Performance of EPC Services. The Transmission Developer shall perform the EPC Services, as set forth in Appendix A hereto, using Reasonable Efforts to complete the EPC Services by the Milestone dates set forth in Appendix A hereto. The Affected System Operator shall not be required to undertake any action which is inconsistent with its standard safety practices, its material and equipment specifications, its design criteria and construction procedures, its labor agreements, and Applicable Laws and Regulations. In the event the Transmission Developer reasonably expects that it will not be able to complete the EPC Services by the specified dates, the Transmission Developer shall promptly provide written notice to the Affected System Operator and NYISO, and shall undertake Reasonable Efforts to meet the earliest dates thereafter. The NYISO has no responsibility, and shall have no liability, for the performance of any of the EPC Services under this Agreement.
Appears in 3 contracts
Samples: Engineering, Procurement, and Construction Agreement, Service Agreement, Engineering, Procurement, and Construction Agreement
Performance of EPC Services. The Transmission Developer shall perform the EPC Services, as set forth in Appendix A hereto, using Reasonable Efforts to complete the EPC Services by the Milestone dates set forth in Appendix A hereto. The Affected System Operator shall not be required to undertake any action which is inconsistent with its standard safety practices, its material and equipment specifications, its design criteria and construction procedures, its labor agreements, and Applicable Laws and Regulations. In the event the Transmission Developer reasonably expects that it will not be able to complete the EPC Services by the specified dates, the Transmission Developer shall promptly provide written notice to the Affected System Operator and NYISO, and shall undertake Reasonable Efforts to meet the earliest dates thereafter. The NYISO has no responsibility, and shall have no liability, for the performance of any of the EPC Services under this Agreement.
Appears in 1 contract
Samples: Engineering, Procurement, and Construction Agreement
Performance of EPC Services. The Transmission Developer shall perform the EPC Services, as set forth in Appendix A hereto, using Reasonable Efforts to complete the EPC Services by the Milestone dates set forth in Appendix A hereto. The Affected System Operator Developer shall not be required to undertake any action which is inconsistent with its the Affected System Operator’s standard safety practices, its material and equipment specifications, its design criteria and construction procedures, its labor agreements, and Applicable Laws and Regulations. In the event the Transmission Developer reasonably expects that it will not be able to complete the EPC Services by the specified dates, the Transmission Developer shall promptly provide written notice to the Affected System Operator and NYISO, and shall undertake Reasonable Efforts to meet the earliest dates thereafter. The NYISO has no responsibility, and shall have no liability, for the performance of any of the EPC Services under this Agreement.
Appears in 1 contract
Samples: Engineering, Procurement, and Construction Agreement