NO DAMAGES FOR DELAY BY TOWN Sample Clauses

NO DAMAGES FOR DELAY BY TOWN. CONSULTANT shall not be entitled to an increase in the contract price or payment or compensation of any kind from TOWN for direct, indirect, consequential, impact or other costs, expenses or damages including but not limited to costs of acceleration or inefficiency or extended overhead, arising because of delay, disruption, interference or hindrance from any cause whatsoever, whether such delay, disruption, interference or hindrance be reasonable or unreasonable, foreseeable or unforeseeable, or avoidable or unavoidable; provided, however, that this provision shall not preclude recovery of damages by CONSULTANT for hindrances or delays due solely to fraud, bad faith or active malicious interference on the part of TOWN. Otherwise, CONSULTANT shall be entitled only to extensions of the contract time as the sole and exclusive remedy for excusable events of delay. 1.2.1 If the CONSULTANT submits a schedule or expresses an intention to complete the Services to be provided under this Agreement TASK ORDER(S) issued hereunder required by any required milestone or completion date, the TOWN shall not be liable to the CONSULTANT for any costs incurred, lost profits, extended overhead, expenses, or other damages of any kind because of delay or hindrance, regardless of whether such delay or hindrance was caused by the TOWN or its agents, should CONSULTANT be unable to complete the work before such milestone or completion date as is described within the schedule. 1.2.2 On any particular TASK ORDER the TOWN shall have the right to include a provision for liquidated damages as a result of any delay.
AutoNDA by SimpleDocs

Related to NO DAMAGES FOR DELAY BY TOWN

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.

  • Force Majeure, Notice of Delay, and No Damages for Delay The Contractor will not be responsible for delay resulting from its failure to perform if neither the fault nor the negligence of the Contractor or its employees or agents contributed to the delay and the delay is due directly to acts of God, wars, acts of public enemies, strikes, fires, floods, or other similar cause wholly beyond the Contractor’s control, or for any of the foregoing that affect subcontractors or suppliers if no alternate source of supply is available to the Contractor. In case of any delay the Contractor believes is excusable, the Contractor will notify the Department or Customer in writing of the delay or potential delay and describe the cause of the delay either (1) within 10 days after the cause that creates or will create the delay first arose, if the Contractor could reasonably foresee that a delay could occur as a result, or (2) if delay is not reasonably foreseeable, within five days after the date the Contractor first had reason to believe that a delay could result. The foregoing will constitute the Contractor’s sole remedy or excuse with respect to delay. Providing notice in strict accordance with this paragraph is a condition precedent to such remedy. No claim for damages will be asserted by the Contractor. The Contractor will not be entitled to an increase in the Contract price or payment of any kind from the Department or Customer for direct, indirect, consequential, impact or other costs, expenses or damages, including but not limited to costs of acceleration or inefficiency, arising because of delay, disruption, interference, or hindrance from any cause whatsoever. If performance is suspended or delayed, in whole or in part, due to any of the causes described in this paragraph, after the causes have ceased to exist the Contractor will perform at no increased cost, unless the Department or Customer determines, in its sole discretion, that the delay will significantly impair the value of the Contract to the State of Florida or to Customers, in which case the Department or Customer may (1) accept allocated performance or deliveries from the Contractor, provided that the Contractor grants preferential treatment to Customers with respect to commodities or contractual services subjected to allocation, or (2) purchase from other sources (without recourse to and by the Contractor for the related costs and expenses) to replace all or part of the commodity or contractual services that are the subject of the delay, which purchases may be deducted from the Contract quantity, or (3) terminate the Contract in whole or in part.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!