Common use of Obligations relating to Project Agreements Clause in Contracts

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due.

Appears in 16 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Commercial Complex without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause 5.2.4 shall not apply where the Concessionaire grants a sub-licence for a cumulative period, including any renewals thereof, not exceeding 11 (eleven) months. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.4 within a period of 60 (sixty) days from the date of receiving a notice alongwith full particulars and documents from the Concessionaire, the approval shall be deemed to have been granted to the extent such sub-licence, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement. 5.2.5 Notwithstanding anything to the contrary contained in Clause 5.2.4, the Concessionaire shall not sub–licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Commercial Complex at any time prior to the [(***)anniversary] of the Appointed Date. For the avoidance of doubt, the restriction imposed herein shall not apply to assignment under the Substitution Agreement. 5.2.6 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and the Concessionaire undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 12 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder.. from 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever.. xxx.xxxxxx.xxx Downloaded 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Commercial Complex without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause 5.2.4 shall not apply where the Concessionaire grants a sub-licence for a cumulative period, including any renewals thereof, not exceeding 11 (eleven) months. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.4 within a period of 60 (sixty) days from the date of receiving a notice alongwith full particulars and documents from the Concessionaire, the approval shall be deemed to have been granted to the extent such sub-licence, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement. 5.2.5 Notwithstanding anything to the contrary contained in Clause 5.2.4, the Concessionaire shall not sub–licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Commercial Complex at any time prior to the [(***)anniversary] of the Appointed Date. For the avoidance of doubt, the restriction imposed herein shall not apply to assignment under the Substitution Agreement. from 5.2.6 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. xxx.xxxxxx.xxx Downloaded 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and the Concessionaire undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 10 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire and shall respond to the request for consent no later than 30 days from the receipt of such request from the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority and / or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). Further, it is clarified that in case both the Authority and Xxxxxxx’ Representative decide to exercise their right to step-in, the Authority shall have the sole right to step into the Project Agreements. For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of the EPC Contractor and an O&M Contractor and execution of the EPC Contract and O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavor to convey its decision thereon expeditiously and no later than 30 days from the date of receipt of the proposal alongwith the draft agreement by the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 8 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 (a) It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 (b) The Concessionaire shall submit to the PMU/ Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the PMU/ Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority PMU a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the PMU/ Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the PMU / Authority. No review and / or observation of the PMU / Authority and/or and / or its failure to review and/or and / or convey its observations on any Document document shall not relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the PMU / Authority be liable for the same in any manner whatsoever. 5.2.3 (c) The Concessionaire shall not make any addition, replacement or amendments to any ensure that each of the Financing Project Agreements without contains provisions that entitle the prior written consent Authority to step into such agreement, in its sole discretion, in substitution of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and Concessionaire in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authorityof termination. For the avoidance of doubt, it is expressly agreed that in the event the Authority acknowledges does not exercise such rights of substitution within a period not exceeding 30 (thirty) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the covenant shall expressly provide for such eventuality. (d) The Concessionaire expressly agrees to include a covenant in all its Project Agreements and undertakes that it shall not unreasonably withhold its consent for restructuring or rescheduling shall, in respect of each of the Debt DueProject Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where undersuch counter party(ies) shall acknowledge and accept the covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination.

Appears in 6 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 (a) It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 (b) The Concessionaire shall submit to the PMU/ Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the PMU/ Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority PMU a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the PMU/ Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the PMU / Authority. No review and / or observation of the PMU / Authority and/or and / or its failure to review and/or and / or convey its observations on any Document document shall not relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the PMU / Authority be liable for the same in any manner whatsoever. 5.2.3 (c) The Concessionaire shall not make any addition, replacement or amendments to any ensure that each of the Financing Project Agreements without contains provisions that entitle the prior written consent Authority to step into such agreement, in its sole discretion, in substitution of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and Concessionaire in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authorityof termination. For the avoidance of doubt, it is expressly agreed that in the event the Authority acknowledges does not exercise such rights of substitution within a period not exceeding 30 (thirty) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the covenant shall expressly provide for such eventuality. (d) The Concessionaire expressly agrees to include a covenant in all its Project Agreements and undertakes that it shall not unreasonably withhold its consent for restructuring or rescheduling shall, in respect of each of the Debt DueProject Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination.

Appears in 6 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority Maha-Metro a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority Maha- Metro and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority Maha-Metro be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Maha-Metro if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMaha-Metro, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMaha- Metro. For the avoidance of doubt, the Authority Xxxx-Metro acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due.

Appears in 5 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements and/ or any other agreementagreement (other than this Agreement), and no default under any Project Agreement and/ or any other agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.3 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the 5.2.4 The Concessionaire shall be entitled to appoint the O&M Contractor for O&M of the Project, save and except for Core Clinical Services. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority. The decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and the Concessionaire undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to ensure compliance of the provisions of this Clause 5.2.4, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement and/ or under Applicable Laws. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall be entitled to appoint its Associate as the O&M Contractor for Core Clinical Services.

Appears in 5 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. The Concessionaire shall, within 7 (seven) days of receipt of comments by the Authority, make amendments to the Project Agreements and resubmit the same to the Authority for its review and comments. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due.

Appears in 4 contracts

Samples: Public Private Partnership Agreement, Public Private Partnership Agreement, Public Private Partnership Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall be allowed to sub license the use of Commercial facility, during the subsistence of this agreement. But the legal documents pertaining to this arrangement can only be executed after the completion of the area to be sub-licensed at the project site eg. registration and rent agreement, and this will be duly informed to the Authority within a period of one month from the date of execution of such agreement. Also the concessionaire will every year give a list of all the tenants along with the area and tenure of the agreement entered. Provided that the provisions of this Clause 5.2.4 shall not apply where the Concessionaire grants a sub-licence for a cumulative period, including any renewals thereof, not exceeding 11 (eleven) months. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.4 within a period of 60 (sixty) days from the date of receiving a notice along with full particulars and documents from the Concessionaire, the approval shall be deemed to have been granted to the extent such sub-licence, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement. 5.2.5 Notwithstanding anything to the contrary contained in Clause 5.2.4, the Concessionaire shall any manner create an Encumbrance on any Project Asset forming part of Commercial Complex at any time prior to the [(***)anniversary] of the Appointed Date. For the avoidance of doubt, the restriction imposed herein shall not apply to assignment under the Substitution Agreement. 5.2.6 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire will have the right for the selection or replacement of an O&M Contractor and execution of the O&M contract on its own. The selection or replacement of O&M Contractor shall be informed to the Authority by the Concessionaire. In the interest of the national security and public security Concessionaire shall ensure that O&M Contractor are cleared after due police verification.

Appears in 4 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority MOR the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority MOR shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority MOR a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of MOR to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by MOR. No review and/ or observation of the Authority and/or MOR and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority MOR be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority MOR if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMOR, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMOR. For the avoidance of doubt, the Authority MOR acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire.

Appears in 4 contracts

Samples: Construction Agreement, Construction Agreement, Construction Agreement

Obligations relating to Project Agreements. 5.2.1 It 6.3.4.1 Notwithstanding anything contained in the Agreement or any other agreement, it is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement agreements shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 6.3.4.2 The Concessionaire must comply with the provisions of the Project Agreements and documents and save as otherwise provided in the Agreement may only: (a) terminate (or otherwise agree to do so) any Project Agreement; or (b) in any respect, depart from its obligations or waive any rights under any Project Agreements, 6.3.4.3 Without prejudice to Section 6.3.2.1 and 6.3.2.2 above, the Concessionaire shall submit to the Authority FBR the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority . FBR shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days Days of the receipt of such drafts. Within 7 (seven) days Days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority FBR a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments 6.3.4.4 Notwithstanding anything to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and contrary contained in the event that any replacement or amendment is made without such consentAgreement, the Concessionaire agrees and acknowledges that selection or replacement of an EPC and O&M Contractor and execution of the EPC and O&M Contract shall not enforce such replacement or amendment nor permit enforcement thereof against be subject to the Authorityprior approval of FBR. For The decision of FBR in this context being final, conclusive and binding on the avoidance of doubtConcessionaire, and the Authority acknowledges and agrees Concessionaire undertakes that it shall not unreasonably withhold give effect to any such selection or contract without such prior approval of FBR. It is also agreed that FBR shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its consent for restructuring Contractors from any liability or rescheduling of the Debt Dueobligation under this Agreement.

Appears in 4 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority MOR the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority MOR shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority MOR a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of MOR to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by MOR. No review and/ or observation of the Authority and/or MOR and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority MOR be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority MOR if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMOR, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMOR. For the avoidance of doubt, the Authority MOR acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle MOR to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event MOR does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on MOR and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to MOR an acknowledgment and undertaking, in a form acceptable to MOR, from the counter party(ies) of each of the Project Agreements, where-under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from MOR in the event of Termination or Suspension.

