No Early Completion. Contractor shall not submit a schedule showing early completion without indicating float time through the date set for Project completion by Owner. Contractor’s schedule shall account for all days past early completion as float which belongs to the Project. Usage of float shall not entitle Contractor to any delay claim or damages due to delay.
Appears in 4 contracts
Samples: Construction Contract, Bid Documents, Proposition 39 Energy Conservation and Energy Efficiency Services Agreement
No Early Completion. Contractor Design-Builder shall not submit a schedule Baseline Schedule showing early completion without indicating float time through the date set for Project completion by Owner. ContractorDesign-Builder’s schedule shall account for all days past early completion as float which belongs to the Project. Usage of float shall not entitle Contractor Design-Builder to any delay claim or damages due to delay.
Appears in 1 contract
Samples: Design Build Agreement