Common use of Minor Deficiencies Clause in Contracts

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and IO, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

AutoNDA by SimpleDocs

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOHRRH, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and IONHS, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IO, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOCAMH, shall, within 15 Business Days of Project Co's applicationthe Substantial Completion Notice, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the gives a Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOthe City, shall, within 15 Business Days of Project Co's ’s application, prepare a list of all Minor Deficiencies (the "a “Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOHMQ, shall, within 15 Business Days of Project Co's applicationthe Substantial Completion Notice, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and IOWGH, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOMHCP, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOSJHC, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

AutoNDA by SimpleDocs

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the gives a Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOthe Ministry, shall, within 15 Business Days of Project Co's ’s application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice or the Phase 2A Completion Notice, the Independent Certifier, in consultation with Project Co and IOWCH, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOHMQ, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and IOHMQ, shall, within 15 Business Days of Project Co's Co‟s application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the gives a Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IO, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement

Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and IOHHS, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.

Appears in 1 contract

Samples: Project Agreement