Appears in 3 contracts

Samples: Construction Contract, Construction Agreement, Construction Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any addition, replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in the Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without such prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review intimation and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such draftsrecord. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire and shall respond to the request for consent no later than 30 days from the receipt of such request from the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority and/ or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the "Covenant"). Further, it is clarified that in case both the Authority and Xxxxxxx' Representative decide to exercise their right to step-in, the Authority shall have the sole right to step into the Project Agreements. For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of the EPC Contractor and an O&M Contractor and execution of the EPC Contract and O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall convey its decision thereon expeditiously and no later than 30 days from the date of receipt of the proposal along with the draft agreement by the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority Maha-Metro a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority Maha- Metro and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority Maha-Metro be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Maha-Metro if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMaha-Metro, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMaha- Metro. For the avoidance of doubt, the Authority Maha-Metro acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is 4.2.1 The Implementation Agency shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Implementation Agency in the event of Termination (the “Covenant”). The Implementation Agency expressly agreed agrees to include the Covenant in all its Project Agreements and undertakes that the Concessionaire it shall, at all timesin respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be responsible bound by the same and liable for all its obligations under this Agreement notwithstanding not to seek any relief or remedy whatsoever from the Authority in the event of Termination. 4.2.2 Notwithstanding anything to the contrary contained in the Project Agreements Agreement, the Implementation Agency agrees and acknowledges that selection or any other agreementreplacement of all Contractors and execution of all Contracts shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Implementation Agency, and no default under undertakes that it shall not give effect to any Project Agreement such selection or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days contract without prior approval of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its recordAuthority. For the avoidance of doubt, it is expressly agreed that approval of the review and comments Authority hereunder shall be limited to ensuring compliance with national security and public interest perspective, and the terms of this AgreementAuthority shall endeavour to convey its decision thereon expeditiously. It is further also agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement not be liable in any manner nor on account of grant or otherwise of such approval and that such approval or denial thereof shall the Authority be liable for the same not in any manner whatsoever. 5.2.3 The Concessionaire shall not make absolve the Implementation Agency or its Contractors from any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on under this Agreement. 4.2.3 Notwithstanding anything to the Authority, and contrary contained in the event that any replacement or amendment is made without such consentthis Agreement, the Concessionaire shall Implementing Agency agrees and acknowledge that it will not enforce assign any work to any Contractor/sub- contractor/vendor from a country which shares a land border with India unless such replacement or amendment nor permit enforcement thereof against Contractor/sub-contractor/vendor is registered with the Authoritycompetent authority. The Implementing Agency will ensure that such Contractor/sub-contractor/vendor fulfils all requirements in this regard and is eligible to be considered (where applicable, evidence of valid registration by the competent authority). The competent authority for registration will be the registration committee constituted by the Department for Promotion of Industry and Internal Trade (DPIIT), India. Political and security clearance from the Ministries of External and Home Affairs respectively will be mandatory for this purpose. For interpretation of this clause, Department of Expenditure, Ministry of Finance, GOI letter no. F.No.6/18/2019-PPD dated 23rd July 2020 or subsequent guidelines issued by the avoidance of doubt, the Authority acknowledges and agrees that it GOI shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duebe referred.

Appears in 3 contracts

Samples: Development, Operation and Maintenance Agreement, Development, Operation and Maintenance Agreement, Development, Operation and Maintenance Agreement

Obligations relating to Project Agreements. 5.2.1 (a) It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire from its obligations or liability hereunderunder this Agreement. 5.2.2 (b) The Concessionaire shall submit to the Authority the drafts copies of all Project Agreements, Agreements or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire thereto within [15 (fifteen) )] days from the date of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoevertheir execution. 5.2.3 (c) The Concessionaire shall not make any addition, replacement or amendments amendment to any of the Financing Agreements Documents without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any the financial liability or obligation on of the AuthorityAuthority under this Agreement, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for the restructuring or rescheduling of the Debt DueDue to the extent that such restructuring or rescheduling does not increase the financial liability of the Authority under this Agreement. (d) The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of termination or suspension (the Covenant). The Parties agree that in the event the Authority does not exercise such rights of substitution within a period not exceeding [90 (ninety)] days from the Hand-back Date, the Project Agreements shall be deemed to cease to be in force and effect on the Hand-back Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of termination or suspension. (e) The Concessionaire shall also procure that such Project Agreements shall also include a covenant that all disputes arising out of such Agreements shall be settled between the Concessionaire and the counter party(ies) and that the Authority or its advisors/contractors/consultants shall not be impleaded in such disputes whatsoever.

Appears in 3 contracts

Samples: Concession Agreement, Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 5.2.1. It is expressly agreed that the Concessionaire Service Provider shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Service Provider from its obligations or liability hereunder. 5.2.2 5.2.2. The Concessionaire Service Provider shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Service Provider within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Service Provider shall submit to the Authority a true copy thereof, duly attested by a Director director of the ConcessionaireService Provider, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and / or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and / or observation of the Authority and/or and / or its failure to review and/or and / or convey its observations on any Document document shall relieve the Concessionaire Service Provider of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 5.2.3. The Concessionaire Service Provider shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Service Provider shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Service Provider. 5.2.4. Notwithstanding anything to the contrary contained in this Agreement, the Service Provider shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Right of Way to the Silos, as the case may be, without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-lease, sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws. 5.2.5. The Service Provider shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Service Provider in the event of Termination (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Termination Date, the Project Agreements shall be deemed to cease to be in force and effect on the Termination Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Service Provider expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Government an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination.

Appears in 2 contracts

Samples: Service Agreement, Service Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Concessioning Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Concessioning Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Concessioning Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Concessioning Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Concessioning Authority. No review and/ or observation of the Concessioning Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Concessioning Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Concessioning Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Concessioning Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Concessioning Authority. For the avoidance of doubt, the Concessioning Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire.‌ 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Concessioning Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Concessioning Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Concessioning Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Concessioning Authority an acknowledgment and undertaking, in a form acceptable to the Concessioning Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Concessioning Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Concessioning Authority from national security and public interest perspective, the decision of the Concessioning Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Concessioning Authority. For the avoidance of doubt, it is expressly agreed that approval of the Concessioning Authority hereunder shall be limited to national security and public interest perspective, and the Concessioning Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Concessioning Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Real Estate Development without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a Material Adverse Effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause

Appears in 2 contracts

Samples: Concession Agreement, Model Concession Agreement

Obligations relating to Project Agreements. 5.2.1 (a) It is expressly agreed that the Concessionaire Developer shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Developer from its obligations or liability hereunder. 5.2.2 (b) The Concessionaire Developer shall submit to the Authority Client the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority Client shall have the right but not the obligation obliged to undertake such review and provide its comments, if any, to the Concessionaire Developer within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Developer shall submit to the Authority Client a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority Client and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Developer of its obligations and liabilities under this Agreement in any manner nor shall the Authority Client be liable for the same in any manner whatsoever. 5.2.3 (c) The Concessionaire Developer shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Client if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityClient, and in the event that any replacement or amendment is made without such consent, the Concessionaire Developer shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityClient. For the avoidance of doubt, the Authority Client acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Developer.

Appears in 2 contracts

Samples: Development Agreement, Development Agreement

Obligations relating to Project Agreements. 5.2.1 5.2.1. It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts5.2.2. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority ULB if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityULB, and in andin the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityULB. For the avoidance of doubt, the Authority ULB acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.3. The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the ULB to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of TerminationorSuspension(the―Covenant‖).Fortheavoid anceofdoubt,itis expressly agreed that in the event the ULB does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the ULB and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the ULB an acknowledgment and undertaking, in a form acceptable to the ULB, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the Same and not to seek any relief or remedy whatsoever from the ULB in the event of Termination or Suspension. The Concessionaire shall also procure that such Project Agreements shall also include a covenant that all disputes arising out of such Agreements shall be settled between the Concessionaire and the Counter-parties and that ULB/Authority or its advisors/contractors/consultant s shall not be impleaded in such disputes whatsoever.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 5.2.1. It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Concession Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 5.2.2. The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the ofthe receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 5.2.3. The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling reschedulingof the debt of the Debt DueConcessionaire. 5.2.4. The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decisionof the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavourto convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaireor its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 5.2.1. It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 5.2.2. The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreementthe 5.2.3. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if Authority. If such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4. The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement (including financing agreements if any) or amendment thereto, the Concessionaire Operator shall submit to the Authority a true copy thereof, duly attested by a Director of the ConcessionaireOperator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. 5.2.4 The Operator shall procure that each of the Project Agreements contains provisions that entitle the Authority and / or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Operator in the event of Termination (the “Covenant”). For Further, it is clarified that in case both the avoidance of doubtAuthority and Xxxxxxx’ Representative decide to exercise their right to step-in, the Authority acknowledges and agrees that it shall have the sole right to step into the Project Agreements. 5.2.5 All contracts entered in to by the Operator with shipping companies, transporters, contractors, agents, or any other third parties in relation with the Scope of Work of this Agreement, shall be coterminous with this Agreement. The Operator shall not unreasonably withhold its consent enter into any sub-licensing arrangement for restructuring or rescheduling the Project Facility with any other party and ensure that all such contracts executed must contain a specific provision to this effect and that the Authority shall in no case be liable for the obligations, if any, arising out of such contracts after the Debt DueCompletion by efflux of time /exercise of exit option /Termination of this Agreement.

Appears in 2 contracts

Samples: Operation & Maintenance Agreement, Operation & Maintenance Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Operator shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Operator shall submit to the Authority a true copy thereof, duly attested by a Director or any person authorised by the Board of Directors of the ConcessionaireOperator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Operator. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Depot Sites, without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-lease, sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Real Estate Development without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause 5.2.5 shall not apply where the Operator grants a sub-licence for a cumulative period, including any renewals thereof, not exceeding 11 (eleven) months. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.5 within a period of 60 (sixty) days from the date of receiving a notice along with full particulars and documents from the Operator, the approval shall be deemed to have been granted to the extent such sub-licence, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement.]

