Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtu, that Contractor anticipates it will need for each applicable Subproject in accordance with the following Commissioning Feed Gas forward plan:
Appears in 7 contracts
Samples: Escrow Agreement (Sabine Pass Liquefaction, LLC), Escrow Agreement (Sabine Pass Liquefaction, LLC), Escrow Agreement (Cheniere Energy Partners LP Holdings, LLC)
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable Subproject 3 in accordance with the following Commissioning Feed Gas forward plan:
Appears in 4 contracts
Samples: Procurement and Construction Agreement (Cheniere Corpus Christi Holdings, LLC), Procurement and Construction Agreement (Cheniere Energy Inc), Procurement and Construction Agreement (Corpus Christi Pipeline GP, LLC)
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable the Subproject in accordance with the following Commissioning Feed Gas forward plan:
Appears in 2 contracts
Samples: Escrow Agreement (Cheniere Energy Partners, L.P.), Escrow Agreement (Cheniere Energy Partners, L.P.)
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable Subproject in accordance with the following Commissioning Feed Gas forward plan:
Appears in 1 contract
Samples: Engineering, Procurement and Construction Agreement (Cheniere Energy Inc)
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable Subproject 6(a) in accordance with the following Commissioning Feed Gas forward plan:
Appears in 1 contract
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable Subproject the Project in accordance with the following Commissioning Feed Gas forward plan:
Appears in 1 contract
Samples: Procurement and Construction Agreement (Tellurian Inc. /De/)
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable Subproject Project 3 in accordance with the following Commissioning Feed Gas forward plan:
Appears in 1 contract
Samples: Procurement and Construction Agreement (Tellurian Inc. /De/)
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable Subproject Project 5 in accordance with the following Commissioning Feed Gas forward plan:
Appears in 1 contract
Notice of Delivery of Feed Gas for Commissioning, Start Up and Performance Testing. Contractor shall provide to Owner a schedule of the quantities of Commissioning Feed Gas, in MMbtuMMBtu, that Contractor anticipates it will need for each applicable Subproject Project 4 in accordance with the following Commissioning Feed Gas forward plan:
Appears in 1 contract
Samples: Procurement and Construction Agreement (Tellurian Inc. /De/)