Common use of Payment for Material Stored On-Site Clause in Contracts

Payment for Material Stored On-Site. (a) Payment for the actual unit cost of materials suitably stored on the site of the Work (“Work Site”) and intended for incorporation in the Work will be made by the Owner to the Contractor subject to the provisions of Section 4.02 of this Contract, Section 90-07 of the FAA General Provisions, and the following conditions: (1) The Contractor shall furnish supporting evidence satisfactory to the Owner evidencing the cost of the materials and shipment to the Work Site. (2) The materials shall not be stored on the Work Site for more than ninety (90) calendar days before they are installed without the written consent of the Owner. (3) The materials shall be stored on the Work Site in accordance with applicable recommendations of the manufacturer and the instructions of the Owner. (4) A representative of the Owner or Engineer may inspect and inventory any stored materials. (b) Payment will not be made for materials stored away from the Work Site without the written consent of Owner. In the event that the Owner consents to payment for materials stored off-site, such payment shall be conditioned upon submission by the Contractor of bills of sale or such other documentation satisfactory to the Owner to establish the title of the Owner to such materials or equipment, and the submission of satisfactory insurance certificates for the stored materials. (c) Notwithstanding any provision herein to the contrary, if payments are to be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the Work Site, such payments shall be conditioned upon submission by the Contractor of bills of sale or such other documentation satisfactory to the Owner to establish the title of the Owner to such materials or equipment, and the submission of satisfactory insurance certificates for the stored materials to protect the interest of the Owner. (d) Regardless of ownership or insurance, the Contractor shall remain the guardian and protector of all materials and equipment stored or incorporated into the Work.

Appears in 3 contracts

Samples: Lump Sum Construction Contract, Lump Sum Construction Contract, Lump Sum Construction Contract

AutoNDA by SimpleDocs

Payment for Material Stored On-Site. (a) Payment for the actual unit cost of materials suitably stored on the site of the Work (“Work Site”) and intended for incorporation in the Work will be made by the Owner to the Contractor subject to the provisions of Section 4.02 of this Contract, Section 90-07 of the FAA General Provisions, and the following conditions: (1) The Contractor shall furnish supporting evidence satisfactory to the Owner evidencing the cost of the materials and shipment to the Work Sitework site. (2) The materials shall not be stored on the Work Site work site for more than ninety (90) calendar days before they are installed without the written consent of the Owner. (3) The materials shall be stored on the Work Site work site in accordance with applicable recommendations of the manufacturer and the instructions of the Owner. (4) A representative of the Owner or Engineer may inspect and inventory any stored materials. (b) Payment will not be made for materials stored away from the Work Site work site without the written consent of Owner. In the event that the Owner consents to payment for materials stored off-site, such payment shall be conditioned upon submission by the Contractor of bills of sale or such other documentation satisfactory to the Owner to establish the title of the Owner to such materials or equipment, and the submission of satisfactory insurance certificates for the stored materials. (c) Notwithstanding any provision herein to the contrary, if payments are to be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the Work Sitework site, such payments shall be conditioned upon submission by the Contractor of bills of sale or such other documentation satisfactory to the Owner to establish the title of the Owner to such materials or equipment, and the submission of satisfactory insurance certificates for the stored materials to protect the interest of the Owner. (d) Regardless of ownership or insurance, the Contractor shall remain the guardian and protector of all materials and equipment stored or incorporated into the Work.

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!