Appears in 2 contracts

Samples: Model Concession Agreement, Model Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Lead ULB if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityLead ULB, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityLead ULB. For the avoidance of doubt, the Authority Lead ULB acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.3 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Lead ULB to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Lead ULB does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Lead ULB and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Lead ULB an acknowledgment and undertaking, in a form acceptable to the Lead ULB, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Lead ULB in the event of Termination or Suspension.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of the Bus Terminal along with associated amenities & facilities and Commercial Complex, without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws provided, (a) the period of the sub-license shall be co-terminus with the period of this Concession Agreement. Upon termination of this Agreement, the sub-license so granted by the Concessionaire shall also stand terminated. (b) in case of pre-mature Termination of this Concession Agreement, as per the discretion of the Authority, all proceeds/ rentals arising out from such sub-licensing of the Project Facility shall thereupon accrue to the Authority. (c) the Concessionaire shall furnish the copy of the signed sub-license deed to the Authority for its information and record. (d) the sub-license deeds shall not contain any provision which is directly or indirectly violative of the terms and conditions of this Agreement and/ or causes any material adverse effect on the interests of the Authority under this Agreement. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.4 within a period of 60 (sixty) days from the date of receiving a notice along with full particulars and documents from the Concessionaire, the approval shall be deemed to have been granted to the extent such sub-licence, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement. 5.2.5 Notwithstanding anything to the contrary contained in Clause 5.2.4, the Concessionaire shall not sub–licence, assign or in any manner create an Encumbrance on any Project Asset forming part of the Bus Terminal along with associated amenities & facilities and Commercial Complex at any time prior to the [18 (Eighteen) Months] of the Appointed Date. For the avoidance of doubt, the restriction imposed herein shall not apply to assignment under the Substitution Agreement. 5.2.6 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It it is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and / or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and / or observation of the Authority and/or and/ or its failure to review and/or and / or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90(ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be inforce and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies)of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Model Concession Agreement, Model Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever.. Downloaded from xxx.xxxxxx.xxx 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Commercial Complex without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause 5.2.4 shall not apply where the Concessionaire grants a sub-licence for a cumulative period, including any renewals thereof, not exceeding 11 (eleven) months. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.4 within a period of 60 (sixty) days from the date of receiving a notice alongwith full particulars and documents from the Concessionaire, the approval shall be deemed to have been granted to the extent such sub-licence, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement. 5.2.5 Notwithstanding anything to the contrary contained in Clause 5.2.4, the Concessionaire shall not sub–licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Commercial Complex at any time prior to the [(***)anniversary] of the Appointed Date. For the avoidance of doubt, the restriction imposed herein shall not apply to assignment under the Substitution Agreement. 5.2.6 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. Downloaded from xxx.xxxxxx.xxx 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and the Concessionaire undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 5.3.1. It is expressly agreed that the Concessionaire shall, at all times, shall be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts5.3.2. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire and shall respond to the request for consent no later than 30 (thirty) days from the receipt of such request from the Concessionaire. 5.3.3. The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt due. 5.2.4 The Concessionaire shall ensure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire SPD shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the agreements related to this project “Project Agreements Agreements” or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire SPD from its obligations or liability hereunder. 5.2.2 The Concessionaire SPD shall submit to the Authority Railways the drafts of all Project Agreements, Agreements including the Financing Agreements or any amendments or replacements thereto, for its review and comments, and the Authority Railways shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire SPD within [15 (fifteen) )] days of the receipt of such drafts. Within [7 (seven) )] days of execution of any Project Agreement or amendment thereto, the Concessionaire SPD shall submit to the Authority Railways a true copy thereof, duly attested by a Director of the ConcessionaireSPD, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of Railways to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by Railways. No review and / or observation of the Authority and/or Railways and / or its failure to review and/or and / or convey its observations on any Document document shall not relieve the Concessionaire SPD of its obligations and liabilities under this Agreement in any manner nor shall the Authority Railways be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire SPD shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Railways if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityRailways, and in the event that any replacement or amendment is made without such consent, the Concessionaire SPD shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityRailways. For the avoidance of doubt, the Authority Railways acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the SPD. 5.2.4 The SPD shall ensure that each of the Project Agreements contains provisions that entitle Railways to step into such agreement, in its sole discretion, in substitution of the SPD in the event of Termination or Suspension. For the avoidance of doubt, it is expressly agreed that in the event Railways does not exercise such rights of substitution within a period not exceeding [90 (ninety)] days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on .

Appears in 2 contracts

Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement

Obligations relating to Project Agreements. 5.2.1 It The Concessionaire shall be entitled to sub-contract its obligations under this Agreement in part (but not in full) in accordance with the provisions of this Clause 5.2 and the other provisions of this Agreement provided always that such sub- contracting shall not in any manner whatsoever relieve the Concessionaire from any of its obligation or liability under this Agreement and the Concessionaire shall at all times remain responsible for any act or omission of its counter-parties under a Project Agreement (other than this Agreement) and its contractors/sub-contractors, as if they were the acts or omissions of the Concessionaire. 5.2.2 The Concessionaire shall procure goods and services, and award contracts, sub- contracts, or any other rights or privilege in the Project in a competitive, fair, transparent and efficient manner, and shall at all times enter into contracts on an arm’s length basis and in accordance with Applicable Laws. 5.2.3 {The Concessionaire shall procure that the Lead Technical Member is expressly agreed that responsible for all matters pertaining to the operation of the Hospital as is listed in Schedule 25. The Authority may require the Concessionaire to submit documents evidencing compliance with this provision, from time to time.} Notwithstanding the aforesaid and/or anything to the contrary contained in this Agreement and/or any Project Agreement, under no circumstances shall the Concessionaire sub-contract the overall development, operation and maintenance of the Project and the Concessionaire shall, at all times, times be responsible for carrying out and liable for all its obligations under this Agreement notwithstanding anything contained in shall carry out the Project Agreements or any other agreement, overall administration and no default under any Project Agreement or agreement shall excuse management of the Concessionaire from its obligations or liability hereunderHospital. 5.2.2 5.2.4 The Concessionaire shall submit to the Authority the drafts of all such Project Agreements, Financing Agreements, insurance contracts or any such amendments or replacements thereto, as may be requested by the Authority for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days Upon the request of execution of any Project Agreement or amendment theretothe Authority, the Concessionaire shall submit to the Authority a true copy thereofof the Project Agreement(s), Financing Agreement(s), insurance contracts or amendments thereto, as the case may be, duly attested by a Director of the Concessionaire, for its recordrecord within 7 (seven) days of receipt of such request. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/ or its failure to request for a Project Agreement, Financing Agreement, insurance contracts or any amendment for review and/or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 5.2.5 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the The Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt DueDue of the Concessionaire. 5.2.6 The Concessionaire shall ensure that each Project Agreement contains provisions in accordance with this Clause 5.2.6 that entitle the Authority or its nominee, in its sole discretion, to step into such an agreement to substitute the Concessionaire in the event of Termination (the “Covenant”) on the following terms and conditions: (a) Any bank guarantee submitted by any Project Counterparty to the Concessionaire in accordance with the provisions of the Project Agreement, as performance security or any other form of security, assurance or guarantee for the performance of such Project Agreement, shall be transferred in the name of the Authority or its nominee by such Project Counterparty; (b) The benefits of all warranties given by the Project Counterparties under the Project Agreements shall be available to the Authority or its nominee; (c) In case the Authority step in occurs due to the termination of the Agreement prior to its term, the Project Agreement may, irrespective of any longer remaining term of the Project Agreement, be terminated by the Authority after expiry of 90 (ninety) days from such termination of this Agreement and, the Authority shall not be liable to make any payments solely on account of such termination of the Project Agreement; (d) The Project Counterparty shall not terminate the Project Agreement solely on account of the right of the Authority to step into such agreement and the Authority shall not incur any liability to the Project Counterparty solely on account of the inclusion of the Covenant; (e) In the event the Authority does not exercise its rights to step in place of the Concessionaire in the Project Agreement within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreement shall be deemed to cease to be in force and effect on the Transfer Date without the Authority being liable in any manner whatsoever; and (f) All sums claimed by the Project Counterparty as being due and owing for works and services performed or accruing prior to Termination, shall constitute debt between the Concessionaire and the Project Counterparty, and the Authority shall not in any manner be liable for such sums. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each Project Agreement, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from each of the Project Counterparties that it would be bound by the Covenant and not to seek any relief or remedy whatsoever from the Authority in the event of Termination. 5.2.7 The Concessionaire shall be entitled to appoint O&M Contractor(s) for O&M of the Hospital (except the Core Clinical Services) and for provision and operation of the Ancillary Facilities at the Hospital subject to the O&M Contractor meeting the requirements stipulated in Schedule 22. {Notwithstanding anything to the contrary contained in this Clause 5.2.7 but subject always to Clause 5.2.3, the Authority agrees that the Concessionaire shall be entitled to appoint the Lead Technical Member or an Associate of the Lead Technical Member as an O&M Contractor for the O&M of the Hospital, including for providing the Core Clinical Services, provided that the Authority may, in its sole discretion, not allow the Concessionaire to appoint an Associate of the Lead Technical Member as an O&M Contractor for providing the Core Clinical Services only from a national security and/or a public interest perspective. The Concessionaire shall immediately upon execution, submit a copy of the duly executed O&M Contract with the Lead Technical Member or its Associate, as the case may be, to the Authority for its review, and the Authority may request amendments to the O&M Contract for ensuring compliance with the terms of this Agreement, and the Concessionaire shall comply with such request of the Authority within 15 (fifteen) days of receipt of the request.}

