Processing Of Submittals Clause Samples
The "Processing Of Submittals" clause defines the procedures and requirements for reviewing and approving documents, samples, or other materials that a contractor must submit to the project owner or architect. Typically, this clause outlines the types of submittals required, the timelines for submission and review, and the responsibilities of each party in the approval process. For example, it may specify that shop drawings, product data, or material samples must be submitted for review before installation. The core function of this clause is to ensure that all materials and methods used in the project meet the contract requirements and design intent, thereby reducing the risk of errors, rework, or disputes during construction.
Processing Of Submittals. The Construction Manager shall in timely fashion review, approve if appropriate and forward submittals to the Professional(s) for review and approval along with such detail and information as the Professional requires. No part of the Work dealt with by a submittal shall be fabricated or performed until such approval has been given.
7.2.1 A Professional is responsible to the Owner, but not to the Construction Manager, to verify that the submittals conform to the design concept and functional requirements of the plans and specifications, that the detailed design portrayed in shop drawings and proposed equipment and materials shown in submittals are of the quality specified and will function properly, and that the submittals comply with the Contract for Construction Management.
7.2.2 The Construction Manager shall perform no portion of the Work for which the Contract Documents require submittal and review of shop drawings, product data, samples or similar submittals until the respective submittal has been approved by the Professional. The Work shall then be performed in accordance with the approved submittals except that the Construction Manager shall not be relieved of responsibility for deviations from requirements of the Contract Documents by the Professional’s approval of shop drawings, product data, samples or similar submittals unless the Construction Manager has specifically informed the Professional in writing of such deviation at the time of submittal and
(i) the Professional has given written approval to the specific deviation as a minor change in the Work; or (ii) a change order or construction change directive has been issued authorizing the deviation. The Construction Manager shall not be relieved of responsibility for errors or omissions in shop drawings, product data, samples or similar submittals by the Professional’s approval thereof.
Processing Of Submittals. The Contractor shall in timely fashion review, approve if appropriate and forward submittals to the Design Professional for review and approval along with such detail and information as the Professional requires. No part of the Work dealt with by a submittal shall be fabricated or performed until such approval has been given.
7.2.1 A Professional is responsible to the Owner, but not to the Contractor, to verify that the submittals conform to the design concept and functional requirements of the plans and specifications, that the detailed design portrayed in shop drawings and proposed equipment and materials shown in submittals are of the quality specified and will function properly, and that the submittals comply with the Agreement.
7.2.2 All Work shall be performed in accordance with approved submittals. Approval of submittals by a Professional shall not relieve the Contractor from complying with this Agreement, including all plans and specifications, except as changed by Change Order.
Processing Of Submittals. The DB shall in timely fashion review, approve if appropriate and forward submittals to the Owner for review and approval along with such detail and information as the Owner requires. No part of the Work dealt with by a submittal shall be fabricated or performed until such approval has been given.
7.2.1 The Owner is not responsible to the DB to verify that the submittals conform to the design concept and functional requirements of the plans and specifications, that the detailed design portrayed in shop drawings and proposed equipment and materials shown in submittals are of the quality specified and will function properly, and that the submittals comply with this Contract.
7.2.2 All Work shall be performed in accordance with approved submittals. Approval of submittals by the Owner shall not relieve the DB from complying with this Contract, including all plans and specifications, except as changed by Change Order.
Processing Of Submittals. The Builder shall in timely fashion review, approve if appropriate and forward submittals to the Architect for review and approval along with such detail and information as the Professional requires. No part of the Work dealt with by a submittal shall be fabricated or performed until such approval has been given.
Processing Of Submittals. The Construction Manager shall in timely fashion review, approve if appropriate and forward submittals to the Owner for review and approval along with such detail and information as the Owner requires. No part of the Work dealt with by a submittal shall be fabricated or performed until such approval has been given.
Processing Of Submittals. The CM shall in timely fashion review, approve if appropriate and forward submittals to the Design Professional for review and approval along with such detail and information as the Design Professional requires. No part of the Work dealt with by a submittal shall be fabricated or performed until such approval has been given.
7.2.1 The Design Professional is responsible to the Owner, but not to the CM, to verify that the submittals conform to the design concept and functional requirements of the
7.2.2 All Work shall be performed in accordance with approved submittals. Approval of submittals by the Design Professional shall not relieve the CM from complying with this Contract, including all plans and specifications, except as changed by Change Order.
Processing Of Submittals. The CM shall in timely fashion review, approve if appropriate and forward submittals to the Design Professional for review and approval along with such detail and information as the Design Professional requires. No part of the Work dealt with by a submittal shall be fabricated or performed until such approval has been given.
7.2.1 The Design Professional is responsible to the Owner, but not to the CM, to verify that the submittals conform to the design concept and functional requirements of the plans and specifications, that the detailed design portrayed in shop drawings and proposed equipment and materials shown in submittals are of the quality specified and will function properly, and that the submittals comply with this Contract.
7.2.2 All Work shall be performed in accordance with approved submittals. Approval of submittals by the Design Professional shall not relieve the CM from complying with this Contract, including all plans and specifications, except as changed by Change Order.
Processing Of Submittals. The DB shall in timely fashion review, approve if appropriate and forward submittals to the Owner for review and approval along with such detail and
7.2.1 The Owner is not responsible to the DB to verify that the submittals conform to the design concept and functional requirements of the plans and specifications, that the detailed design portrayed in shop drawings and proposed equipment and materials shown in submittals are of the quality specified and will function properly, and that the submittals comply with this Contract.
7.2.2 All Work shall be performed in accordance with approved submittals. Approval of submittals by the Owner shall not relieve the DB from complying with this Contract, including all plans and specifications, except as changed by Change Order.