Common use of Notice and Report of Project Completion Clause in Contracts

Notice and Report of Project Completion. When Contractor believes that it has achieved Project Completion, it shall deliver to Owner a written notice thereof (the "Notice of Project Completion"). The Notice of Project Completion shall contain a report in a form acceptable to Owner and with sufficient detail to enable Owner to determine the achievement by Contractor of the Punch List items and such other information as Owner may require to determine whether Project Completion has been achieved.

Appears in 3 contracts

Samples: Agreement (Aes Ironwood LLC), Agreement (Aes Ironwood LLC), Agreement (Aes Ironwood LLC)

AutoNDA by SimpleDocs

Notice and Report of Project Completion. When Contractor believes that it has achieved Project Completion, it shall deliver to Owner Client a written notice thereof (the "Notice of Project Completion"). The Notice of Project Completion shall contain a report in a form acceptable to Owner report, including the results of the completed Performance Test and with sufficient detail to enable Owner to determine the achievement by Contractor of the Punch List items and such other information as Owner may require Client to determine whether Project Completion has been achieved.

Appears in 2 contracts

Samples: Construction Agreement (BioFuel Energy Corp.), Construction Agreement (BioFuel Energy Corp.)

Notice and Report of Project Completion. When Contractor believes that it has achieved Project Completion, it shall deliver to Owner a written notice thereof (the "Notice of Project Completion"). The Notice of Project Completion shall contain a report in a form acceptable to Owner and with sufficient detail to enable Owner to determine the achievement by Contractor of all Work to be performed under the Contract, including the Punch List items items, and such other information as that Owner may reasonably require to determine whether Project Completion has been achieved.

Appears in 1 contract

Samples: Contract

AutoNDA by SimpleDocs

Notice and Report of Project Completion. When Contractor believes that it has achieved Project Completion, it shall deliver to Owner and the Independent Engineer a written notice thereof (the "Notice of Project CompletionNOTICE OF PROJECT COMPLETION"). The Notice of Project Completion shall contain a report in a form acceptable mutually and reasonably agreeable to Contractor and Owner (with the written concurrence of the Independent Engineer) and with sufficient detail to enable Owner and the Independent Engineer to determine the achievement by Contractor of the Punch List items and such other information as Owner or the Independent Engineer may require to determine whether Project Completion has been achieved.

Appears in 1 contract

Samples: And Construction Services (Aes Red Oak LLC)