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement this Agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority Maha-Metro a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority Maha-Metro and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority Maha-Metro be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Maha-Metro if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMaha-Metro, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMaha-Metro. For the avoidance of doubt, the Authority Xxxx-Metro acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority ULB if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityULB, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityULB. For the avoidance of doubt, the Authority ULB acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.3 The Concessionaire shall ensure that each of the Project Agreements contains provisions that entitle the ULB to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the ULB does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the ULB and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the ULB an acknowledgment and undertaking, in a form acceptable to the ULB, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the ULB in the event of Termination or Suspension. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub- license, assign or in any manner create any Encumbrance on Project Site, Existing Assets and Immovable Project Assets.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire and shall respond to the request for consent no later than 30 days from the receipt of such request from the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority and / or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). Further, it is clarified that in case both the Authority and Lenders’ Representative decide to exercise their right to step-in, the Authority shall have the sole right to step into the Project Agreements. For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of the EPC Contractor and an O&M Contractor and execution of the EPC Contract and O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavor to convey its decision thereon expeditiously and no later than 30 days from the date of receipt of the proposal alongwith the draft agreement by the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Real Estate Development without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, shall at all times, times be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, agreement and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 . The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen15(fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this its Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 . The Concessionaire shall not make any addition, replacement or amendments to any procure that each of the Financing Project Agreements contains provisions that entitle the Authority to step into such Agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall., in respect of each of the Project Agreements, procure and deliver to the Authority and acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor, if any, and execution of the O&M Contract shall be subject to the prior written consent approval of the Authority if such addition, replacement or amendment has, or may havefrom national security and public interest perspective, the effect decision of imposing or increasing any financial liability or obligation the Authority in this behalf being final, conclusive and binding on the AuthorityConcessionaire, and in the event undertakes that any replacement or amendment is made without such consent, the Concessionaire it shall not enforce give effect to any such replacement selection or amendment nor permit enforcement thereof against contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority acknowledges hereunder shall be limited to national security and agrees public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that it the Authority shall not unreasonably withhold be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its consent for restructuring Contractors from any liability or rescheduling of the Debt Dueobligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 1) It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 2) The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 3) The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 4) Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Real Estate Development without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub- licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause 5.2.4) shall not apply where the Concessionaire grants a sub-licence for a cumulative period, including any renewals thereof, not exceeding 11 (eleven) months. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.4) within a period of 60 (sixty) days from the date of receiving a notice along with full particulars and documents from the Concessionaire, the approval shall be deemed to have been granted to the extent such sub-license, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement. 5) Notwithstanding anything to the contrary contained in Clause 5.2.4), the Concessionaire shall not sub–licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Real Estate Development at any time prior to the [3rd (third) anniversary] of the Appointed Date. For the avoidance of doubt, the restriction imposed herein shall not apply to assignment under the Substitution Agreement. 6) The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority MPRDC the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority MPRDC shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority MPRDC a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of MPRDC to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the MPRDC. No review and/ or observation of the Authority and/or MPRDC and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority MPRDC be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority MPRDC if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMPRDC , and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMPRDC. For the avoidance of doubt, the Authority MPRDC acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle MPRDC to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event MPRDC does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on MPRDC and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to MPRDC an acknowledgment and undertaking, in a form acceptable to the MPRDC , from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from MPRDC in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of MPRDC from national security and public interest perspective, the decision of MPRDC in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the MPRDC . For the avoidance of doubt, it is expressly agreed that approval of MPRDC hereunder shall be limited to national security and public interest perspective, and MPRDC shall endeavour to convey its decision thereon expeditiously. It is also agreed that MPRDC shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority Authority, the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation any failure or omission of the Authority and/or its failure to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any addition, replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due.Due of the

Appears in 1 contract

Samples: Model Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority MOPIT the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority MOPIT shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority MOPIT a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority MOPIT and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority MOPIT be liable for the same in any manner whatsoever... 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority MOPIT if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMOPIT, and in the event that any addition, replacement or amendment is made without such consent, the Concessionaire shall not enforce such addition, replacement or amendment nor permit enforcement thereof against the AuthorityMOPIT. For the avoidance of doubt, the Authority MOPIT acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the MOPIT to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the MOPIT does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the MOPIT and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the MOPIT an acknowledgement and undertaking, in a form acceptable to the MOPIT, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief and remedy whatsoever from the MOPIT in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O & M Contractor and execution of the O & M Contract shall be subject to the prior approval of the MOPIT from national security and public interest perspective, the decision of the MOPIT in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the MOPIT. For the avoidance of doubt, it is expressly agreed that approval of the MOPIT hereunder shall be limited to national security and public interest perspective, and the MOPIT shall endeavour to convey its decision thereon expeditiously. It is also agreed that the MOPIT shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 4.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 4.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the be Authority be liable for the same in any manner whatsoever. 5.2.3 4.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 4.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire and shall respond to the request for consent no later than 30 days from the receipt of such request from the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority and / or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). Further, it is clarified that in case both the Authority and Lenders’ Representative decide to exercise their right to step-in, the Authority shall have the sole right to step into the Project Agreements. For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of the EPC Contractor and an O&M Contractor and execution of the EPC Contract and O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavor to convey its decision thereon expeditiously and no later than 30 days from the date of receipt of the proposal along with the draft agreement by the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 ‌ 5.2.1. It is expressly agreed that the Concessionaire shall, shall at all times, times be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, agreement and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 . The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 5.2.2. The Concessionaire shall not make any addition, replacement or amendments to any procure that each of the Financing Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.3. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor, if any, and execution of the O&M Contract shall be subject to the prior written consent approval of the Authority if such addition, replacement or amendment has, or may havefrom national security and public interest perspective, the effect decision of imposing or increasing any financial liability or obligation the Authority in this behalf being final, conclusive and binding on the AuthorityConcessionaire, and in the event undertakes that any replacement or amendment is made without such consent, the Concessionaire it shall not enforce give effect to any such replacement selection or amendment nor permit enforcement thereof against contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority acknowledges hereunder shall be limited to national security and agrees public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that it the Authority shall not unreasonably withhold be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its consent for restructuring Contractors from any liability or rescheduling of the Debt Dueobligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, Operator shall at all times, times be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, agreement and no default under any Project Agreement or agreement shall excuse the Concessionaire Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Operator shall submit to the Authority SPV the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority SPV shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Operator shall submit to the Authority SPV a true copy thereof, duly attested by a Director director of the ConcessionaireOperator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority SPV and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority SPV be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Operator shall not make any addition, replacement or amendments to any ensure that each of the Financing Project Agreements without contains provisions that entitle the prior written consent SPV to step into such agreement, in its sole discretion, in substitution of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and Operator in the event that any replacement of Termination or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthoritySuspension. For the avoidance of doubt, it is expressly agreed that in the Authority event the SPV does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the SPV, provisions in each of the Project Agreements shall expressly provide for such eventuality. The Operator expressly agrees to include this covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the SPV an acknowledgment and undertaking, in a form acceptable to the SPV, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept this covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the SPV in the event of Termination or Suspension. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Operator agrees and acknowledges that selection or replacement of any sub-Contractor and agrees execution of any sub- Contract shall be subject to the prior approval of the SPV from national security and public interest perspective, the decision of the SPV in this behalf being final, conclusive and binding on the Operator, and undertakes that it shall not unreasonably withhold its consent for restructuring give effect to any such selection or rescheduling contract without prior approval of the Debt DueSPV. For the avoidance of doubt, it is expressly agreed that approval of the SPV hereunder shall be limited to national security and public interest perspective, and the SPV shall endeavour to convey its decision thereon expeditiously. It is also agreed that the SPV shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Operator or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Operation Services Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority GOTN, HD the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority GOTN, HD shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority GOTN, HD a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority GOTN, HD and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority GOTN, HD be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority GOTN, HD if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityGOTN, HD, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityGOTN, HD. For the avoidance of doubt, the Authority GOTN, HD acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall ensure that each of the Project Agreements contains provisions that entitle - GOTN, HD to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of GOTN, HD from national security and public interest perspective and that the decision of GOTN, HD in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or replacement contract without prior approval of GOTN, HD. For the avoidance of doubt, it is expressly agreed that approval of GOTN, HD hereunder shall be limited to national security and public interest perspective, and GOTN, HD shall endeavour to convey its decision thereon expeditiously. It is also agreed that GOTN, HD shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire theOperator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Operator shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Operator shall submit to the Authority a true copy thereof, duly attested by a Director of the ConcessionaireOperator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Operator. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Depot Sites, without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-lease, sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub- licence, assign or in any manner create an Encumbrance on any Project Assetwithoutprior written approval of the Authority. 5.2.6 The Operator shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Operator in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, whereunder such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from nationalsecurity and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Operator, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavor to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Operator or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements and/ or any other agreementagreement (other than this Agreement), and no default under any Project Agreement or and/or any other agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.3 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the "Covenant"). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.4 The Concessionaire shall be entitled to appoint the O&M Contractor for O&M of the Project, save and except for Core Clinical Services. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority. The decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and the Concessionaire undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to ensure compliance of the provisions of this Clause 5.2.4, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement and/ or under Applicable Laws. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall be entitled to appoint its Associate as the O&M Contractor for Core Clinical Services.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire DEVELOPER shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire DEVELOPER from its obligations or liability hereunder. 5.2.2 The Concessionaire DEVELOPER shall submit to the Authority SH&DB the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority SH&DB shall have the right but not the obligation obliged to undertake such review and provide its comments, if any, to the Concessionaire DEVELOPER within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire DEVELOPER shall submit to the Authority SH&DB a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever.a 5.2.3 The Concessionaire DEVELOPER shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority SH&DB if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthoritySH&DB, and in the event that any replacement or amendment is made without such consent, the Concessionaire DEVELOPER shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthoritySH&DB. For the avoidance of doubt, the Authority SH&DB acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the DEVELOPER.

