Monthly Progress Schedule Sample Clauses

Monthly Progress Schedule. ‌ 13 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline 14 Schedule during the D&C Period, commencing after issuance of NTP 2, until the closing for final 15 payment for the Work associated with NTP 2. The Monthly Progress Schedule must reflect 16 progress up to the closing date, forecast finish for in-progress activities and re-forecast early 17 dates for activities planned in the next update period. The Monthly Progress Schedule must 18 include the following:
AutoNDA by SimpleDocs
Monthly Progress Schedule. ‌ 4 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline 5 Schedule during the D&C Period, commencing after issuance of NTP 2, until the closing for final 6 payment for the Work associated with NTP 2. The Monthly Progress Schedule must reflect 7 progress up to the closing date, forecast finish for in-progress activities and re-forecast early 8 dates for activities planned in the next update period. The Monthly Progress Schedule must 9 include the following:
Monthly Progress Schedule. 27 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline Schedule during 28 the Work, commencing after issuance of NTP 2, until the closing for Final Payment. The Monthly Progress 29 Schedule shall reflect progress up to the closing date, forecast finish for in-progress activities and re- 30 forecast early dates for activities planned in the next update period. The Monthly Progress Schedule shall 31 include the following: 32 Actual start and finish dates for completed activities; 1 Actual start dates, percentage complete, and remaining duration for activities in progress; 2 All proposed activities, logic, and restraint date revisions required to:
Monthly Progress Schedule. The term “Monthly Progress Schedule(s)” means the updated Contract Schedule provided monthly by Contractor to Judicial Council updates to the Approved Construction Schedule consistent with the requirements of the Contract Documents.

Related to Monthly Progress Schedule

  • Monthly Progress Report ‌ 2 Developer shall provide additional, separate, filtered reports of the Project activities and Work 3 elements based on the Monthly Progress Schedule with the Monthly Progress Report, including 4 the following:

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Monthly Progress Reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.

  • Work Progress Schedule Refer to Special Conditions and Division 1 General Administration Specifications for additional schedule requirements. Unless indicated otherwise in those documents, Contractor shall submit to the ODR and the A/E its initial Work Progress Schedule for the Work in relation to the entire Project not later than twenty-one (21) days after the effective date of the Notice to Proceed. Unless otherwise indicated in the Contract Documents, the Work Progress Schedule shall be based upon a computerized Critical Path Method (CPM) with full reporting capability. This initial schedule shall indicate the dates for starting and completing the various aspects required to complete the Work, including mobilization, procurement, installation, testing, inspection, and acceptance of all the Work of the Contract. When acceptable to the Owner, the initially accepted schedule shall be the Baseline Schedule for comparison to actual conditions throughout the contract duration.

  • DISTRIBUTION OF CONTRACTOR PRICE LIST AND CONTRACT APPENDICES Contractor shall provide Authorized Users with electronic copies of the Contract, including price lists and Appendices, upon request. OGS CENTRALIZED CONTRACT MODIFICATIONS Contract Updates will be handled as provided in Appendix C – Contract Modification Procedures.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.