Non-Reimbursable Costs. 5.7.1 The following shall not be deemed as Cost of the Work: 5.7.1.1 Compensation for Design-Builder’s personnel stationed at Design-Builder’s principal or branch offices, except as provided for in Sections 5.5. 5.7.1.2 Overhead and general expenses, except as provided for in Section 5.5, or which may be recoverable for changes to the Work. 5.7.1.3 The cost of Design-Builder’s capital used in the performance of the Work. 5.7.1.4 Any costs that would cause the Guaranteed Maximum Price, as adjusted in accordance with the Contract Documents, to be exceeded.
Appears in 5 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Non-Reimbursable Costs. 5.7.1 A. The following shall not be deemed as Cost of the Work:
5.7.1.1 1. Compensation for Design-Builder’s personnel stationed at Design-Builder’s principal or branch offices, except as provided for in Sections 5.56.5.
5.7.1.2 2. Overhead and general expenses, except as provided for in Section 5.56.5, or which may be recoverable for changes to the Work.
5.7.1.3 3. The cost of Design-Builder’s capital used in the performance of the Work.
5.7.1.4 4. Any costs that would cause the Guaranteed Maximum PriceGMP, as adjusted in accordance with the Contract Documents, to be exceeded.
Appears in 1 contract
Samples: Design Build GMP Contract
Non-Reimbursable Costs. 5.7.1 The following shall not be deemed as Cost of the Work:
5.7.1.1 Compensation for Design-Builder’s personnel stationed at Design-Builder’s principal or branch offices, except as provided for in Sections 5.5.
. 5.7.1.2 Overhead and general expenses, except as provided for in Section 5.5, or which may be recoverable for changes to the Work.
5.7.1.3 The cost of Design-Builder’s capital used in the performance of the Work.
5.7.1.4 Any costs that would cause the Guaranteed Maximum Price, as adjusted in accordance with the Contract Documents, to be exceeded.which
Appears in 1 contract
Samples: Design Build Contract