Appears in 1 contract

Samples: Development Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority MOR the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority MOR shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority MOR a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of MOR to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by MOR. No review and/ or observation of the Authority and/or MOR and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority MOR be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority MOR if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMOR, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMOR. For the avoidance of doubt, the Authority MOR acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle MOR to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of 7 H U P L Q D W CLoveRnantQ · R U ) 6 RX avoidance of doubt, it is expressly agreed that in the event MOR does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on MOR and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to MOR an acknowledgment and undertaking, in a form acceptable to MOR, from the counter party(ies) of each of the Project Agreements, where-under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from MOR in the event of Termination or Suspension.

Appears in 1 contract

Samples: Construction Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire and shall respond to the request for consent no later than 30 days from the receipt of such request from the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority and / or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). Further, it is clarified that in case both the Authority and Xxxxxxx‟ Representative decide to exercise their right to step-in, the Authority shall have the sole right to step into the Project Agreements. For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of the EPC Contractor and O&M Contractor and execution of the EPC Contract and O&M Contract shall be subject to the following: a. The prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority; and b. The prior approval of the Authority to ensure that the proposed replacements possess necessary qualification and credentials as that of the original EPC Contractor and O&M Contractor, as the case may be. The Authority shall endeavour to convey its decision thereon expeditiously and no later than 30 days from the date of receipt of the proposal along with the draft agreement by the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Concession Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement Agreements or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Concession Agreement. It is further agreed that no any failure or omission of the Authority to review and/or comment hereunder shall not be construed or deemed as acceptance of any such agreement or Document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Concession Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Mine Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire Mine Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Mine Operator shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Mine Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment or replacement thereto, the Concessionaire Mine Operator shall submit to the Authority a true copy thereof, duly attested by a Director director of the ConcessionaireMine Operator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such Project Agreement or any amendments or replacements thereto by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document of the aforesaid document(s) shall relieve the Concessionaire Mine Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Mine Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in . In the event that any such replacement or amendment is made to any of the Financing Agreements without such consentprior written consent of the Authority, the Concessionaire Mine Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling the debt of the Debt DueMine Operator. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Mine Operator shall not sub-lease, sub-licence, assign or in any manner create an Encumbrance on the Site or on the Coal Depot, as the case may be, without prior written approval of the Authority, which approval the Authority may deny if such sub-licence, assignment or Encumbrance has or may have a Material Adverse Effect on the rights and obligations of the Authority under this Agreement or the Applicable Laws. 5.2.5 The Mine Operator shall procure that each of the Project Agreements contain provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Mine Operator in the event of the Termination or Suspension (the "Covenant"). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period of 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Mine Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.6 Notwithstanding anything to the contrary contained in this Agreement, the Mine Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority and the decision of the Authority in this behalf shall be final, conclusive and binding on the Mine Operator. In this regard, the Mine Operator undertakes that it shall not give effect to any such selection or replacement of an O&M Contractor, or execution the O&M Contract, without such prior approval of the Authority. It is also agreed that the Authority shall not be liable in any manner whatsoever on account of grant or otherwise denial of such approval and that such approval or denial thereof shall not in any manner absolve the Mine Operator or its O&M Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Model Contract Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Mine Developer and Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire Mine Developer and Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Mine Developer and Operator shall submit to the Authority TANGEDCO the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority TANGEDCO shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Mine Developer and Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Mine Developer and Operator shall submit to the Authority TANGEDCO a true copy thereof, duly attested by a Director director of the ConcessionaireMine Developer and Operator, for its record. For the avoidance of doubt, it is agreed that the review views and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of TANGEDCO to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by TANGEDCO. No review and/or observation of the Authority TANGEDCO and/or its failure to review and/or convey its observations on any Document document shall not relieve the Concessionaire Mine Developer and Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority TANGEDCO be liable for the same in any manner whatsoever. TANGEDCO shall have rights to seek any contract, agreement along with amendments of Mine Developer and Operator if necessary, to ensure the compliance with the terms of this Agreement. However, TANGEDCO shall have a right to seek from the Mine Developer and Operator certified copies of any other contract or agreement (apart from the Project Agreements) along with any amendments thereto, that may have been entered into by the Mine Developer and Operator for fulfillment of its Obligations under this Agreement. 5.2.3 It shall be the duty of the Mine Developer and Operator to ensure that none of the Project Agreements entered into or to be entered into by Mine Developer and Operator with any third party shall contain any term(s) which is/are contrary to or inconsistent with this Agreement or the Allotment Agreement. In the event, any such contrary or inconsistent term/s is/are found in any of the Project Agreements entered into or to be entered into by Mine Developer and Operator with any third party, then the Mine Developer and Operator shall immediately procure amendment / rectification of such Project Agreements to that extent. For the removal of doubts, the Mine Developer and Operator declares and agrees that it shall not be excused from amending / rectifying any such Project Agreements on the ground that the same was reviewed or commented upon by TANGEDCO in the manner stipulated in Clause 5.2.2. 5.2.4 The Concessionaire Mine Developer and Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority TANGEDCO if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityTANGEDCO, and in the event that any replacement or amendment is made without such consent, the Concessionaire Mine Developer and Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityTANGEDCO. For the avoidance of doubt, the Authority TANGEDCO acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling the debt of the Debt DueMine Developer and Operator. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Mine Developer and Operator shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Site or on the Coal Depot, as the case may be, without prior written approval of TANGEDCO, which approval TANGEDCO may, in its discretion, deny if such sub-license, assignment or Encumbrance has or may have a Material Adverse Effect on the rights and obligations of TANGEDCO under this Agreement or Applicable Laws. 5.2.6 The Mine Developer and Operator shall ensure that each of the Project Agreements contain provisions that entitle TANGEDCO to step into such agreements in its sole discretion (the "Covenant").For the avoidance of doubt, it is expressly agreed that the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on TANGEDCO and the Covenant shall expressly provide for such eventuality. The Mine Developer and Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreement, procure and deliver to TANGEDCO an acknowledgment and undertaking, in a form acceptable to TANGEDCO, from the counter party(s) of each of the Project Agreement, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from TANGEDCO in the event of Termination or Suspension. 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Mine Developer and Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of TANGEDCO and the decision of TANGEDCO in this behalf shall be final, conclusive and binding on the Mine Developer and Operator, and the Mine Developer and Operator undertakes that it shall not give effect to any such selection or contract without prior approval of TANGEDCO. It is also agreed that TANGEDCO shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Mine Developer and Operator or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Coal Mining Agreement

