Common use of Notices of Other Claims Clause in Contracts

Notices of Other Claims. Except for claims for: an extension of time under clause 10.6; payment under clause 12.2 of the original Contract Price specified in the Contract Particulars; or a Variation instructed in accordance with clause 11.2 or to which clause 16.1 applies, the Contractor must give the Contract Administrator the notices required by clause 16.3 if it wishes to make a Claim against the Commonwealth in respect of any direction by the Contract Administrator or any other fact, matter or thing (including a breach of the Contract by the Commonwealth) under, arising out of or in connection with the Contractor's Activities, the Works or the Contract, including anything in respect of which: it is otherwise given an express entitlement under the Contract; or the Contract expressly provides that: amounts are to be added to the Contract Price; or otherwise, the Contract Price will be increased or adjusted, as determined by the Contract Administrator.

Appears in 8 contracts

Samples: Formal Agreement, Formal Agreement, Formal Agreement

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.