DELAYS AND EXTENSIONS OF TIME Sample Clauses

DELAYS AND EXTENSIONS OF TIME. 8.3.1 If the Contractor is delayed at any time in the progress of the Work by any act or failure to act by the State or the Architect, or by any employee of either, or by any separate contractor employed by the State, or by changes ordered in the Work, fire, unusual delay in transportation, adverse weather conditions not reasonably anticipatable, unavoidable casualties, or any causes beyond the Contractor's control, or by delay authorized by the State pending alternative dispute resolution proceedings, or by any other cause which may justify the delay, then the Contract Time shall be extended by Change Order for such reasonable time as recommended by the Architect and approved by the State. 8.3.2 Any claim for extension of time shall be made in writing to the Architect not more than twenty days after the commencement of the delay; otherwise it shall be waived. In the case of a continuing delay only one claim is necessary. The Contractor shall provide an estimate of the probable effect of such delay on the progress of the Work. 8.3.3 This Paragraph 8.3 does not exclude the recovery of damages for delay by either party under other provisions of the Contract Documents.
AutoNDA by SimpleDocs
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to perform this Contract continuously and diligently. No charges or claims for damages shall be made by the Contractor for any delays or hindrances, regardless of cause, in the performance of services under this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
DELAYS AND EXTENSIONS OF TIME. If the Contractor is delayed at any time in the progress of the Work by any act or failure to act by the State or the Architect, or by any employee of either, or by any separate contractor employed by the State, or by changes ordered in the Work, fire, unusual delay in transportation, adverse weather conditions not reasonably anticipatable, unavoidable casualties, or any causes beyond the Contractor's control, or by delay authorized by the State pending alternative dispute resolution proceedings, or by any other cause which may justify the delay, then the Contract Time shall be extended by Change Order for such reasonable time as recommended by the Architect and approved by the State.
DELAYS AND EXTENSIONS OF TIME. 8.3.1 If the Contractor is delayed at any time in progress of the Work by an act or neglect of the Owner or Architect, or of an employee of either, or of a separate Contractor employed by the Owner, or by changes ordered in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other caused beyond the Contractor's control, or by delay authorized by the Owner, or by other causes which the Architect determines may justify delay, the Contract Time shall be extended by Change Order to the extent such delay will prevent the Contractor from achieving Substantial Completion with the contract Time and if the performance of the Work is not, was not, or would not have been delayed by any other cause for which the Contractor is not entitled to an extension in the contract time under the Contract Documents. The Contractor further acknowledges and agrees that adjustments in the contract Time will be permitted for a delay only to the extent such delay (1) is not caused, or could not have been anticipated, by the Contractor, or (2) could not be limited or avoided by the Contractor's timely notice to the Owner of the delay and (3) is of a duration not less than one (1) day. 8.3.1.1 Weather, which hinders or prevents work, is not a basis for a time extension unless it surpasses in severity the weather reasonably to be expected in the locality at the particular time of the year. If the contractor files timely notice that he was delayed by weather sufficiently severe as to entitle Contractor to additional time, Contractor should furnish promptly, a statement of the portion of the work affected, an explanation as to the reasons work was prevented or hindered by the weather if not readily apparent, the dates on which such portions of work were affected, the total number of days the job in its entirety was delayed, and other information such as official weather bureau climatological data for a ten year period, local weather bureau data, job daily records, etc. Time extensions due to adverse weather shall not be allowed after the Contract Substantial Completion date. Construction time is based on Local Average weather conditions. Requests for time extensions due to adverse weather, shall be considered only for and equal to the number of "rain days" in excess of the ten year mean average number of days for any given time period as shown by the the US National Oceanic and Atmospheric Administration, National Climatic Data Center, Ashville, Nor...