AutoNDA by SimpleDocs

Obligations relating to Project Agreements. 5.2.1 (a) It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 (b) The Concessionaire shall submit to the Authority AMC the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority AMC shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 Within (sevenc) days The Concessionaire shall procure that each of execution the Project Agreements contains provisions that entitle the AMC to step into such agreement, in its sole discretion, in substitution of any Project Agreement or amendment thereto, the Concessionaire shall submit to in the Authority a true copy thereof, duly attested by a Director event of the Concessionaire, for its recordTermination. For the avoidance of doubt, it is expressly agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without the AMC does not exercise such consentrights of substitution within a period not exceeding 30 (thirty) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the AMC and the covenant shall expressly provide for such eventuality. (d) The Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against expressly agrees to include the Authority. For the avoidance of doubt, the Authority acknowledges covenant in all its Project Agreements and agrees undertakes that it shall not unreasonably withhold its consent for restructuring or rescheduling shall, in respect of each of the Debt DueProject Agreements, procure and deliver to the AMC an acknowledgment and undertaking, in a form acceptable to the AMC, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the AMC in the event of Termination.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding not withstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Operator shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Operator shall submit to the Authority a true copy thereof, duly attested by a Director of the ConcessionaireOperator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Operator. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub- lease, sub-license, assign or in any manner create an Encumbrance on the Depot Sites, without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-lease, sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub- licence, assign or in any manner create an Encumbrance on any Project Asset. 5.2.6 The Operator shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Operator in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Operator, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavor to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Operator or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Contractor shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Contractor from its obligations or liability hereunder. 5.2.2 The Concessionaire Contractor shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Contractor within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Contractor shall submit to the Authority a true copy thereof, duly attested by a Director of the ConcessionaireContractor, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire Contractor of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Contractor shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Contractor shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Contractor and shall respond to the request for consent no later than 30 days from the receipt of such request from the Contractor. 5.2.4 The Contractor shall procure that each of the Project Agreements contains provisions that entitle the Authority and / or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Contractor in the event of Termination or Suspension (the “Covenant”). Further, it is clarified that in case both the Authority and Lenders’ Representative decide to exercise their right to step-in, the Authority shall have the sole right to step into the Project Agreements. For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Contractor expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Contractor agrees and acknowledges that selection or replacement of the EPC Contractor and an O&M Contractor and execution of the EPC Contract and O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Contractor, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavor to convey its decision thereon expeditiously and no later than 30 days from the date of receipt of the proposal along with the draft agreement by the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Contractor or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Contract Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Operator shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Operator shall submit to the Authority a true copy thereof, duly attested by a Director of the ConcessionaireOperator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Operator. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Depot Sites, without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-lease, sub- license, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub-license, assign or in any manner create an Encumbrance on any Project Asset and infrastructure created by Operator including charging stations without prior written approval of the Authority after entering into this Concession Agreement 5.2.6 The Operator shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Operator in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, whereunder such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Operator, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavor to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Operator or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Mine Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire Mine Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Mine Operator shall submit to the Authority the drafts of maintain all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the . The Authority shall have reserves the right but not the obligation to undertake call for any such review related documents as and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such draftswhen required. Within 7 (seven) days from the date of execution making of any Project Agreement or amendment theretosuch request by the Authority, the Concessionaire Mine Operator shall submit to with the Authority a true copy thereofof the required documents, duly attested by a Director director of the Concessionaire, for its recordMine Operator. For The documents so submitted in the avoidance of doubt, it is agreed that the review and comments hereunder aforesaid manner shall be limited to ensuring compliance kept with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoeveras confidential records. 5.2.3 The Concessionaire Mine Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in . In the event that any such replacement or amendment is made to any of the Financing Agreements without such consentprior written consent of the Authority, the Concessionaire Mine Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling the debt of the Debt DueMine Operator. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Mine Operator shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Site or on the Coal Depot, as the case may be, without prior written approval of the Authority, which approval the Authority may deny if such sub-license, assignment or Encumbrance has or may have a Material Adverse Effect on the rights and obligations of the Authority under this Agreement or the Applicable Laws. 5.2.5 The Mine Operator shall procure that each of the Project Agreements contain provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Mine Operator in the event of the Termination or Suspension (the "Covenant"). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period of 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Mine Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.6 Notwithstanding anything to the contrary contained in this Agreement, the Mine Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority and the decision of the Authority in this behalf shall be final, conclusive and binding on the Mine Operator. In this regard, the Mine Operator undertakes that it shall not give effect to any such selection or replacement of an O&M Contractor, or execution the O&M Contract, without such prior approval of the Authority. It is also agreed that the Authority shall not be liable in any manner whatsoever on account of grant or otherwise denial of such approval and that such approval or denial thereof shall not in any manner absolve the Mine Operator or its O&M Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Contract Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority TNRDC the drafts of all Project AgreementsAgreements including a template for sub‐license of the shops, offices etc. in the MLCP and its components to the User, or any amendments or replacements thereto, thereto for its review and comments, and the Authority TNRDC shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 15 (sevenfifteen) days of execution of any Project Agreement Agreements or amendment thereto, the Concessionaire shall submit to the Authority TNRDC a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no No review and/or and/ or observation of the Authority and/or TNRDC and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority TNRDC be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any procure that each of the Financing Project Agreements without the prior written consent contains provisions that entitle TNRDC to step into such agreement, in its sole discretion, in substitution of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and Concessionaire in the event that any replacement of Termination or amendment is made without such consent, Suspension (the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority“Covenant”). For the avoidance of doubt, it is expressly agreed that in the Authority event TNRDC does not exercise such rights of substitution, the Project Agreements shall cease to be in force and effect on the Transfer Date without any liability whatsoever on TNRDC and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to TNRDC an acknowledgment and undertaking, in a form acceptable to TNRDC, from the counter party(s) of each of the Project Agreements, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from TNRDC in the event of Termination or Suspension. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor for Project shall be subject to the prior approval of TNRDC, the decision of TNRDC in this behalf being final, conclusive and agrees binding on the Concessionaire, and undertakes that it shall not unreasonably withhold give effect to any such selection or contract without prior approval of TNRDC. It is also agreed that TNRDC shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its consent for restructuring Contractors from any liability or rescheduling of the Debt Dueobligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 5.2.1. It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 5.2.2. The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 5.2.3. The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if Authority. If such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4. The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. The Concessionaire shall, within 7 (seven) days of receipt of comments by the Authority, make amendments to the Project Agreements and resubmit the same to the Authority for its review and comments. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of any Contractor and execution of any Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority Government the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority Government shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority Government a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Government to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Government. No review and/ or observation of the Authority and/or Government and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority Government be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Government if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityGovernment, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityGovernment. For the avoidance of doubt, the Authority Government acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Government to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Government does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Government and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Government an acknowledgment and undertaking, in a form acceptable to the Government, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Government in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Government from national security and public interest perspective, the decision of the Government in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Government. For the avoidance of doubt, it is expressly agreed that approval of the Government hereunder shall be limited to national security and public interest perspective, and the Government shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Government shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire . Further, each Member of the Consortium shall submit to be jointly and severally liable for the Authority the drafts performance of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to obligations of the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of under this Agreement. It is further agreed clarified that no review and/or observation such joint and several liability of the Authority and/or its failure to review and/or convey its observations on any Document Members constituting the Consortium shall relieve apply only as regards the obligations of the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall towards the Authority and the Hospitals, as defined in this Concession Agreement, and shall not apply to any liability of the Members to Third Parties as regards the Medical Services, as defined in this Concession Agreement. It is further clarified that the liabilities of the respective Members of the Consortium to Third Parties as regards the Medical Services shall be liable for the same as defined in any manner whatsoeverClause 29.1.1 of this Concession Agreement. 5.2.3 5.2.2 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. (a) The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority.For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.3 The Concessionaire shall procure that each of the Project Agreements to which the Concessionaire is a party contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority Confirming Party the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority Confirming Party shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority Confirming Party a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority Confirming Party and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Concessioning Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority Confirming Party if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Concessioning Authority/Confirming Party, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Concessioning Authority/Confirming Party. For the avoidance of doubt, the Authority Concessioning Authority/Confirming Party acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Concessioning Authority/Confirming Party to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 . The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 . The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire shall not sub-licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Real Estate Development without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a material adverse effect on the rights and obligations of the Authority under this Agreement or Applicable Laws; provided that the provisions of this Clause 5.2.4 shall not apply where the Concessionaire grants a sub-licence for a cumulative period, including any renewals thereof, not exceeding 11 (eleven) months. For the avoidance of doubt, it is agreed that if the Authority does not deny the approval required under this Clause 5.2.4 within a period of 60 (sixty) days from the date of receiving a notice along with full particulars and documents from the Concessionaire, the approval shall be deemed to have been granted to the extent such sub-licence, assignment or Encumbrance, as the case may be, is in accordance with the provisions of this Agreement. Notwithstanding anything to the contrary contained in Clause 5.2.4, the Concessionaire shall not sub–licence, assign or in any manner create an Encumbrance on any Project Asset forming part of Real Estate Development at any time prior to the [3rd (third) anniversary] of the Appointed Date. For the avoidance of doubt, the restriction imposed herein shall not apply to assignment under the Substitution Agreement. The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 5.2.1. It is expressly agreed that the Concessionaire shall, at all timestimes during the Concession Period, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement Agreements or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 5.2.2. The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 5.2.3. The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4. The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (“Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of all EPC Contractors or O&M Contractors and execution of all EPC Contracts or O&M Contracts shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director an authorized official of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or and/ or convey its observations on any Document anydocument shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements executed by the Concessionaire with Third Parties contain provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Model Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of any Contractor shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the Covenant ). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements, shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 4.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 4.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or comment hereunder shall not be construed or deemed as acceptance of any such agreement or Document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 4.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 4.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Concessioning Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority Government shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority Government a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Concessioning Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Concessioning Authority. No review and/ or observation of the Concessioning Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Concessioning Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Concessioning Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Concessioning Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Concessioning Authority. For the avoidance of doubt, the Concessioning Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Concessioning Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Covenantoubt, it is expressly agreed that in the event the Government does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Concessioning Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Concessioning Authority an acknowledgment and undertaking, in a form acceptable to the Concessioning Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Concessioning Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Concessioning Authority from national security and public interest perspective, the decision of the Concessioning Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Concessioning Authority. For the avoidance of doubt, it is expressly agreed that approval of the Concessioning Authority hereunder shall be limited to national security and public interest perspective, and the Concessioning Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Concessioning Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Mine Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire Mine Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Mine Operator shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Mine Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Mine Operator shall submit to the Authority a true copy thereof, duly attested by a Director director of the ConcessionaireMine Operator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Mine Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Mine Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire Mine Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling the debt of the Debt DueMine Operator. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Mine 17 Operator shall not sub-lease, sub-licence, assign or in any manner create an Encumbrance on the Site or on the Coal Depot, as the case may be, without prior written approval of the Authority, which approval the Authority may, in its discretion, deny if such sub-licence, assignment or Encumbrance has or may have a Material Adverse Effect on the rights and obligations of the Authority under this Agreement or Applicable Laws. 5.2.5 The Mine Operator shall procure that each of the Project Agreements contain provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Mine Operator in the event of Termination or Suspension (the "Covenant"). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Mine Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(s) of each of the Project Agreements, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.6 Notwithstanding anything to the contrary contained in this Agreement, the Mine Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority and the decision of the Authority in this behalf being final, conclusive and binding on the Mine Operator, and the Mine Operator undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Mine Operator or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Coal Mining Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Dueof the Concessionaire. 5.2.4 Left Blank .

