Not Shown or Indicated Sample Clauses

Not Shown or Indicated. 11.3.2.1 If an Underground Facility is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as defined in this Agreement), identify Owner of such Underground Facility and give written notice to that Owner and to Owner and Architect. The Architect will promptly review the Underground Facility and determine the extent, if any, to which a change is required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. During such time, Contractor shall be responsible for the safety and protection of such Underground Facility. 11.3.2.2 If Architect concludes that a change in the Contract Documents is required, the appropriate documentation will be issued to reflect and document such consequences. An equitable adjustment shall be made in the Contract Price or Contract Times, or both, to the extent that they are attributable to the existence or location of any Underground Facility that was not shown or indicated or not shown or indicated with reasonable accuracy in the Contract Documents and that Contractor did not know of and could not reasonably have been expected to be aware of or to have anticipated. If Owner and Contractor are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment in Contract Price or Contract Times, Owner or Contractor may make a Claim therefore as provided in this Agreement.
Not Shown or Indicated. If an Underground Facility which conflicts with the Work is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.17.A), identify the owner of such Underground Facility and give notice to that owner and to City. City will review the discovered Underground Facility and determine the extent, if any, to which a change may be required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. Contractor shall be responsible for the safety and protection of such discovered Underground Facility.
Not Shown or Indicated. 1. If an Underground Facility which conflicts with the Work is uncovered or revealed at or contiguous to the Site which was not shown or indicated, or not shown or indicated with reasonable accuracy in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by Paragraph 6.17.A), identify the owner of such Underground Facility and give notice to that owner and to City. City will review the discovered Underground Facility and determine the extent, if any, to which a change may be required in the Contract Documents to reflect and document the consequences of the existence or location of the Underground Facility. Contractor shall be responsible for the safety and protection of such discovered Underground Facility. 2. If City concludes that a change in the Contract Documents is required, a Change Order may be issued to reflect and document such consequences. 3. Verification of existing utilities, structures, and service lines shall include notification of all utility companies a minimum of 48 hours in advance of construction including exploratory excavation if necessary.
Not Shown or Indicated. If an Underground Facility is uncovered or revealed at or contiguous to the site which was not shown or indicated in the Contract Documents, Contractor shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby or performing any Work in connection therewith (except in an emergency as required by paragraph 6.29), identify the owner of such Underground Facility and give written notice to that owner and to the Town. Contractor shall be responsible for the safety and protection of such Underground Facility as provided in these General Conditions. Contractor shall be allowed an increase in the Contract Price or an extension of the Contract Times, or both, to the extent that they are attributable to the existence of any Underground Facility that was not shown or indicated in the Contract Documents and that Contractor did not know of and could not reasonably have been expected to be aware of or to have anticipated. If the Town and Contractor are unable to agree on entitlement to or the amount or length of any such adjustment in Contract Price or Contract Times, Contractor may make a claim therefor as provided in Articles 10 or 11. However, the Town, Project Manager and Project Manager's Consultants shall not be liable to Contractor for any claims, costs, losses or damages incurred or sustained by Contractor on or in connection with any other project or anticipated project.