Common use of Payment of Liquidated Damages Clause in Contracts

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Section 7.3 Liquidated Damages is $1,500 per calendar day.

Appears in 4 contracts

Samples: www.courts.ca.gov, www.courts.ca.gov, www.courts.ca.gov

AutoNDA by SimpleDocs

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 2,000.00 per calendar day.

Appears in 3 contracts

Samples: Agreement, www.courts.ca.gov, www.courts.ca.gov

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 $ per calendar day.

Appears in 1 contract

Samples: www.courts.ca.gov

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $$1,500 per calendar day.

Appears in 1 contract

Samples: Standard Agreement

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 2,000.00 per calendar day. Liquidated Damages will not apply to Maintenance Phase-out.

Appears in 1 contract

Samples: www.courts.ca.gov

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Constriction (Document 00700) Section 7.3 Liquidated Damages is $1,500 3,000 per calendar day.

Appears in 1 contract

Samples: www.courts.ca.gov

AutoNDA by SimpleDocs

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Section 7.3 Liquidated Damages is $1,500 1,000 per calendar day.

Appears in 1 contract

Samples: Standard Agreement

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 5,000.00 per calendar day.

Appears in 1 contract

Samples: Agreement

Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 2000.00 per calendar day.

Appears in 1 contract

Samples: www.courts.ca.gov

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!