Meter Installation. (a) Unless this requirement is waived by SunWater, a Meter acceptable to SunWater must be acquired and installed, at the cost of the Customer, within the Customer’s Nominated Works or SunWater Works by: (i) SunWater; or (ii) if requested by ▇▇▇▇▇▇▇▇, by the Customer. (b) Any party installing a Meter shall install the same correctly in accordance with the approval under clause 10.4. (c) SunWater’s right under subclause (a) includes the right to require the replacement or upgrade of a Meter already installed where such replacement or upgrading is necessary in the reasonable opinion of SunWater but at the cost of SunWater or, where the Customer has breached clause 11.2, the Customer.
Appears in 2 contracts
Sources: Standard Supply Contract, Standard Contract Resource Operations Licence
Meter Installation. (a) Unless this requirement is waived by SunWater, a Meter acceptable to SunWater must be acquired and installed, installed at the cost of the Customer, within the Customer’s Nominated Works or SunWater Works byWorks
(b) The Customer may:
(i) SunWaterinstall the Meter itself; or
(ii) if requested by ▇▇▇▇▇▇▇▇, by arrange for a third party to install the CustomerMeter.
(bc) Any party installing a Meter shall install the same correctly in accordance with the approval under clause 10.4.
(cd) SunWater’s right under subclause (a) includes the right to require the replacement or upgrade of a Meter already installed where such replacement or upgrading is necessary in the reasonable opinion of SunWater but at the cost of SunWater or, where the Customer has breached clause 11.2, the Customer.
Appears in 1 contract
Sources: Bulk Water Supply Contract
Meter Installation. (a) Unless this requirement is waived by SunWater, a Meter acceptable to SunWater must be acquired and installed, at the cost of the Customer, within the Customer’s Nominated Works or SunWater Works by:
(i) SunWater; or
(ii) if requested by ▇▇▇▇▇▇▇▇, by the CustomerWorks.
(b) Any party installing a Meter shall install the same correctly in accordance with the approval under clause 10.4.
(c) SunWater’s right under subclause (a) includes the right to require the replacement or upgrade of a Meter already installed where such replacement or upgrading is necessary in the reasonable opinion of SunWater but at the cost of SunWater or, where the Customer has breached clause 11.2, the Customer.
Appears in 1 contract
Sources: Bulk Water Supply Contract
Meter Installation. (a) Unless this requirement is waived by SunWater, a Meter acceptable to SunWater must be acquired and installed, at the cost of the Customer, within the Customer’s Nominated Customer Offtake Works or SunWater Distribution Works by:
(i) SunWater; or
(ii) if requested by ▇▇▇▇▇▇▇▇SunWater, by the Customer.
(b) Any party installing a Meter shall install the same correctly in accordance with the approval under clause 10.4.
(c) SunWater’s right under subclause (a) includes the right to require the replacement or upgrade of a Meter already installed where such replacement or upgrading is necessary in the reasonable opinion of SunWater but at the cost of SunWater or, where the Customer has breached clause 11.2, the Customer.
Appears in 1 contract
Sources: Standard Supply Contract