Pricing of Delay Claims. Subject to Sections 13.4.3 and 13.5 above, Contractor will be entitled to an equitable adjustment for time-related Project overhead costs for compensable Excusable Delays. Once the Baseline Schedule is approved, the parties agree to negotiate in good faith and attempt to reach agreement on daily rates that will apply for such time-related Project overhead costs.
Appears in 3 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Pricing of Delay Claims. Subject to Sections 13.4.3 and 13.5 above, Contractor will be entitled to an equitable adjustment for time-related Project overhead costs for compensable Excusable Delays. Once the Baseline Schedule is approved, the parties agree to negotiate in good faith and attempt to reach agreement on daily rates that will apply for such time-related Project overhead costs.