Appears in 1 contract

Samples: Transmission Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority Authority, the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. The Concessionaire shall, within 7 (seven) days of receipt of comments by the Authority, make amendments to the Project Agreements and resubmit the same to the Authority for its review and comments. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority Government the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority Government shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority Government a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or and/ or observation of the Authority Government and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority Government be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any procure that each of the Financing Project Agreements without contains provisions that entitle the prior written consent Government to step into such agreement, in its sole discretion, in substitution of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and Concessionaire in the event that any replacement of Termination or amendment is made without such consent, Suspension (the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority“Covenant”). For the avoidance of doubt, it is expressly agreed that in the Authority event the Government does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Government and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Government an acknowledgment and undertaking, in a form acceptable to the Government, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Government in the event of Termination or Suspension. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and agrees execution of the O&M Contract shall be subject to the prior approval of the Government from national security and public interest perspective, the decision of the Government in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not unreasonably withhold its consent for restructuring give effect to any such selection or rescheduling contract without prior approval of the Debt DueGovernment. For the avoidance of doubt, it is expressly agreed that approval of the Government hereunder shall be limited to national security and public interest perspective, and the Government shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Government shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Mine Developer and Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire Mine Developer and Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Mine Developer and Operator shall submit to the Authority TANGEDCO the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority TANGEDCO shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Mine Developer and Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Mine Developer and Operator shall submit to the Authority TANGEDCO a true copy thereof, duly attested by a Director director of the ConcessionaireMine Developer and Operator, for its record. For the avoidance of doubt, it is agreed that the review views and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of TANGEDCO to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by TANGEDCO. No review and/or observation of the Authority TANGEDCO and/or its failure to review and/or convey its observations on any Document document shall not relieve the Concessionaire Mine Developer and Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority TANGEDCO be liable for the same in any manner whatsoever. TANGEDCO shall have rights to seek any contract, agreement along with amendments of Mine Developer and Operator if necessary, to ensure the compliance with the terms of this Agreement. However, TANGEDCO shall have a right to seek from the Mine Developer and Operator certified copies of any other contract or agreement (apart from the Project Agreements) along with any amendments thereto, that may have been entered into by the Mine Developer and Operator for fulfillment of its Obligations under this Agreement. 5.2.3 It shall be the duty of the Mine Developer and Operator to ensure that none of the Project Agreements entered into or to be entered into by Mine Developer and Operator with any third party shall contain any term(s) which is/are contrary to or inconsistent with this Agreement or the Allotment Agreement. In the event, any such contrary or inconsistent term/s is/are found in any of the Project Agreements entered into or to be entered into by Mine Developer and Operator with any third party, then the Mine Developer and Operator shall immediately procure amendment / rectification of such Project Agreements to that extent. For the removal of doubts, the Mine Developer and Operator declares and agrees that it shall not be excused from amending / rectifying any such Project Agreements on the ground that the same was reviewed or commented upon by XXXXXXXX in the manner stipulated in Clause 5.2.2. 5.2.4 The Concessionaire Mine Developer and Operator shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority TANGEDCO if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityTANGEDCO, and in the event that any replacement or amendment is made without such consent, the Concessionaire Mine Developer and Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityTANGEDCO. For the avoidance of doubt, the Authority XXXXXXXX acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling the debt of the Debt DueMine Developer and Operator. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Mine Developer and Operator shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Site or on the Coal Depot, as the case may be, without prior written approval of TANGEDCO, which approval TANGEDCO may, in its discretion, deny if such sub-license, assignment or Encumbrance has or may have a Material Adverse Effect on the rights and obligations of TANGEDCO under this Agreement or Applicable Laws. 5.2.6 The Mine Developer and Operator shall ensure that each of the Project Agreements contain provisions that entitle TANGEDCO to step into such agreements in its sole discretion (the "Covenant"). For the avoidance of doubt, it is expressly agreed that the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on TANGEDCO and the Covenant shall expressly provide for such eventuality. The Mine Developer and Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreement, procure and deliver to TANGEDCO an acknowledgment and undertaking, in a form acceptable to TANGEDCO, from the counter party(s) of each of the Project Agreement, where under such counter party(s) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from TANGEDCO in the event of Termination or Suspension. 5.2.7 Notwithstanding anything to the contrary contained in this Agreement, the Mine Developer and Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of TANGEDCO and the decision of TANGEDCO in this behalf shall be final, conclusive and binding on the Mine Developer and Operator, and the Mine Developer and Operator undertakes that it shall not give effect to any such selection or contract without prior approval of TANGEDCO. It is also agreed that TANGEDCO shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Mine Developer and Operator or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Coal Mining Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. Further, each Member of the Consortium shall be jointly and severally liable for the performance of all the obligations of the Concessionaire under this Agreement. It is clarified that such joint and several liability of the Members constituting the Consortium shall apply only as regards the obligations of the Concessionaire towards the Authority and the Hospitals, as defined in this Concession Agreement, and shall not apply to any liability of the Members to Third Parties as regards the Medical Services, as defined in this Concession Agreement. It is further clarified that the liabilities of the respective Members of the Consortium to Third Parties as regards the Medical Services shall be as defined in Clause 29.1.1 of this Concession Agreement. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements to which the Concessionaire is a party contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that replacement of the O&M Contractor / O&M Member {and execution of the O&M Contract (applicable in the case of O&M Contractor)} shall be subject to the prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement. The Concessionaire agrees and acknowledges that such replaced O&M Contractor / O&M Member shall meet the O&M capabilities prescribed in Clause 2.2.7 of the RFP.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, shall at all times, times be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, agreement and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 . The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 5.2.2 The Concessionaire shall not make any addition, replacement or amendments to any procure that each of the Financing Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.3 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor, if any, and execution of the O&M Contract shall be subject to the prior written consent approval of the Authority if such addition, replacement or amendment has, or may havefrom national security and public interest perspective, the effect decision of imposing or increasing any financial liability or obligation the Authority in this behalf being final, conclusive and binding on the AuthorityConcessionaire, and in the event undertakes that any replacement or amendment is made without such consent, the Concessionaire it shall not enforce give effect to any such replacement selection or amendment nor permit enforcement thereof against contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority acknowledges hereunder shall be limited to national security and agrees public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that it the Authority shall not unreasonably withhold be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its consent for restructuring Contractors from any liability or rescheduling of the Debt Dueobligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 . The Concessionaire shall submit to the Authority / SSNNL / FED the drafts copies, duly attested by the Director of the Concessionaire, of all Project Agreements, if any, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire thereto within 15 90 (fifteenNinety) days from the date of the receipt of such drafts. Within 7 (seven) days of its execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its information and record. For the avoidance of doubt, it is agreed that the review and comments hereunder purpose of this condition shall be limited to ensuring Authority/Authority of Concessionaire's compliance in such regard with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document / SSNNL / FED shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority never be liable for the same in any manner whatsoever. 5.2.3 . The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority / SSNNL / FED if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityAuthority / SSNNL / FED, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityAuthority / SSNNL / FED. For the avoidance of doubt, the Authority / SSNNL / FED acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt due of the Concessionaire. The Concessionaire shall ensure that each of the Project Agreements contains provisions that entitle the Authority / SSNNL / FED to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority / SSNNL / FED does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority / SSNNL / FED and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority / SSNNL / FED an acknowledgment and undertaking, in a form acceptable to the Authority / SSNNL / FED, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority / SSNNL / FED in the event of Termination or Suspension. Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be as per terms of this Agreement and further, the Concessionaire shall always ensure to take all possible reasonable measures to scrutinize the credentials and bonafide in respect of each of such O & M contractors/sub-licensee prior to their appointment from national security and public interest perspective. Accordingly, it is also agreed that the Authority / SSNNL / FED shall not be liable in any manner on account of grant thereof and shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement. The Concessionaire shall not sub-contract any Construction Works in more than 70% (seventy per cent) of the Estimated Project Cost of the Project and shall carry out Construction Works directly under its own supervision and through its own personnel in at least 30% (thirty per cent) of the Estimated Project Cost of the Project. Provided, however, that in respect of the Works carried out directly by the Concessionaire, it may enter into contracts for the supply and installation of materials, plant, equipment, road furniture, safety devices and labour, as the case may be, for such Construction Works. The Parties further agree that all obligations and liabilities under this Agreement for the entire Project shall at all times remain with the Concessionaire. In the event any sub-contract for Construction Works, or the aggregate of such subcontracts with any sub-Contractor, exceeds 5% (five percent) of the Total Project Cost, the Concessionaire shall communicate the name and particulars, including the relevant experience of the sub-Contractor, to the Authority / SSNNL / FED prior to entering into any such sub-contract. The Authority / SSNNL / FED shall examine the particulars of the sub-Contractor from the national security and public interest perspective and may require the Concessionaire, no later than 15 (fifteen) business days from the date of receiving the communication from the Concessionaire, not to proceed with the sub- contract, and the Concessionaire shall comply therewith. In the event any sub-contract referred to in Clause 5.2.7 relates to a sub-Contractor who has, over the preceding 3 (three) years, not undertaken at least one work of a similar nature with a contract value exceeding 40% (forty per cent) of the value of the sub-contract to be awarded hereunder and received payments in respect thereof for an amount equal to at least such 40% (forty per cent), the Authority / SSNNL / FED may, no later than 15 (fifteen) business days from the date of receiving the communication from the Concessionaire, require the Concessionaire not to proceed with such sub-contract, and the Concessionaire shall comply therewith. It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the agreements with its sub- Contractors or any other agreement that may be entered into by the Concessionaire, and no default under any such agreement shall excuse the Concessionaire from its obligations or liability hereunder.