Permitted Changes. There will be no changes to the Project Objective, including the Target Cost, Contract Time, or the ICL unless one of the following conditions occur: 12.1.1 Owner-Elected Changes; 12.1.2 Owner’s Directive; 12.1.3 Unforeseen and Differing Site Conditions; 12.1.4 Post Permit Changes; 12.1.5 Owner’s suspension of the Work per Section 17.2; and/or 12.1.6 Reconciliation of allowance items to actual cost.
Appears in 3 contracts
Samples: Integrated Project Delivery Agreement, Integrated Project Delivery Agreement, Integrated Project Delivery Agreement
Permitted Changes. There will be no changes to the Project Objective, including the Target Cost, Contract Time, or the ICL unless one of the following conditions occur:
12.1.1 11.1.1 Owner-Elected Changes;
12.1.2 11.1.2 Owner’s Directive;
12.1.3 11.1.3 Unforeseen and Differing Site Conditions;
12.1.4 11.1.4 Post Permit Changes;
12.1.5 11.1.5 Owner’s suspension of the Work per Section 17.2; and/or16.2;
12.1.6 11.1.6 Reconciliation of allowance Allowance items to actual cost; or
11.1.7 Permitted Delays per Section 10.5, except Force Majeure.
Appears in 1 contract