Performance Bank Guarantee (PBG). 2.5.1. The Performance Bank Guarantee furnished under this Agreement shall be for guaranteeing the successful commissioning of the Project for power up to the Contracted Capacity within the time specified in this Agreement. 2.5.2. The failure on the part of the SPG to furnish and maintain the Performance Bank Guarantee shall be a material breach of the term of this Agreement on the part of the SPG. 2.5.3. The PBG shall be initially valid from the date of issue until 2 months (i.e. sixty (60) days) beyond the 9 months from the date of signing of Power Purchase Agreement (PPA). 2.5.4. The PBG will be returned to the SPG after successful commissioning of Solar power plant, after taking into account any penalties due to delay in commissioning as per terms and conditions of RfS. 2.5.5. CFA up to 100% of the total eligible CFA will be released to the RESCO developer through DISCOM on successful operation and performance of solar plant for two months after the commissioning with at least one month CUF as per minimum CUF agreed in PPA, as per MNRE’s sanction for the CFA, subject to release of the same by MNRE-GoI 2.5.6. On
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Performance Bank Guarantee (PBG). 2.5.1. The Performance Bank Guarantee furnished under this Agreement shall be for guaranteeing the successful commissioning of the Project for power up to the Contracted Capacity within the time specified in this Agreement.
2.5.2. The failure on the part of the SPG to furnish and maintain the Performance Bank Guarantee shall be a material breach of the term of this Agreement on the part of the SPG.
2.5.3. The PBG shall be initially valid from the date of issue until 2 months (i.e. sixty (60) days) beyond the 9 months from the date of signing of Power Purchase Agreement (PPA).
2.5.4. The PBG will be returned to the SPG after successful commissioning of Solar power plant, after taking into account any penalties due to delay in commissioning as per terms and conditions of RfS.
2.5.5. CFA up to 100% of the total eligible CFA will be released to the RESCO developer through DISCOM PGVCL on successful operation and performance of solar plant for two months after the commissioning with at least one month CUF as per minimum CUF agreed in PPA, as per MNRE’s sanction for the CFA, subject to release of the same by MNRE-GoI
2.5.6. On
Appears in 2 contracts
Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement (Ppa)
Performance Bank Guarantee (PBG). 2.5.1. The Performance Bank Guarantee furnished under this Agreement shall be for guaranteeing the successful commissioning of the Project for power up to the Contracted Capacity within the time specified in this Agreement.
2.5.2. The failure on the part of the SPG to furnish and maintain the Performance Bank Guarantee shall be a material breach of the term of this Agreement on the part of the SPG.
2.5.3. The PBG shall be initially valid from the date of issue until 2 months (i.e. sixty (60) days) beyond the 9 months from the date of signing of Power Purchase Agreement (PPA).
2.5.4. The PBG will be returned to the SPG after successful commissioning of Solar power plant, after taking into account any penalties due to delay in commissioning as per terms and conditions of RfS.
2.5.5. CFA up to 100% of the total eligible CFA will be released to the RESCO developer through DISCOM on successful operation and performance of solar plant for two months after the commissioning with at least one month CUF as per minimum CUF agreed in PPA, as per MNRE’s sanction for the CFA, subject to release of the same by MNRE-GoI
2.5.6. On
Appears in 1 contract
Samples: Power Purchase Agreement (Ppa)
Performance Bank Guarantee (PBG). 2.5.1. The Performance Bank Guarantee furnished under this Agreement shall be for guaranteeing the successful commissioning of the Project for power up to the Contracted Capacity within the time specified in this Agreement.
2.5.2. The failure on the part of the SPG to furnish and maintain the Performance Bank Guarantee shall be a material breach of the term of this Agreement on the part of the SPG.
2.5.3. The PBG shall be initially valid from the date of issue until 2 months (i.e. sixty (60) days) beyond the 9 months from the date of signing of Power Purchase Agreement (PPA).
2.5.4. The PBG will be returned to the SPG after successful commissioning of Solar power plant, after taking into account any penalties due to delay in commissioning as per terms and conditions of RfS.
2.5.5. CFA up to 100% of the total eligible CFA will be released to the RESCO developer through DISCOM UGVCL on successful operation and performance of solar plant for two months after the commissioning with at least one month CUF as per minimum CUF agreed in PPA, as per MNRE’s sanction for the CFA, subject to release of the same by MNRE-GoI
2.5.6. On
Appears in 1 contract
Samples: Power Purchase Agreement (Ppa)