Notices and Claims. All notices and Claims shall be made in writing as required by the Agreement. 13.4.1 Any notice of a Claim of the Contractor against KCDA or the Client and any Claim of the Contractor, whether under the Agreement or otherwise, must be made pursuant to and in strict accordance with the applicable provisions of the Contract Documents. Failure to comply with these requirements shall constitute waiver of the Claim. No act, omission, or knowledge, actual or constructive, of KCDA, the Client, or the A/E shall in any way be deemed to be a waiver of the requirement for timely written notice and a timely written Claim unless KCDA, the Client, and the Contractor sign an explicit, unequivocal written waiver approved by KCDA and the Client's Board of Directors. 13.4.2 The fact that KCDA, the Client, and the Contractor may continue to discuss or negotiate a Claim that has or may have been defective or untimely under the Contract shall not constitute waiver of the provisions of the Contract Documents unless KCDA, the Client, and Contractor sign an explicit, unequivocal written waiver approved by the Client's board of directors. 13.4.3 The Contractor expressly acknowledges and agrees that the Contractor's failure to timely submit required notices or timely submit Claims has a substantial impact upon and prejudices KCDA and the Client, including but not limited to the inability to fully investigate or verify the Claim, mitigate damages, choose alternative options, adjust the budget, delete or modify the impacted Work, and/or monitor time, cost and quantities. For these and other reasons, the parties stipulate that KCDA and the Client are prejudiced by the Contractor's failure to timely submit notices or Claims as required by the Contract Documents.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Notices and Claims. All notices and Claims shall be made in writing as required by the Agreement.
13.4.1 Any notice of a Claim of the Contractor against KCDA or the Client and any Claim of the Contractor, whether under the Agreement or otherwise, must be made pursuant to and in strict accordance with the applicable provisions of the Contract Documents. Failure to comply with these requirements shall constitute waiver of the Claim. No act, omission, or knowledge, actual or constructive, of KCDA, the Client, or the A/E shall in any way be deemed to be a waiver of the requirement for timely written notice and a timely written Claim unless KCDA, the Client, and the Contractor sign an explicit, unequivocal written waiver approved by KCDA and the Client's ’s Board of Directors.
13.4.2 The fact that KCDA, the Client, and the Contractor may continue to discuss or negotiate a Claim that has or may have been defective or untimely under the Contract shall not constitute waiver of the provisions of the Contract Documents unless KCDA, the Client, and Contractor sign an explicit, unequivocal written waiver approved by the Client's ’s board of directors.
13.4.3 The Contractor expressly acknowledges and agrees that the Contractor's ’s failure to timely submit required notices or timely submit Claims has a substantial impact upon and prejudices KCDA and the Client, including but not limited to the inability to fully investigate or verify the Claim, mitigate damages, choose alternative options, adjust the budget, delete or modify the impacted Work, and/or monitor time, cost and quantities. For these and other reasons, the parties stipulate that KCDA and the Client are prejudiced by the Contractor's ’s failure to timely submit notices or Claims as required by the Contract Documents.