DELAYS AND EXTENSIONS OF TIME. A. If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the SDSTA, or by any separate contractor employed by the SDSTA, or by changes ordered in the Work, or by labor disputes not caused by the labor practices of the Contractor, or by fire, unusual delay in transportation, severe and unusual weather conditions not reasonably anticipated, unavoidable casualties, or any other causes beyond Contractor's control and not occurring due to the fault or neglect of the Contractor, any subcontractor or any other person for whose acts the Contractor is responsible, then the Contract Time shall be extended by Change Order for such reasonable time as the SDSTA shall determine. B. Any claim for extension of time shall be made in writing to the SDSTA not more than ten (10) days after the commencement of the delay; otherwise it shall be deemed waived. In the case of continuing delay, only one claim is necessary. C. Time extensions will not be granted for rain, wind, snow, or other natural phenomena of normal intensity for the locality where the Work is to be performed. D. Contractor's right to make a claim or claims for an extension of time shall not preclude Contractor's right to make a claim for delay damages arising out of the SDSTA’s significant interference, by action or inaction, with the Contractor's Work.
DELAYS AND EXTENSIONS OF TIME. The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays, interruptions, interferences, or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract. Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the State in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the State, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
DELAYS AND EXTENSIONS OF TIME. 2.6.1 The Contractor shall provide the requisite labor and sufficient Materials and Equipment to maintain the Project Schedule and in particular, that portion of the Project Schedule applicable to the Contractor's Work. If the Contractor's Work is delayed by reason of its or its Subcontractors' or its Vendors’ acts, the Contractor shall, at the Owner’s Representative’s direction, increase the number of workers, the number of shifts, the days of work and, to the extent permitted by law, institute overtime operations, all at the Contractor’s sole cost and expense, in order to regain any time loss and maintain the Project Schedule and the Overall Contract Schedule. All costs of all standby trades will be charged to the Contractor when such corrective measures are required. 2.6.2 The Contractor shall not cause any hindrance or delay to other contractors on the Project. In addition to and without in any way limiting the Contractor’s indemnification and other obligations under Article 8 of this Contract, the Contractor shall be solely responsible and shall indemnify and hold harmless the Owner, the City, all other Additional Insureds, and the Other Interested Parties, from all claims, including costs and reasonable attorneys’ fees, related to any and all damages sustained by any other contractor having or who shall hereafter have a contract with the Owner for the performance of work upon the Work Site or the Project due to any act or omission of the Contractor including, without limitation, costs incurred due to the Contractor’s failure to coordinate work with other contractors or due to delays caused to other contractors by the Contractor. The Contractor agrees to reimburse each such other contractor for all such damages. In addition to the foregoing, the Owner’s Representative and the Owner shall have the right, after three (3) days' written Notice to the Contractor, to provide any such labor, additional labor, overtime labor and Materials and Equipment necessary to remedy such hindrance or delay to each such other contractor’s work, and the Owner may, in its sole discretion, in addition to any other remedy it may have under this Contract, or at law or equity, deduct the costs thereof from any moneys then due or thereafter to become due to the Contractor, or to require the Contractor to pay for such costs on demand. In the event the Owner intends to extend any such other contractor’s time to complete that contractor’s work due to delays caused by the Contracto...
AutoNDA by SimpleDocs
DELAYS AND EXTENSIONS OF TIME. 2.1 If the Design-Builder is delayed at any time in the commencement or progress of the Work by an act or neglect of the Owner or of a consultant or separate contractor employed by the Owner; or by changes ordered in the Work by the Owner; or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Design-Builder’s control; or by delay authorized by the Owner pending mediation and binding dispute resolution or by other causes that the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine.
DELAYS AND EXTENSIONS OF TIME. 18.1 The Contractor agrees to prosecute the work continuously and diligently and no charges or claims for damages shall be made by it for any delays or hindrances from any cause whatsoever during the progress of any portion of the work specified in this Contract. 18.2 Time extensions will be granted only for excusable delays that arise from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the County in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the County, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of either the Contractor or the subcontractors or suppliers.
DELAYS AND EXTENSIONS OF TIME. (a) If the Prime Contractor is delayed at any time in the progress of the Work by an act or neglect of the Owner or Architect/Engineer, or of an employee of either, or of a separate contractor employed by the Owner, or by changes ordered in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Prime Contractor’s control, or by delay authorized by the Owner pending a claim, or by other causes which the Architect/Engineer determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Architect/Engineer and Owner may determine. (b) Claims relating to Contract Time and time extensions shall be made in accordance with the applicable provisions of Paragraph 4.3.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!