Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Section 7.3 Liquidated Damages is $1,500 per calendar day.
Appears in 4 contracts
Samples: www.courts.ca.gov, www.courts.ca.gov, www.courts.ca.gov
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 2,000.00 per calendar day.
Appears in 3 contracts
Samples: Agreement, www.courts.ca.gov, www.courts.ca.gov
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 $ per calendar day.
Appears in 1 contract
Samples: www.courts.ca.gov
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $$1,500 per calendar day.
Appears in 1 contract
Samples: Standard Agreement
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 2,000.00 per calendar day. Liquidated Damages will not apply to Maintenance Phase-out.
Appears in 1 contract
Samples: www.courts.ca.gov
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Constriction (Document 00700) Section 7.3 Liquidated Damages is $1,500 3,000 per calendar day.
Appears in 1 contract
Samples: www.courts.ca.gov
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Section 7.3 Liquidated Damages is $1,500 1,000 per calendar day.
Appears in 1 contract
Samples: Standard Agreement
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 5,000.00 per calendar day.
Appears in 1 contract
Samples: Agreement
Payment of Liquidated Damages. 1. The liquidated damages for the Contractor’s failure to complete Work of the Project within the construction duration as agreed and determined at the commencement of the Project pursuant to 00700 Exhibit H, General Conditions of The Contract for Construction (Document 00700) Section 7.3 Liquidated Damages is $1,500 2000.00 per calendar day.
Appears in 1 contract
Samples: www.courts.ca.gov