Common use of Outage Restoration Clause in Contracts

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 239 contracts

Samples: Service Agreement, Service Agreement, Standard Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Outage Restoration. If an outage on the Attachment a Party's Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the other another Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParties, to the extent such information is known, information on the nature of the Emergency StateCondition, if the outage is caused by an Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage, if requested by a Party, which may be provided by e-mail or facsimile.

Appears in 170 contracts

Samples: Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment a Party's Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParty, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 70 contracts

Samples: Surplus Large Generator Interconnection Agreement, Surplus Large Generator Interconnection Agreement, Agreement

Outage Restoration. If an outage on either the Attachment Interconnection Customer’s or Transmission Owner’s Interconnection Facilities, Network Upgrades, System Protection Facilities or System Upgrade Facilities or System Deliverability Distribution Upgrades of the Connecting Transmission Owner or Developer adversely affects the other a Party’s operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParties, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice to the other Parties explaining the nature of the outage.

Appears in 58 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 37 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities Transmission Project or System Network Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 27 contracts

Samples: Service Agreement, Service Agreement, Service Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer Interconnection Customer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 17 contracts

Samples: Interconnection Agreement, Standard Interconnection Agreement, Standard Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 17 contracts

Samples: Large Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Outage Restoration. If an outage on either the Attachment Interconnection Customer’s or Transmission Owner’s Interconnection Facilities, Network Upgrades, System Protection Facilities or System Upgrade Facilities or System Deliverability Distribution Upgrades of the Connecting Transmission Owner or Developer adversely affects the other a Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParties, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice to the other Parties explaining the nature of the outage.

Appears in 16 contracts

Samples: Generator Interconnection Agreement, Interconnection Agreement, Large Generator Interconnection Agreement (ITC Holdings Corp.)

Outage Restoration. If an outage on the Attachment a Party's Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the other another Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParties, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 15 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities of TrAILCo or System Deliverability Upgrades of the Connecting Transmission Owner or Developer NYSEG adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party Party, and to the NYISO, or PJM, as applicable, to the extent such information is known, information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 13 contracts

Samples: Transmission Facility Interconnection Agreement, Service Agreement, Service Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 9 contracts

Samples: Transmission Facility Interconnection Agreement, Service Agreement, Service Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer Interconnection Customer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 9 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment a Party’s Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParty, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 8 contracts

Samples: Generator Interconnection Agreement, Agreement, Large Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities or System SystemTransmission Project or Network Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 6 contracts

Samples: Service Agreement, Service Agreement, Service Agreement

Outage Restoration. If an outage on the Attachment Facilities a Party's Interconnection Facilities, Network Upgrades or System Upgrade Facilities or System Deliverability Distribution Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParty, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 5 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Standard Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 5 contracts

Samples: Interconnection Agreement, , and Construction Agreement, Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities Transmission Project or System Network Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.. SERVICE AGREEMENT NO. 2599

Appears in 4 contracts

Samples: Service Agreement, Service Agreement, Service Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 4 contracts

Samples: Agreement, Agreement, Agreement

Outage Restoration. If an outage on the Attachment a Party's Interconnection Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParty, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 3 contracts

Samples: Study Agreement, Study Agreement, Study Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any SERVICE AGREEMENT NO. 2672 corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 3 contracts

Samples: Service Agreement, Service Agreement, Service Agreement

Outage Restoration. If an outage on either the Attachment Interconnection Customer's or Transmission Owner's Interconnection Facilities, Network Upgrades, System Protection Facilities or System Upgrade Facilities or System Deliverability Distribution Upgrades of the Connecting Transmission Owner or Developer adversely affects the other a Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParties, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice to the other Parties explaining the nature of the outage.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Asset Sale Agreement (CMS Energy Corp)

Outage Restoration. If an outage on the Attachment Facilities Transmission Project or System Network Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.. SERVICE AGREEMENT NO. 2605

Appears in 2 contracts

Samples: Service Agreement, Project Interconnection Agreement

AutoNDA by SimpleDocs

Outage Restoration. If an outage on the Attachment LS Power Transmission Facilities or System Network Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 2 contracts

Samples: Project Interconnection Agreement, Project Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities Transmission Project or System Network Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, SERVICE AGREEMENT NO. 2605 information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 2 contracts

Samples: Service Agreement, Service Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service serviceCon Edison shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the theany Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 2 contracts

Samples: Service Agreement, Service Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(iesfacility (ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment a Party's Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the anotherthe other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOPartiesParty, to the extent such information is known, information on the nature of the Emergency StateCondition, if the outage is caused by an Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage, if requested by a Party, which may be provided by e-mail or facsimile.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, www3.sce.com

Outage Restoration. If an outage on the a Party’s Interconnectionthe Attachment Facilities or System Network UpgradesSystem Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency StateConditionState , an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Interconnection Agreement

Outage Restoration. If an outage on either the Attachment Interconnection Customer’s or Transmission Owner’s Interconnection Facilities, Network Upgrades, System Protection Facilities or System Upgrade Facilities or System Deliverability Distribution Upgrades of the Connecting Transmission Owner or Developer adversely affects the other a Party’s operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParties, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be FERC Electric Tariff Generator Interconnection Agreement (GIA) ATTACHMENTS 92.0.0 followed up as soon as practicable with written notice to the other Parties explaining the nature of the outage.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.. SERVICE AGREEMENT NO. 2356

Appears in 1 contract

Samples: Service Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer DeveloperInterconnection Customer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Sithe Interconnection Agreement

Outage Restoration. If an outage on the Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.outage.‌

Appears in 1 contract

Samples: , and Construction Agreement

Outage Restoration. If an outage on the Attachment AttachmentNYPA Transmission Facilities or System SystemNetwork Upgrade Facilities or System Deliverability Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s operations or facilities, the Party that owns the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns the facility that is out of service shall provide the other Party and NYISO, to the extent such information is known, information on the nature of the Emergency or Emergency State, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Service Agreement

Outage Restoration. If an outage on the Attachment a Party's Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParty, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.outage.‌

Appears in 1 contract

Samples: Clustering Large Generator Interconnection

Outage Restoration. If an outage on the Attachment Interconnection Facilities or System Upgrade Facilities Network Upgrades owned or System Deliverability Upgrades of the Connecting Transmission Owner or Developer controlled by a Party adversely affects the other another Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(iesfacility(s) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOwhose operations or facilities are adversely affected, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Outage Restoration. If an outage on the Attachment a Party's Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParty, to the extent such information is known, information on the nature of the Emergency StateCondition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.. 44

Appears in 1 contract

Samples: Interconnection Agreement

Outage Restoration. If an outage on the Attachment a Party’s Interconnection Facilities or System Upgrade Facilities or System Deliverability Network Upgrades of the Connecting Transmission Owner or Developer adversely affects the other another Party’s operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party and NYISOParties, to the extent such information is known, information on the nature of the Emergency StateCondition, if the outage is caused by an Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage. if requested by a Party, which may be provided by e-mail or facsimile.

Appears in 1 contract

Samples: Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!