Notice of Force Majeure. Event If a Force Majeure Event occurs, the party affected by the Force Majeure Event must: Promptly (when reasonably possible to do so) give the other party notice of the Force Majeure Event and an estimate of the non-performance and delay; take all reasonable steps to overcome the effects of the Force Majeure Event; and resume compliance as soon as practicable after the Force Majeure Event no longer affects it.
Appears in 14 contracts
Samples: Products Agreement, Products Agreement, Products Agreement
Notice of Force Majeure. Event If a Force Majeure Event occurs, the party affected by the Force Majeure Event must: Promptly (when reasonably possible to do so) promptly give the other party notice of the Force Majeure Event and an estimate of the non-performance and delay; take all reasonable steps to overcome the effects of the Force Majeure Event; and resume compliance as soon as practicable after the Force Majeure Event no longer affects it.
Appears in 7 contracts
Samples: Products Agreement, Products Agreement, Products Agreement
Notice of Force Majeure. Event If a Force Majeure Event occurs, the party affected by the Force Majeure Event must: Promptly :
(when reasonably possible to do soa) promptly give the other party notice of the Force Majeure Event and an estimate of the non-performance and delay; ;
(b) take all reasonable steps to overcome the effects of the Force Majeure Event; and and
(c) resume compliance as soon as practicable after the Force Majeure Event no longer affects it.
Appears in 6 contracts
Samples: Products Agreement, Products Agreement, Products Agreement
Notice of Force Majeure. Event If a Force Majeure Event occurs, the party affected by the Force Majeure Event must: :
(a) Promptly (when reasonably possible to do so) give the other party notice of the Force Majeure Event and an estimate of the non-performance and delay; ;
(b) take all reasonable steps to overcome the effects of the Force Majeure Event; and and
(c) resume compliance as soon as practicable after the Force Majeure Event no longer affects it.
Appears in 3 contracts
Samples: Products Agreement, Interlocal Agreement, Products Agreement
Notice of Force Majeure. Event If a Force Majeure Event occurs, the party affected by the Force Majeure Event must: Promptly promptly (when reasonably possible to do so) give the other party notice of the Force Majeure Event and an estimate of the non-performance and delay; take all reasonable steps to overcome the effects of the Force Majeure Event; and resume compliance as soon as practicable after the Force Majeure Event no longer affects it.
Appears in 2 contracts
Samples: Products Agreement, Products Agreement
Notice of Force Majeure. Event If a Force Majeure Event occurs, the party affected by the Force Majeure Event must: Promptly must:
(when reasonably possible to do soa) promptly give the other party notice of the Force Majeure Event and an estimate of the non-performance and delay; ;
(b) take all reasonable steps to overcome the effects of the Force Majeure Event; and and
(c) resume compliance as soon as practicable after the Force Majeure Event no longer affects it.
Appears in 1 contract
Samples: Products Agreement