Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be: 1. Permits and applicable regulations as may be provided by law or that govern the site; 2. Amendments and Change Orders; 3. Contract; 4. Addenda and Bulletins; 5. Supplementary General Conditions;
Appears in 2 contracts
Samples: Construction Phase Services, Construction Phase Services
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments Use of Contingency or Change Orders - in inverse chronological order, and Change Orders;in the same order as specific portions they are modifying (i.e., later-issued language shall take precedence and prevail over earlier conflicting versions or language).
3. Contract;
4. Addenda and BulletinsSupplemental General Conditions;
5. Supplementary General Conditions;
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments and Change Orders;
3. Contract;
4. Addenda and Bulletins;
5. Supplementary General Conditions;
Appears in 2 contracts
Samples: Construction Contract, Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments and Change Orders;
3. ContractAgreement;
4. Bid, as accepted by County;
5. Addenda and Bulletins;
56. Supplementary General ConditionsSpecial Provisions;
Appears in 1 contract
Samples: Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments Use of Contingency or Change Orders - in inverse chronological order, and Change Ordersin the same order as specific portions they are modifying (i.e., later-issued language shall take precedence and prevail over earlier conflicting versions or language);
3. Contract;
4. Addenda and Bulletins;
5. Supplementary General Conditions;
Appears in 1 contract
Samples: Construction Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments and Change Orders;
3. Contract;
4. Addenda and Bulletins;
5. Supplementary General Conditions;
6. General Conditions;
Appears in 1 contract
Samples: Construction Services Contract
Precedence of Contract Documents. If there is a conflict among Contract Documents, the document highest in precedence shall control. The precedence shall be:
1. a) Permits and applicable regulations as may be provided by law or that govern the site;
2. Amendments b) Use of Contingency or Change Orders - in inverse chronological order, and Change Orders;in the same order as specific portions they are modifying (i.e., later-issued language shall take precedence and prevail over earlier conflicting versions or language).
3. c) Contract;
4. Addenda and Bulletins;
5. d) Supplementary General Conditions;
e) General Conditions;
Appears in 1 contract
Samples: Design and Construction Agreement