New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to: (i) Design and construct the Project. (ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, the Participating Transmission Owner, and the applicable distribution provider for the Interconnection Facilities to Schedule and deliver the Product. (iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project. (iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project. (v) At Buyer’s request, provide to Buyer Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes. (vi) Within fifteen (15) days after the close of each month from the first month following the Execution Date until the Commercial Operation Date, provide to Buyer a Monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The Monthly Progress Report shall indicate whether Seller is on target to meet the Guaranteed Commercial Operation Date. (vii) Provide to Buyer a copy of the Final Output Report, and any updates thereafter for the time period beginning on the Effective Date and ending on the last day of the first Contract Year.]
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
New Generation Facility. (a) Seller, at no cost to BuyerPG&E, shall be responsible to:
(i) Design and construct the Project.
(ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, ISO and the Participating Transmission Owner, and the applicable distribution provider Owner for the Interconnection Facilities to Schedule and deliver the Seller’s Product.
(iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project.
(iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project.
(v) At Buyer’s request, provide to Buyer Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance written Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changeschanges for Buyer’s review and approval.
(vi) Within fifteen (15) days after the close of each calendar month from the first month following the Execution Date until the Commercial Operation Date, provide to Buyer a Monthly Construction Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The Monthly Progress Report Buyer shall indicate whether have the right to:
(i) Notify Seller is on target to meet in writing of the Guaranteed Commercial Operation Dateresults of the review within thirty (30) calendar days of Buyer’s receipt of all specifications for the Project, including a description of any flaws perceived by Buyer in the design.
(viiii) Provide Inspect the Project's construction site or on-site Seller data and information pertaining to Buyer a copy of the Final Output Report, and any updates thereafter for the time period beginning on the Effective Date and ending on the last day of the first Contract YearProject during business hours upon reasonable notice.]
Appears in 2 contracts
Samples: Master Power Purchase and Sale Agreement, Master Power Purchase and Sale Agreement
New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to:
(i) Design and construct the Project.
(ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with the CAISO, CAISO and the Participating Transmission Owner, and the applicable distribution provider Owner for the Interconnection Facilities to Schedule and deliver the Product.
(iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project.
(iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project.
(v) At Buyer’s request, provide to Buyer Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes.
(vi) Within fifteen (15) days after the close of each month from the first month following the Execution Date until the Commercial Operation Date, provide to Buyer a Monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The Monthly Progress Report shall identify the Milestones and indicate whether Seller has met or is on target to meet the Guaranteed Commercial Operation Datesuch Milestones.
(viib) Provide to Buyer a copy shall have the right, but not the obligation, to:
(i) Notify Seller in writing of the Final Output Report, and any updates thereafter results of the review within thirty (30) days of Buyer’s receipt of all specifications for the time period beginning on Project, including a description of any flaws perceived by Buyer in the Effective Date design.
(ii) Inspect the Project’s construction site or on-site Seller data and ending on information pertaining to the last day of the first Contract YearProject during business hours upon reasonable notice.]
Appears in 2 contracts
Samples: Power Purchase and Sale Agreement, Power Purchase and Sale Agreement
New Generation Facility. (a) Seller, at no cost to Buyer, shall be responsible to:
(i) Design and construct the Project.
(ii) Perform all studies, pay all fees, obtain all necessary approvals and execute all necessary agreements with to secure the CAISO, the Participating Transmission Owner, interconnection and the applicable distribution provider for the Interconnection Facilities transmission arrangements required pursuant to Schedule and deliver the ProductSection 3.4(a)(i).
(iii) Acquire all permits and other approvals necessary for the construction, operation, and maintenance of the Project.
(iv) Complete all environmental impact studies necessary for the construction, operation, and maintenance of the Project.
(v) At Buyer’s request, provide to Buyer Seller’s electrical specifications and design drawings pertaining to the Project for Buyer’s review prior to finalizing design of the Project and before beginning construction work based on such specifications and drawings. Seller shall provide to Buyer reasonable advance Notice of any changes in the Project and provide to Buyer specifications and design drawings of any such changes.
(vi) Within fifteen (15) days after the close of each month from the first month following the Execution Date until the Commercial Operation Date, provide to Buyer a Monthly Progress Report and agree to regularly scheduled meetings between representatives of Buyer and Seller to review such monthly reports and discuss Seller’s construction progress. The Monthly Progress Report shall indicate whether Seller has met or is on target to meet the Guaranteed Commercial Operation DateMilestones.
(vii) Provide applies to Buyer a copy of the Final Output Report, and any updates thereafter for the time period beginning on the Effective Date and ending on the last day of the first Contract Year.As-Available Products only]
Appears in 2 contracts