Effect of Force Majeure Sample Clauses

Effect of Force Majeure. If either Party is rendered wholly or partially unable to perform its obligations under this Agreement because of a Force Majeure Act, that Party shall be excused from whatever performance is affected by the Force Majeure Act to the extent so affected, provided that: a) Within five (5) Business Days after the occurrence of the inability to perform due to a Force Majeure Act, the Affected Party provides a written notice to the other Party of the particulars of the occurrence, including an estimation of its expected duration and probable impact on the performance of its obligations hereunder, and continues to furnish periodic reports with respect thereto, every seven (7) days, during the period of Force Majeure, b) The Affected Party shall use all reasonable efforts to continue to perform its obligations hereunder and to correct or cure as soon as possible the Force Majeure Act, c) The suspension of performance shall be of no greater scope and no longer duration than is reasonably necessitated by the Force Majeure Act, d) The Affected Party shall provide the other Party with prompt notice of the cessation of the Force Majeure Act giving rise to the excuse from performance and shall thereupon resume normal performance of obligations under this Agreement with utmost promptitude, e) The non-performance of any obligation of either Party that was required to be performed prior to the occurrence of a Force Majeure Act shall not be excused as a result of such subsequent Force Majeure Act, f) The occurrence of a Force Majeure Act shall not relieve either Party from its obligations to make any payment hereunder for performance rendered prior to the occurrence of Force Majeure Act or for partial performance hereunder during period of subsistence Force Majeure Act; and g) The Force Majeure Act, shall not relieve either Party from its obligation to comply with Applicable Laws. The Affected Party shall exercise all reasonable efforts to mitigate or limit damages to the other Party.
AutoNDA by SimpleDocs
Effect of Force Majeure. A Party shall not be considered to be in default in the performance of its obligations to the extent that the failure or delay of its performance is due to a Force Majeure event, and the non-affected Party shall be excused from its corresponding performance obligations for the period of the affected Party’s failure or delay of performance. The burden of proof for establishing the existence and consequences of an event of Force Majeure lies with the Party initiating the claim.
Effect of Force Majeure. Other than as provided in Section 21.5 (Guaranteed Project Milestones Including Commercial Operations) and Section 21.6 (Termination for Force Majeure), neither Party shall be responsible or liable for any delays or failures in its performance under this Agreement as and to the extent (i) such delays or failures are substantially caused by conditions or events of Force Majeure, and (ii) the conditions of Section 21.4 (Satisfaction of Certain Conditions) are satisfied.
Effect of Force Majeure. In the event either party is rendered unable by force majeure to carry out any of its obligations under this Contract, in whole or in part, then the obligations of that party, to the extent affected by the force majeure shall be suspended during the continuance of the inability, provided however, that due diligence is exercised to resume performance at the earliest practical time. As soon as reasonably possible after the occurrence of the force majeure relied upon to suspend performance, the party whose contractual obligations are affected thereby shall give notice and full particulars of the force majeure to the other party. The cause, as far as possible, shall be remedied with all reasonable diligence. The term "force majeure" includes acts of God, strikes, lockouts or other industrial disturbances, acts of the public enemy, orders of the government of the United States or the State of Texas or any civil or military authority, insurrections, riots, epidemics, landslides, lightning, earthquakes, fires, hurricanes, storms, floods, washouts, droughts, arrests, restraints of government and civil disturbances, explosions, breakage, or accidents to equipment, pipelines, or canals, partial or complete failure of water supply, and any other inability’s of either party, whether similar to those enumerated or otherwise, that are not within the control of the party claiming the inability and that could not have been avoided by the exercise of due diligence and care. It is understood and agreed that the settlement or strikes and lockouts shall be entirely within the discretion of the party having the difficulty and that the requirement that any force majeure be remedied with all reasonable dispatch shall not require the settlement of strikes and lockouts by acceding to the demands of the opposing party if the settlement is unfavorable to it in the judgment of the party having the difficulty.
Effect of Force Majeure. If either Party is unable, wholly or in part, by Force Majeure to perform obligations under this Agreement, such performance shall be excused and suspended so long as the circumstances that give rise to such inability exist or would exist if the Party claiming the Force Majeure used commercially reasonable efforts to cure such circumstances, but for no longer period. The Party whose performance is affected shall give prompt notice thereof; such notice may be given orally or in writing but, if given orally, it shall be promptly confirmed in writing, providing details regarding the nature, extent and expected duration of the Force Majeure, its anticipated effect on the ability of such party to perform obligations under this Agreement, and the estimated duration of any interruption in service or other adverse effects resulting from such Force Majeure, and shall be updated or supplemented to keep the other Party advised of the effect and remedial measures being undertaken to overcome the Force Majeure. Such inability shall be promptly corrected to the extent it may be corrected through the exercise of commercially reasonable due diligence. Neither Party shall be liable for any losses or damages arising out of a suspension of performance that occurs because of Force Majeure.
Effect of Force Majeure. No Party shall be liable for any loss or damage that arises directly or indirectly through or as a result of any delay in the fulfilment of or failure to fulfil its obligations in whole or in part (other than the payment of money as may be owed by a Party) under this Agreement where the delay or failure is due to Force Majeure. The obligations of the Party affected by the event of Force Majeure (the "AFFECTED PARTY") shall be suspended, to the extent that those obligations are affected by the event of Force Majeure, from the date the Affected Party first gives notice in respect of that event of Force Majeure until cessation of that event of Force Majeure (or the consequences thereof).
Effect of Force Majeure. A Party shall not be considered to be in default in the performance of its obligations to the extent that the failure or delay of its performance is due to a Force Majeure event, and the non-affected Party shall be excused from its corresponding performance obligations for the period of the affected Party’s failure or delay of performance; provided that, with respect to Provider’s commitment to provide Showing Quantity under this Agreement, Provider’s failure or delay of its performance of such obligation shall only be excused in accordance with this Article Nine to the extent the Force Majeure event in question affects the Project. The burden of proof for establishing the existence and consequences of an event of Force Majeure lies with the Party initiating the claim.
AutoNDA by SimpleDocs
Effect of Force Majeure. Except for the obligation of a party to make payments required hereunder, the parties shall be excused from performing any of their respective obligations under this Agreement and shall not be liable in damages or otherwise on account of the non-performance of any such obligation, for so long as and to the extent that such party is unable to perform such obligation as a result of any Force Majeure Event.
Effect of Force Majeure. If either party is rendered unable by an event of Force Majeure to carry out, in whole or part, its obligations under this Agreement, then, for only the pendency of such Force Majeure, the party affected by the event (other than the obligation to make payments then due or becoming due with respect to performance which occurred prior to the event) shall be temporarily relieved of its obligations hereunder insofar as they are affected by Force Majeure but for no longer period. The party affected by an event of Force Majeure shall provide the other party with written notice setting forth the full details thereof within two (2) Business Days after the occurrence of such event and shall take all reasonable measures to mitigate or minimize the effects of such event of Force Majeure.
Effect of Force Majeure. Each Critical Milestone and the Expected Initial Delivery Date shall be extended on a day-for-day basis without the payment of liquidated damages, not exceeding an aggregate extension of 365 days, to the extent that such Critical Milestone or Expected Initial Delivery Date is delayed as a result of a Force Majeure Event invoked by the Seller in accordance with Section 3.11.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!