Monthly Updates. Contractor shall submit to the District Representative each month an up-to-date status report of the Work. The status report shall include: (a) Contractor's estimated percentage complete and remaining duration for each activity not yet complete. (b) Actual start/finish dates for activities as appropriate. (c) Identification of processing errors, if any on the previous update reports. (d) Revisions, if any, to the assumed activity durations including revisions for weather impact for any activities due to the effect of the previous update on the schedule. (e) Identification of activities that are affected by requested or proposed changes to the Work. (f) Resolution of conflict between actual Work progress and schedule logic. When out of sequence activities develop in the Contract Schedule because of actual construction progress, Contractor shall submit revision to schedule logic to conform to current status and direction. The District Representative will review the updated information and meet with Contractor each month at the Site to determine the status of the Work. If agreement cannot be reached on any issue, Contractor will use the District Representative's determination in the processing of the update. Tenant Improvement Payments pursuant to this Facilities Lease will be based on the update of the Contract Schedule. No Tenant Improvement Payments will be made without the required monthly update of the Contract Schedule.
Appears in 4 contracts
Samples: Facilities Lease, Facilities Lease, Facilities Lease
Monthly Updates. Contractor shall submit to the District Representative each month an up-to-date status report of the Work. The status report shall include:
(a) Contractor's estimated percentage complete and remaining duration for each activity not yet complete.
(b) Actual start/finish dates for activities as appropriate.
(c) Identification of processing errors, if any on the previous update reports.
(d) Revisions, if any, to the assumed activity durations including revisions for weather impact for any activities due to the effect of the previous update on the schedule.
(e) Identification of activities that are affected by requested or proposed changes to the Work.
(f) Resolution of conflict between actual Work progress and schedule logic. When out of sequence activities develop in the Contract Schedule because of actual construction progress, Contractor shall submit revision to schedule logic to conform to current status and direction. The District Representative will review the updated information and meet with Contractor each month at the Site to determine the status of the Work. If agreement cannot be reached on any issue, Contractor will use the District Representative's determination in the processing of the update. Tenant Improvement Payments Progress payments pursuant to this Facilities Lease will be based on the update of the Contract Schedule. No Tenant Improvement Payments progress payments will be made without the required monthly update of the Contract Schedule.
Appears in 2 contracts
Samples: Facilities Lease, Facilities Lease
Monthly Updates. Contractor shall submit to the District Representative each month an up-to-date status report of the Work. The status report shall include:
(a) Contractor's ’s estimated percentage complete and remaining duration for each activity not yet complete.
(b) Actual start/finish dates for activities as appropriate.
(c) Identification of processing errors, if any on the previous update reports.
(d) Revisions, if any, to the assumed activity durations including revisions for weather impact for any activities due to the effect of the previous update on the schedule.
(e) Identification of activities that are affected by requested or proposed changes to the Work.
(f) Resolution of conflict between actual Work work progress and schedule logic. When out of sequence activities develop in the Contract Schedule because of actual construction progress, Contractor shall submit revision to schedule logic to conform to current status and direction. The District Representative will review the updated information and meet with Contractor each month at the Site to determine the status of the Work. If agreement cannot be reached on any issue, Contractor will use the District Representative's ’s determination in the processing of the update. Tenant Improvement Payments Progress payments pursuant to this Facilities Lease will be based on the update of the Contract Schedule. No Tenant Improvement Payments progress payments will be made without the required monthly update of the Contract Schedule.
Appears in 1 contract
Samples: Facilities Lease