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or any other agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director an authorized official of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements executed by the Concessionaire with Third Parties contain provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that agreed, no review and/or and / or observation of the Authority and/or and / or its failure to review and/or and / or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire and shall respond to the request for consent no later than 30 days from the receipt of such request from the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority and / or Lenders Representative to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). Further, it is clarified that in case both the Authority and Xxxxxxx’ Representative decide to exercise their right to step-in, the Authority shall have the sole right to step into the Project Agreements. For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. The Concessionaire shall, within 7 (seven) days of receipt of comments by the Authority, make amendments to the Project Agreements and resubmit the same to the Authority for its review and comments. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without Draft Concession Agreement any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreement, procure and deliver to the Authority an acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of any contractor and execution of any contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority MPRDC the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority MPRDC shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority MPRDC a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of MPRDC to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by MPRDC. No review and/or observation of the Authority MPRDC and/or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority MPRDC be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority MPRDC if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMPRDC, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMPRDC. For the avoidance of doubt, the Authority MPRDC acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle MPRDC to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event MPRDC does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on MPRDC and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to MPRDC an acknowledgment and undertaking, in a form acceptable to MPRDC, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from MPRDC in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of MPRDC from national security and public interest perspective, the decision of MPRDC in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of MPRDC . For the avoidance of doubt, it is expressly agreed that approval of MPRDC hereunder shall be limited to national security and public interest perspective, and MPRDC shall endeavour to convey its decision thereon expeditiously. It is also agreed that MPRDC shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt DueDue of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority MPRDC the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority MPRDC shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority MPRDC a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of MPRDC to review and/or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by MPRDC. No review and/ or observation of the Authority and/or MPRDC and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority MPRDC be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority MPRDC if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityMPRDC, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the AuthorityMPRDC. For the avoidance of doubt, the Authority MPRDC acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle MPRDC to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event MPRDC does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on MPRDC and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to MPRDC an acknowledgment and undertaking, in a form acceptable to MPRDC, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from MPRDC in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of MPRDC from national security and public interest perspective, the decision of MPRDC in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of MPRDC. For the avoidance of doubt, it is expressly agreed that approval of MPRDC hereunder shall be limited to national security and public interest perspective, and MPRDC shall endeavour to convey its decision thereon expeditiously. It is also agreed that MPRDC shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It it is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and / or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and / or observation of the Authority and/or and/ or its failure to review and/or and / or convey its observations on any Document document shall relieve the Concessionaire of for its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90(ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be inforce and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies)of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire Operator shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the any other Project Agreements or any other agreement, and no default under any other Project Agreement or agreement shall excuse the Concessionaire Operator from its obligations or liability hereunder. 5.2.2 The Concessionaire Operator shall submit to the Authority the drafts of all Project Agreements, Agreements (to which the Authority is not a party) or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire Operator within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire Operator shall submit to the Authority a true copy thereof, duly attested by a Director or any person authorised by the Board of Directors of the ConcessionaireOperator, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire Operator of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire Operator shall not make any addition, replacement or amendments to any of the Financing Agreements Agreements” without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the AuthorityTotal Project Cost, and in the event that any replacement or amendment is made without such consent, the Concessionaire Operator shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, and subject to this Clause 5.2.3, no prior consent of the Authority acknowledges and agrees that it shall not unreasonably withhold its consent be required for restructuring or rescheduling of the Debt Duedebt of the Operator provided such restructuring or rescheduling does not result in an increase in the Total Project Cost. 5.2.4 Notwithstanding anything to the contrary contained in this Agreement, the Operator shall not sub-lease, sub-license, assign or in any manner create an Encumbrance on the Depot Sites. 5.2.5 The Operator shall ensure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Operator in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect from the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality subject to the Operator issuing a notice of reminder to the Authority at least 15 (fifteen) days prior to the expiry of the aforesaid 90 (ninety) day period. The Operator expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.6 Notwithstanding anything to the contrary contained in this Agreement, the Operator agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective. The decision of the Authority in this behalf shall be final, conclusive and binding on the Operator, and therefore the Operator undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. Provided however, that this Clause 5.2.6 shall not apply to any subcontracts entered into by the Operator for the provision of any housekeeping or basic office support staff services. For the avoidance of doubt, it is expressly agreed that approval of the Authority under this Clause 5.2.6 shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Operator or its Contractors from any liability or obligation under this Agreement. 5.2.7 OEM Undertaking to the Authority In case of Termination of the Agreement, the OEM warranties product restoration to ensure continuous operation of Buses and other infrastructure provided by the Operator under this Agreement. The OEM Undertaking to be executed by the OEM is at Schedule W. In addition to the OEM Undertaking, XXX also agrees to execute Comprehensive Maintenance Contract as specified in Schedule Z. For the purpose of clarity, it is mentioned that a specific distinction between OEM and its Associate/Parent is specifically made. The Agreements referred herein shall be signed by OEM.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 4.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding not withstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 4.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or comment hereunder shall not be construed or deemed as acceptance of any such agreement or Document by the Authority. No review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 4.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Duedebt of the Concessionaire. 4.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgement and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 (a) It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 (b) The Concessionaire shall submit to the PMU/ Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the PMU/ Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority PMU a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the PMU/ Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the PMU / Authority. No review and / or observation of the PMU / Authority and/or and / or its failure to review and/or and / or convey its observations on any Document document shall not relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the PMU / Authority be liable for the same in any manner whatsoever. 5.2.3 (c) The Concessionaire shall not make any addition, replacement or amendments to any ensure that each of the Financing Project Agreements without contains provisions that entitle the prior written consent Authority to step into such agreement, in its sole discretion, in substitution of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and Concessionaire in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authorityof Termination. For the avoidance of doubt, it is expressly agreed that in the event the Authority acknowledges does not exercise such rights of substitution within a period not exceeding 30 (thirty) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the covenant shall expressly provide for such eventuality. (d) The Concessionaire expressly agrees to include a covenant in all its Project Agreements and undertakes that it shall not unreasonably withhold its consent for restructuring or rescheduling shall, in respect of each of the Debt DueProject Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, where under such counter party(ies) shall acknowledge and accept the covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no any failure or omission of the Authority to review and/or and/ or comment hereunder shall not be construed or deemed as acceptance of any such agreement or document by the Authority. No review and/ or observation of the Authority and/or and/ or its failure to review and/or and/ or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Dueof the Concessionaire. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority , from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority . For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Obligations relating to Project Agreements. 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, Agreements or any amendments or replacements thereto, thereto for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 30 (fifteenthirty) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due. 5.2.4 The Concessionaire shall procure that each of the Project Agreements contains provisions that entitle the Authority to step into such agreement, in its sole discretion, in substitution of the Concessionaire in the event of Termination or Suspension (the “Covenant”). For the avoidance of doubt, it is expressly agreed that in the event the Authority does not exercise such rights of substitution within a period not exceeding 90 (ninety) days from the Transfer Date, the Project Agreements shall be deemed to cease to be in force and effect on the Transfer Date without any liability whatsoever on the Authority and the Covenant shall expressly provide for such eventuality. The Concessionaire expressly agrees to include the Covenant in all its Project Agreements and undertakes that it shall, in respect of each of the Project Agreements, procure and deliver to the Authority an acknowledgment and undertaking, in a form acceptable to the Authority, from the counter party(ies) of each of the Project Agreements, whereunder such counter party(ies) shall acknowledge and accept the Covenant and undertake to be bound by the same and not to seek any relief or remedy whatsoever from the Authority in the event of Termination or Suspension. 5.2.5 Notwithstanding anything to the contrary contained in this Agreement, the Concessionaire agrees and acknowledges that selection or replacement of an O&M Contractor and execution of the O&M Contract shall be subject to the prior approval of the Authority from national security and public interest perspective, the decision of the Authority in this behalf being final, conclusive and binding on the Concessionaire, and undertakes that it shall not give effect to any such selection or contract without prior approval of the Authority. For the avoidance of doubt, it is expressly agreed that approval of the Authority hereunder shall be limited to national security and public interest perspective, and the Authority shall endeavour to convey its decision thereon expeditiously. It is also agreed that the Authority shall not be liable in any manner on account of grant or otherwise of such approval and that such approval or denial thereof shall not in any manner absolve the Concessionaire or its Contractors from any liability or obligation under this Agreement.

Appears in 1 contract

Samples: Concession Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!