New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, the Participating Transmission Owner, and the applicable distribution provider for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month following the Construction Start Date until the Commercial Operation Date, provide to Buyer a monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (b) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 7 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, the Participating Transmission Owner, and the applicable distribution provider for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month following the Construction Start Date until the Commercial Operation Date, provide to Buyer a monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (bix) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant applies to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.geothermal Projects only]

Appears in 6 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, the Participating Transmission Owner, and the applicable distribution provider for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month following the Construction Start Date until the Commercial Operation Date, provide to Buyer a monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (b) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx Buyer in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 3 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement

New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, CAISO and the Participating Transmission Owner, and the applicable distribution provider Owner for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice written notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the calendar month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month following the Construction Start Date until the Commercial Operation Date, provide to Buyer a monthly Monthly Construction Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Monthly Progress Report shall identify the Milestones and indicate whether Seller has met or is on target to meet the Guaranteed Commercial Operation Datesuch Milestones. (b) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) calendar days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx Buyer in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 3 contracts

Samples: Power Purchase and Sale Agreement, Power Purchase and Sale Agreement, Power Purchase and Sale Agreement

New Generation Facility. [Short Term Offers from existing ERRs: Seller to delete] (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, CAISO and the Participating Transmission Owner, and the applicable distribution provider Owner for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month from the first month following the Construction Start Execution Date until the Commercial Operation Date, provide to Buyer a monthly Monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Monthly Progress Report shall identify the Milestones and indicate whether Seller has met or is on target to meet the Guaranteed Commercial Operation Datesuch Milestones. (b) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx Buyer in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 2 contracts

Samples: Power Purchase and Sale Agreement, Power Purchase and Sale Agreement

New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, the Participating Transmission Owner, and the applicable distribution provider for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month from the first month following the Construction Start Execution Date until the Commercial Operation Date, provide to Buyer a monthly Monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Monthly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. [(vii) Provide to Buyer a copy of the Final Output Report, and any updates thereafter for the time period beginning on the Effective Date and ending on the last day of the first Contract Year.] [(vii) Provide to Buyer copies of all Geothermal Reservoir Reports and any revisions thereto, for the time period beginning on the Effective Date and ending on the last day of the first Contract Year.] (b) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx Buyer in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with to secure the CAISO, the Participating Transmission Owner, interconnection and the applicable distribution provider for the Interconnection Facilities transmission arrangements required pursuant to Schedule and deliver the ProductSection 3.4(a)(i). (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month from the first month following the Construction Start Execution Date until the Commercial Operation Date, provide to Buyer a monthly Monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Monthly Progress Report shall indicate whether Seller has met or is on target to meet the Guaranteed Commercial Operation DateMilestones. (vii) applies to As-Available Products only] [The following Section 3.9(a)(vii) applies to geothermal Projects only] (b) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 1 contract

Samples: Power Purchase Agreement

AutoNDA by SimpleDocs

New Generation Facility. [Short Term Offers from existing ERRs: Seller to delete Section 3.9] (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, CAISO and the Participating Transmission Owner, and the applicable distribution provider Owner for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within fifteen (15) days after the close of each month from the first month following the Construction Start Execution Date until the Commercial Operation Date, provide to Buyer a monthly Monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Monthly Progress Report shall indicate whether Seller has met or is on target to meet the Guaranteed Commercial Operation DateMilestones. (vii) applies to geothermal Projects only] (b) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx Buyer in the design. (ii) Inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 1 contract

Samples: Power Purchase Agreement

New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design design and construct the Project. (ii) Perform perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, the Participating Transmission Owner, and the applicable distribution provider for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At at Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within within fifteen (15) days after the close of each month following the Construction Start Date until the Commercial Operation Date, provide to Buyer a monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (ix) applies to As-Available Products only] [The following Section 3.9(a)(ix) applies to geothermal Projects only] (b) Buyer shall have the right, but not the obligation, to: (i) Notify notify Seller in writing of the results of the review performed pursuant to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx Buyer in the design. (ii) Inspect inspect the Project’s construction site or on-site Seller data and information pertaining to the Project during business hours upon reasonable notice.

Appears in 1 contract

Samples: Power Purchase Agreement

New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design design and construct the Project. (ii) Perform perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, the Participating Transmission Owner, and the applicable distribution provider for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At at Buyer’s request, provide to Buyer the Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Seller shall Notify Buyer of the Construction Start Date by sending to Buyer a written Certification substantially in the form provided in Appendix IV-1 as soon as practical upon issuance of Notice to Proceed. (vii) Within within fifteen (15) days after the close of each quarter from the first quarter following the Execution Date, until the month in which the Construction Start Date has occurred, provide to Buyer a quarterly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such quarterly reports and discuss Seller’s construction progress. The quarterly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (viii) Within within fifteen (15) days after the close of each month following the Construction Start Date until the Commercial Operation Date, provide to Buyer a monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The monthly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (bix) Buyer shall have the right, but not the obligation, to: (i) Notify Seller in writing of the results of the review performed pursuant applies to Section 3.9(a)(v) within thirty (30) days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Xxxxx in the design. (ii) Inspect the Project’s construction site or onAs-site Seller data and information pertaining to the Project during business hours upon reasonable notice.Available Products only]

Appears in 1 contract

Samples: Power Purchase Agreement