Notification procedure for Force Majeure. (a) The affected Party shall notify the other Party of a Force Majeure event within seven (7) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure it shall give the claiming Party written notice of such dispute within thirty (30) days of such notice. Such dispute shall be dealt with in accordance with the dispute resolution mechanism in accordance with Clause (b) Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall within seven (7) days hereof notify the other Party in writing of the cessation and the Parties shall as soon as practicable thereafter continue performance of all obligations under this Agreement.
Appears in 6 contracts
Samples: Master Service Agreement, Master Services Agreement and Service Level Agreement, Master Services Agreement
Notification procedure for Force Majeure. (a) a. The affected Party shall notify the other Party of a Force Majeure event within seven (7) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure it shall give the claiming Party written notice of such dispute within thirty (30) days of such notice. Such dispute shall be dealt with in accordance with the dispute resolution mechanism in accordance with Clause
(b) b. Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall within seven (7) days hereof notify the other Party in writing of the cessation and the Parties shall as soon as practicable thereafter continue performance of all obligations under this Agreement.
Appears in 2 contracts
Samples: Master Service Agreement, Master Service Agreement (Msa) and Service Level Agreement (Sla)
Notification procedure for Force Majeure. (a) The affected Party shall notify the other Party of a Force Majeure event within seven (7) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure Majeure, it shall give the claiming Party written notice of such dispute within thirty (30) days of such notice. Such dispute shall be dealt with in accordance with the dispute resolution mechanism Dispute Resolution Mechanism in accordance with Clauseto Clause 9.
(b) Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall shall, within seven (7) days days, hereof notify the other Party in writing of the cessation and the Parties shall shall, as soon as practicable thereafter thereafter, continue performance of all obligations under this Agreement.
Appears in 1 contract
Samples: Memorandum of Understanding
Notification procedure for Force Majeure. (a) i The affected Party shall notify the other Party of a Force Majeure event Event within seven (7) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure it shall give the claiming Party written notice of such dispute within thirty Seven (307) days of such notice. Such dispute shall be dealt with in accordance with the dispute resolution mechanism in accordance with Clause
(b) clause. ii Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall within seven (7) days hereof thereof notify the other Party in writing of the cessation and the Parties shall as soon as practicable thereafter continue performance of all obligations under this Agreement.
Appears in 1 contract
Notification procedure for Force Majeure. (a) a. The affected Party shall notify the other Party of a Force Majeure event within seven fifteen (715) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure it shall give the claiming Party written notice of such dispute within thirty (30) days of such notice. Such dispute shall be dealt with in accordance with the dispute resolution mechanism in accordance with Clause
(b) b. Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall within seven fifteen (715) days hereof notify the other Party in writing of the cessation and the Parties shall as soon as practicable thereafter continue performance of all obligations under this Agreement.
Appears in 1 contract
Samples: Master Service Agreement
Notification procedure for Force Majeure. (a) The affected Party shall notify the other Party of a Force Majeure event Event within seven (7) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure it shall give the claiming Party written notice of such dispute within thirty (307) days of such notice. Such dispute shall be dealt with in accordance with the dispute resolution mechanism in accordance with Clauseclause.
(b) Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall within seven (7) days hereof thereof notify the other Party in writing of the cessation and the Parties shall as soon as practicable thereafter continue performance of all obligations under this Agreement.
Appears in 1 contract
Samples: GST Suvidha Provider Agreement
Notification procedure for Force Majeure. (a) a. The affected Party shall notify the other Party of a Force Majeure event within seven (7) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure it shall give the claiming Party written notice of such dispute within thirty (30) days of such notice. Such dispute shall be dealt with in accordance with the dispute resolution mechanism in accordance with Clauseclause 25.
(b) b. Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall within seven (7) days hereof notify the other Party in writing of the cessation and the Parties shall as soon as practicable thereafter continue performance of all obligations under this Agreement.
Appears in 1 contract
Samples: Master Service Agreement
Notification procedure for Force Majeure. (a) 17.3.1 The affected Party shall notify the other Party of a Force Majeure event within seven (7) days of occurrence of such event. If the other Party disputes the claim for relief under Force Majeure it shall give the claiming Party written notice of such dispute within thirty (30) days of such notice. Such dispute shall be dealt with in in-accordance with the dispute resolution mechanism in in-accordance with Clause.
(b) 17.3.2 Upon cessation of the situation which led the Party claiming Force Majeure, the claiming Party shall within seven (7) days hereof here of notify the other Party in writing of the cessation and the Parties shall as soon as practicable thereafter continue performance of all obligations under this AgreementRFP document.
Appears in 1 contract
Samples: Service Agreement