Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and NHS, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies. (b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHS's use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Services. (c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies. (d) NHS may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and NHSWGH, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHSWGH's use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) NHS WGH may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and NHSHMQ, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHSHMQ's and MAG’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Courthouse Activities and the HMQ FM Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) NHS HMQ may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to EquipmentFF&E, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and NHSIO, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHS's IO’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital MCSCS Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) NHS IO may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Procured Equipment or Existing Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and NHSHRRH, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHS's HRRH’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) NHS HRRH may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Equipment and Existing Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and NHSMHCP, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHS's MHCP’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List in relation to the Substantial Completion Notice before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are such Minor Deficiencies.
(d) NHS MHCP may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and NHSHHS, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHS's HHS’ use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) NHS HHS may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Equipment and Existing Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and NHSSJHC, shall, within 15 Business Days of Project Co's application, shall prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHS's SJHC’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List in relation to the Substantial Completion Notice before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are such Minor Deficiencies.
(d) NHS SJHC may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for the Substantial Completion Certificate, the Independent Certifier, in consultation with Project Co and NHSIO, shall, within 15 Business Days of Project Co's application, prepare a list of all Minor Deficiencies (the "Minor Deficiencies List") identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHSIO's use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital MCSCS Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) NHS IO may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Project Co Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.
Appears in 1 contract
Samples: Project Agreement
Minor Deficiencies. (a) In the event that Minor Deficiencies exist when Project Co applies for gives the Substantial Completion CertificateNotice, the Independent Certifier, in consultation with Project Co and NHSCAMH, shall, within 15 Business Days of Project Co's applicationthe Substantial Completion Notice, prepare a list of all Minor Deficiencies (the "“Minor Deficiencies List"”) identified at that time and an estimate of the cost and the time for rectifying such Minor Deficiencies.
(b) The Minor Deficiencies List will contain the schedule for the completion and rectification of the Minor Deficiencies. In determining the relevant time for rectifying Minor Deficiencies, Project Co shall schedule the completion and rectification of Minor Deficiencies so as to minimize, to the greatest extent reasonably possible, any impairment of NHS's CAMH’s use and enjoyment of the Facility or disruption of the Project Operations or the performance of the Hospital Services.
(c) The Independent Certifier must prepare the Minor Deficiencies List before the Substantial Completion Certificate is issued, but shall not withhold the Substantial Completion Certificate by reason solely that there are Minor Deficiencies.
(d) NHS CAMH may, in its sole discretion, waive any requirement for Substantial Completion, including with respect to Equipment, and the failure to meet any such requirement shall constitute a Minor Deficiency.