NEW. The ICIFs for the New Facility are as follows: The existing 2 MVA transformer shall be replaced with a 34.5 (delta) -4.16 (wye) kV, resistance grounded (3ph, 2.4kV, 24 Ohm, 100A. 10 sec), 10/12MVA transformer with an X/R ratio of 15 and an impedance of 6.5% @ 10MVA; Three (3) single phase 38 kV distribution class surge arresters; and Three (3) single phase 6 kV distribution class surge arresters. Per Section II.B below, the Connecting Transmission Owner’s Generator Lead Line is being relocated to accommodate the expansion of the landfill. Due to the line relocation, the configuration of the Interconnection Customer’s Interconnection Facilities at the PCO will be modified. (See Attachment 3, Figure 2). Specifically, 30 ft of the Generator Feeder Line (between Pole 209-1 and 209-2) will be removed, a new Pole 209 will be set and the following will be relocated to the new Pole 209: three (3) pole gang-operated load break switch (Switch 588),three (3) 38 kV surge arresters, and three (3) single phase pole mounted SMD-IA 200E fuses. In addition, the Generator Feeder Line will terminate on the load side of the insulators at the new Pole 209, as further described in Section II.B below.
Appears in 3 contracts
Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Agreement, Small Generator Interconnection Agreement
NEW. The ICIFs for the New Facility are as follows: The existing 2 MVA transformer shall be replaced with a 34.5 (delta) -4.16 (wye) kV, resistance grounded (3ph, 2.4kV, 24 Ohm, 100A. 10 sec), 10/12MVA transformer with an X/R ratio of 15 and an impedance of 6.5% @ 10MVA; Three (3) single phase 38 kV distribution class surge arresters; and Three (3) single phase 6 kV distribution class surge arresters. Per Section II.B below, the Connecting Transmission Owner’s Generator Lead Line is being relocated to accommodate the expansion of the landfill. Due to the line relocation, the configuration of the Interconnection Customer’s Interconnection Facilities at the PCO will be modified. (See Attachment 3, Figure 2). Specifically, 30 ft of the Generator Feeder Line (between Pole 209-1 and 209-2) will be removed), a new Pole 209 will be set and the following will be relocated to the new Pole 209: three (3) 3 pole gang-gang operated load break switch (Switch 588),three (3) 38 kV surge arresters588), and three (3) single phase pole mounted SMD-IA 200E fuses. In additionfuses will be removed, and the Generator Feeder Line will terminate on the load side of the insulators at the new Pole 209, as further described in Section II.B below.
Appears in 1 contract
NEW. The ICIFs for the New Facility are as follows: • The existing 2 MVA transformer shall be replaced with a 34.5 (delta) -4.16 (wye) kV, resistance grounded (3ph, 2.4kV, 24 Ohm, 100A. 10 sec), 10/12MVA transformer with an X/R ratio of 15 and an impedance of 6.5% @ 10MVA; • Three (3) single phase 38 kV distribution class surge arresters; and • Three (3) single phase 6 kV distribution class surge arresters. Per Section II.B below, the Connecting Transmission Owner’s Generator Lead Line is being relocated to accommodate the expansion of the landfill. Due to the line relocation, the configuration of the Interconnection Customer’s Interconnection Facilities at the PCO will be modified. (See Attachment 3, Figure 2). Specifically, 30 ft of the Generator Feeder Line (between Pole 209-1 and 209-2) will be removed, a new Pole 209 will be set and the following will be relocated to the new Pole 209: three (3) pole gang-operated load break switch (Switch 588),three (3) 38 kV surge arresters, and three (3) single phase pole mounted SMD-IA 200E fuses. In addition, the Generator Feeder Line will terminate on the load side of the insulators at the new Pole 209, as further described in Section II.B below.
Appears in 1 contract