Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.2, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of Transmission Owner's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 13 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of Transmission Owner's Provider’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 7 contracts
Samples: Study Agreement, Large Generator Interconnection Agreement, Qualifying Facility Large Generator Interconnection Agreement
Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damagesdates, the provision of incentives or the procurement and construction of a portion of Transmission OwnerProvider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 6 contracts
Samples: Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
Negotiated Option. If the Interconnection Customer elects not to exercise its option under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner's ’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of the Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 6 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of Transmission OwnerProvider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.. 19
Appears in 1 contract
Samples: Interconnection Agreement
Negotiated Option. If Interconnection Customer elects not to exercise its the written option provided by Transmission Provider under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damagesdates, the provision of incentives or the procurement and construction of a portion of Transmission OwnerProvider's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 1 contract
Negotiated Option. If the Interconnection Customer elects not to exercise its option under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of the Transmission Owner's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of the Transmission Owner’s 's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of the Transmission Owner’s 's Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 1 contract
Samples: Generator Interconnection Agreement
Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damagesdates, the provision of incentives or the procurement and construction of a portion of Transmission Owner's Provider’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 1 contract
Negotiated Option. If the Interconnection Customer elects not to exercise its option under Article 5.1.25.1.3, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) 30 Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damagesdates, the provision of incentives incentives, or the procurement and construction of a portion of Transmission Owner's Provider’s Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner Provider is responsible for the design, procurement and construction of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner Provider shall assume responsibility for the design, procurement and construction of all facilities other than Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades pursuant to 5.1.1, Standard Option.
Appears in 1 contract
Samples: Generator Interconnection Agreement
Negotiated Option. If Interconnection Customer elects not to exercise its option under Article 5.1.2, Option to Build, Interconnection Customer shall so notify Transmission Provider and Transmission Owner within thirty (30) Calendar Days, and the Parties shall in good faith attempt to negotiate terms and conditions (including revision of the specified dates and liquidated damages, the provision of incentives or the procurement and construction of a portion of Transmission Owner's Interconnection Facilities and Stand Alone Network Upgrades by Interconnection Customer) pursuant to which Transmission Owner is responsible for the design, procurement and construction of Transmission Owner’s Interconnection Facilities and Network Upgrades. If the Parties are unable to reach agreement on such terms and conditions, Transmission Owner shall assume responsibility for the design, procurement and construction of Transmission Owner’s Interconnection Facilities and Network Upgrades pursuant to Article 5.1.1, Standard Option.
Appears in 1 contract