement Implementation Agency for a reasonable period after transfer.
9.2 The Implementation Agency shall re-draft the Exit Management Plan annually thereafter to ensure that it is kept relevant and up to date.
9.3 Each Exit Management Plan shall be presented by the Implementation Agency to and approved by the Nodal Agency or its nominated agencies.
9.4 The terms of payment as stated in the Terms of Payment Schedule include the costs of the Implementation Agency complying with its obligations under this Schedule.
9.5 In the event of termination or expiry of MSA, and Project Implementation, each Party shall comply with the Exit Management Plan.
9.6 During the exit management period, the Implementation Agency shall use its best efforts to deliver the services.
9.7 Payments during the Exit Management period shall be made in accordance with the Terms of Payment Schedule.
9.8 This Exit Management plan shall be furnished in writing to the Nodal Agency or its nominated agencies within 90 days from the Effective Date of this Agreement. Governance Projects 52 | P a g e
Appears in 1 contract
Samples: Master Services Agreement
Management Plan. 9.1 The Implementation Agency System Integrator shall provide the Nodal Agency or its nominated agency with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the MSA as a whole and in relation to the Project Implementation, and the Operation and Management SLA.
(i) A detailed program of the transfer process that could be used in conjunction with a Replacement Implementation Agency System Integrator including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer;
(ii) plans for the communication with such of the Implementation AgencySystem Integrator's sub contractors, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on the Nodal Agency’s operations as a result of undertaking the transfer;
(iii) (if applicable) proposed arrangements for the segregation of the Implementation AgencySystem Integrator's networks from the networks employed by Nodal Agency and identification of specific security tasks necessary at termination;
(iv) Plans for provision of contingent support to Nodal Agency, and Replacement Implementation Agency System Integrator for a reasonable period after transfer.
9.2 The Implementation Agency System Integrator shall re-draft the Exit Management Plan annually thereafter to ensure that it is kept relevant and up to date.
9.3 Each Exit Management Plan shall be presented by the Implementation Agency System Integrator to and approved by the Nodal Agency or its nominated agencies.
9.4 The terms of payment as stated in the Terms of Payment Schedule include the costs of the Implementation Agency System Integrator complying with its obligations under this Schedule.
9.5 In the event of termination or expiry of MSA, and Project Implementation, each Party shall comply with the Exit Management Plan.
9.6 During the exit management period, the Implementation Agency System Integrator shall use its best efforts to deliver the services.
9.7 Payments during the Exit Management period shall be made in accordance with the Terms of Payment Schedule.
9.8 This Exit Management plan shall be furnished in writing to the Nodal Agency or its nominated agencies within 90 days from the Effective Date of this Agreement. Governance Projects 52 | P a g e
Appears in 1 contract
Samples: Contract Agreement for Selection of System Integrators
Management Plan. 9.1 The Implementation Agency Service Provider (SP) shall provide the Nodal Agency Purchaser or its nominated agency with a recommended exit management plan ("Exit Management Plan") which shall deal with at least the following aspects of exit management in relation to the MSA as a whole and in relation to the Project Implementation, and the Operation and Management SLA.
(i) A detailed program of the transfer process that could be used in conjunction with a Replacement Implementation Agency Service Provider (SP) including details of the means to be used to ensure continuing provision of the services throughout the transfer process or until the cessation of the services and of the management structure to be used during the transfer;
(ii) plans for the communication with such of the Implementation AgencyService Provider's sub contractors, staff, suppliers, customers and any related third party as are necessary to avoid any material detrimental impact on the Nodal AgencyPurchaser’s operations as a result of undertaking the transfer;
(iii) (if applicable) proposed arrangements for the segregation of the Implementation AgencyService Provider's networks from the networks employed by Nodal Agency Purchaser and identification of specific security tasks necessary at termination;
(iv) Plans for provision of contingent support to Nodal AgencyPurchaser, and Replacement Implementation Agency Service Provider (SP) for a reasonable period after transfer.
9.2 The Implementation Agency Service Provider (SP) shall re-draft the Exit Management Plan annually thereafter to ensure that it is kept relevant and up to date.
9.3 Each Exit Management Plan shall be presented by the Implementation Agency Service Provider (SP) to and approved by the Nodal Agency Purchaser or its nominated agencies.
9.4 The terms of payment as stated in the Terms of Payment Schedule include the costs of the Implementation Agency Service Provider (SP) complying with its obligations under this Schedule.
9.5 In the event of termination or expiry of MSA, and Project Implementation, each Party shall comply with the Exit Management Plan.
9.6 During the exit management period, the Implementation Agency Service Provider (SP) shall use its best efforts to deliver the services.
9.7 Payments during the Exit Management period shall be made in accordance with the Terms of Payment Schedule.
9.8 This Exit Management plan shall be furnished in writing to the Nodal Agency Purchaser or its nominated agencies within 90 days from the Effective Date of this Agreement. Governance Projects 52 | P a g e.
Appears in 1 contract