Common use of Pass-Through Claims Clause in Contracts

Pass-Through Claims. In the event of any dispute or claim between Contractor and Owner which directly or indirectly involves the Work performed or to be performed by Subcontractor, or in the event of any dispute or claim between Contractor and Subcontractor caused by or arising out of conduct for which Owner may be responsible, Subcontractor agrees to be bound to Contractor and Contractor agrees to he bound to Subcontractor to the same extent that Contractor is bound to Owner by the terms of the Main Contract and by any and all procedures and resulting decisions, findings, determinations, or awards made thereunder by the person so authorized in the Main Contract, or by an administrative agency, board, court of competent jurisdiction or arbitration. If any dispute or claim of Subcontractor is prosecuted or defended by Contractor together with disputes or claims of Contractor’s own, and Subcontractor is not directly a party, Subcontractor agrees to cooperate fully with Contractor and to furnish all documents, statements, witnesses, and other information required by Contractor for such purpose and shall pay or reimburse Contractor for all expenses and costs, including reasonable attorneys’ fees incurred in connection therewith, to the extent of Subcontractor’s interest in such claim or dispute. Subcontractor agrees to be bound by the procedure and final determinations as specified in the Main Contract and agrees that it will not take, or will suspend, any other action or actions (including but not limited to any arbitration(s) or action(s) commenced pursuant to the Federal Xxxxxx Act, state lien statutes, Bond or Retainage Act(s)) with respect to any such claims and will pursue no independent litigation with respect thereto, pending final determination of any dispute resolution procedure between Owner and Contractor. It is expressly understood and agreed that as to any and all claims asserted by Subcontractor in connection with this project arising from the actions or fault of Owner, Contractor shall not be liable to Subcontractor for any greater amount than Owner is liable to Contractor, less any markups or costs incurred by Contractor. As to any claims asserted by Subcontractor for or on account of acts or omissions of Owner or its agents or design professionals, at the sole option of Contractor, Subcontractor agrees to prosecute such claims in Contractor’s name. For any amount recovered or collected (whether through proceedings or settlement) by Subcontractor, Contractor shall be entitled to 10% of such amount received or collected as its xxxx-up for such claims. Subcontractor shall have full responsibility for preparation and presentation of such claims and shall bear expenses thereof including attorneys’ fees.

Appears in 2 contracts

Samples: Subcontract Agreement, Subcontract Agreement

AutoNDA by SimpleDocs

Pass-Through Claims. In the event of any dispute or claim between Contractor and Owner which directly or indirectly involves the Work performed or to be performed by Subcontractor, or in the event of any dispute or claim between Contractor and Subcontractor caused by or arising out of conduct for which Owner may be responsible, Subcontractor agrees to be bound to Contractor and Contractor agrees to he bound to Subcontractor to the same extent that Contractor is bound to Owner by the terms of the Main Contract and by any and all procedures and resulting decisions, findings, determinations, or awards made thereunder by the person so authorized in the Main Contract, or by an administrative agency, board, court of competent jurisdiction or arbitration. If any dispute or claim of Subcontractor is prosecuted or defended by Contractor together with disputes or claims of Contractor’s own, and Subcontractor is not directly a party, Subcontractor agrees to cooperate fully with Contractor and to furnish all documents, statements, witnesses, and other information required by Contractor for such purpose and shall pay or reimburse Contractor for all expenses and costs, including reasonable attorneys’ fees incurred in connection therewith, to the extent of Subcontractor’s interest in such claim or dispute. Subcontractor agrees to be bound by the procedure and final determinations as specified in the Main Contract and agrees that it will not take, or will suspend, any other action or actions (including but not limited to any arbitration(s) or action(s) commenced pursuant to the Federal Xxxxxx Act, state lien statutes, Bond or Retainage Act(s)) with respect to any such claims and will pursue no independent litigation with respect thereto, pending final determination of any dispute resolution procedure between Owner and Contractor. It is expressly understood and agreed that as to any and all claims asserted by Subcontractor in connection with this project arising from the actions or fault of Owner, Contractor shall not be liable to Subcontractor for any greater amount than Owner is liable to Contractor, less any markups or costs incurred by Contractor. As to any claims asserted by Subcontractor for or on account of acts or omissions of Owner or its agents or design professionals, at the sole option of Contractor, Subcontractor agrees to prosecute such claims in Contractor’s name. For any amount recovered or collected (whether through proceedings or settlement) by Subcontractor, Contractor shall be entitled to 10% of such amount received or collected as its xxxxmark-up for such claims. Subcontractor shall have full responsibility for preparation and presentation of such claims and shall bear expenses thereof including attorneys’ fees.

Appears in 1 contract

Samples: Subcontract Agreement

AutoNDA by SimpleDocs

Pass-Through Claims. In the event of any dispute or claim between Contractor and Owner Owner, which directly or indirectly involves the Work work performed or to be performed by Subcontractor, or in the event of any dispute or claim between Contractor and Subcontractor caused by or arising out of conduct for which Owner may be responsible, Subcontractor agrees to shall be bound to Contractor Contractor, and Contractor agrees to he be bound to Subcontractor to the same extent that Contractor is bound to Owner by the terms of the Main Contract and by any and all procedures and resulting decisions, findings, determinations, or awards made thereunder by the person so authorized in the Main Contract, or Contract by an administrative agency, board, court of competent jurisdiction jurisdiction, or arbitration. If any dispute or claim of Subcontractor is prosecuted or defended by Contractor Contractor, together with disputes or claims of Contractor’s own, and Subcontractor is not directly a party, Subcontractor agrees to cooperate fully with Contractor and to furnish all documents, statements, witnesses, and other information required by Contractor for such purpose and shall pay or reimburse Contractor for all expenses and costs, including reasonable attorneys’ fees and expert fees incurred in connection therewith, to the extent of Subcontractor’s interest in such claim or dispute. Subcontractor agrees to shall be bound by the procedure and final determinations as specified in the Main Contract and agrees that it will not take, or will stay or suspend, any other action or actions (including but not limited to any arbitration(s) or action(s) commenced pursuant to the Federal Xxxxxx Act, state lien statutes, Bond or Retainage Act(s)) with respect to any such claims (including, but not limited to, actions commenced pursuant to the federal Xxxxxx Act, lien statutes, or any other state bond or retainage act) and will pursue no independent litigation with respect thereto, pending final determination of any dispute resolution procedure between Owner and Contractor. The timely presentation, cooperation, and participation by Subcontractor in any determination of a dispute under the Main Contract, including any and all appeals under the disputes provision(s) of the Main Contract, shall be conditions precedent to pursuit of any action by Subcontractor against Contractor with respect to any such claim or dispute. It is expressly understood and agreed that as to any and all claims asserted by Subcontractor in connection with this project Project arising from the actions or fault of Owner, Contractor shall not be liable to Subcontractor for any greater amount than Owner is liable to Contractor, less any markups or costs incurred by Contractor. As to any claims asserted by Subcontractor for or on account of acts or omissions of Owner or Owner, its agents or agents, design professionals, professionals at the sole option of Contractor, Subcontractor agrees to prosecute such claims in Contractor’s name. For any amount recovered or collected (whether through proceedings or settlement) by Subcontractor, Contractor shall be entitled to 10% of such amount received or collected as its xxxx-up markup for such claims. Subcontractor shall have full responsibility for preparation and presentation of such claims and shall bear expenses thereof including attorneys’ fees.

Appears in 1 contract

Samples: Subcontract Agreement