Outage Restoration. If an outage on a Party’s Interconnection Facilities adversely affects the other Party’s operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of an Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement

AutoNDA by SimpleDocs

Outage Restoration. If an outage on a Party’s 's Interconnection Facilities Facilities, Distribution Upgrades, or Network Upgrades adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of an Emergency Conditionthe Emergency, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement

Outage Restoration. If an outage on of a Party’s Interconnection Facilities adversely facility(ies) aversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility facility(ies) that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of an the Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 2 contracts

Samples: Interconnection Agreement, Interconnection Agreement

Outage Restoration. If an outage on a Party’s 's Interconnection Facilities or Network Upgrades adversely affects the other another Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal xxxxx l operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other PartyParties, to the extent such information is known, information on the nature of an the Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Outage Restoration. If an outage on a Party’s 's Interconnection Facilities or Network Upgrades adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) Interconnection Facilities or Network Upgrades to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of an the Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Outage Restoration. If an outage on a Party’s Interconnection Facilities or Upgrades adversely affects the other Party’s operations or facilities, the Party that owns or controls the facility that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of an the Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Outage Restoration. If an outage on of a Party’s Interconnection Facilities facility(ies) adversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility facility(ies) that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of an the Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.

Appears in 1 contract

Samples: Interconnection Agreement

Outage Restoration. If an outage on of a Party’s Interconnection Facilities adversely facility(ies) averselyadversely affects the other Party’s 's operations or facilities, the Party that owns or controls the facility facility(ies) that is out of service shall use Reasonable Efforts to promptly restore such facility(ies) to a normal operating condition consistent with the nature of the outage. The Party that owns or controls the facility that is out of service shall provide the other Party, to the extent such information is known, information on the nature of an the Emergency Condition, an estimated time of restoration, and any corrective actions required. Initial verbal notice shall be followed up as soon as practicable with written notice explaining the nature of the outage.