Payment Milestone. 3: subject to the provisions of art. 12.2 hereof, payment of Euro 2,030.00 per kWp (two thousand thirty) shall become due on occurrence of all the following events: (v) satisfactory outcome of the Operational Inspection and issuance of the PAC; (vi) all conditions precedent to Payment Milestones 1 and 2 are in place and valid; (vii) delivery by the Contractor to the Principal of the Warranty Bond, provided that the Warranty Bond shall become effective on payment of Payment Milestone 3 by the Principal. The Contractor shall deliver to the Principal the Warranty Bond, amounting to 15% (fifteen per cent) of the Consideration, to guarantee the due performance of any and all the obligations undertaken by the Contractor under the EPC Contract at the moment of PAC. The Warranty Bond shall be definitively released upon issuance of the FAC, provided that the insurance bond under the O&M contract is issued by the Contractor. 4.3 Once the Contractor believes that any of the Payment Milestones set out under Article 4.2 has been achieved, it shall so notify the Principal in writing. Within 5 (five) Working Days from receipt of the notice, the Principal shall inspect the Works and verify that the relevant Payment Milestone has been achieved. In the event of objection, the Principal shall indicate to the Contractor the works pending performance for that Payment Milestone. In the event that no objection is raised in writing by the Principal within such term, the relevant Payment Milestone shall be deemed approved. Payment shall be made within 5 (five) Working Days of the date of receipt by the Principal of the invoice in relation to Payment Milestone 1 and within 15 (fifteen) Working Days in relation to other Payment Milestones. The relevant invoice may not be issued prior to confirmation under the preceding paragraph, and prior to issuance of the TAC with regard to Payment Milestone 2 and prior to issuance of the PAC with regard to Payment Milestone 3, as set forth in detail under Article 12. The Parties agree that the payments of the Payment Milestone, for which the Principal shall issue a wire transfer confirmation, shall constitute mere advance payments and not the single lots in which the Parties intended dividing up the Works, with the exclusion, therefore, of the provision contained in the second paragraph of Article 1666 of the Civil Code. 4.4 The Parties agree and accept that the Consideration provided in the Contract is fixed and cannot be amended, save as provided in Article 10 of the Contract. Accordingly, the Parties have agreed to exclude the applicability of the Civil Code and every other provision that would entitle the Contractor to obtain a price review in the Contract in order to construct the Works. Save for art. 10 hereof, the risk related to the events referred to in Article 1664 of the Civil Code (burdensomeness or difficulty in performance: i.e. due to an increase of the cost of works and/or materials, or particular performance difficulties due to geological, hydraulic, etc.) and Article 1467 of the Civil Code is fully and expressly undertaken by the Contractor. 4.5 It is understood that, in the case of delay in payment of at least 30 days, the Principal must pay the Contractor interest on arrears as provided for by Legislative Decree 231/2002.
Appears in 2 contracts
Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)
Payment Milestone. 3: subject to the provisions of art. 12.2 hereof, payment of Euro 2,030.00 per kWp (two thousand thirty) shall become due on occurrence of all the following events:
(vi) satisfactory outcome of the Operational Inspection and issuance of the PAC;
(viii) all conditions precedent to Payment Milestones 1 and 2 are in place and valid;
(viiiii) delivery by the Contractor to the Principal of the Warranty Bond, provided that the Warranty Bond shall become effective on payment of Payment Milestone 3 by the Principal. The Contractor shall deliver to the Principal the Warranty Bond, amounting to 15% (fifteen per cent) of the Consideration, to guarantee the due performance of any and all the obligations undertaken by the Contractor under the EPC Contract at the moment of PAC. The Warranty Bond shall be definitively released upon issuance of the FAC, provided that the insurance bond under the O&M contract is issued by the Contractor.
4.3 Once the Contractor believes that any of the Payment Milestones set out under Article 4.2 has been achieved, it shall so notify the Principal in writing. Within 5 (five) Working Days from receipt of the notice, the Principal shall inspect the Works and verify that the relevant Payment Milestone has been achieved. In the event of objection, the Principal shall indicate to the Contractor the works pending performance for that Payment Milestone. In the event that no objection is raised in writing by the Principal within such term, the relevant Payment Milestone shall be deemed approved. Payment shall be made within 5 (five) Working Days of the date of receipt by the Principal of the invoice in relation to Payment Milestone 1 and within 15 (fifteen) Working Days in relation to other Payment Milestones. The relevant invoice may not be issued prior to confirmation under the preceding paragraph, and prior to issuance of the TAC with regard to Payment Milestone 2 and prior to issuance of the PAC with regard to Payment Milestone 3, as set forth in detail under Article 12. The Parties agree that the payments of the Payment Milestone, for which the Principal shall issue a wire transfer confirmation, shall constitute mere advance payments and not the single lots in which the Parties intended dividing up the Works, with the exclusion, therefore, of the provision contained in the second paragraph of Article 1666 of the Civil Code.
4.4 The Parties agree and accept that the Consideration provided in the Contract is fixed and cannot be amended, save as provided in Article 10 of the Contract. Accordingly, the Parties have agreed to exclude the applicability of the Civil Code and every other provision that would entitle the Contractor to obtain a price review in the Contract in order to construct realise the Works. Save for art. 10 hereof, the risk related to the events referred to in Article 1664 of the Civil Code (burdensomeness or difficulty in performance: i.e. due to an increase of the cost of works and/or materials, or particular performance difficulties due to geological, hydraulic, etc.) and Article 1467 of the Civil Code is fully and expressly undertaken by the Contractor.
4.5 It is understood that, in the case of delay in payment of at least 30 days, the Principal must pay the Contractor interest on arrears as provided for by Legislative Decree 231/2002.
Appears in 2 contracts
Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)