PROJECT REPRESENTATION BEYOND BASIC SERVICES. 3.2.1 Unless otherwise included in Basic Services, the following services are considered to be additional services and are not included in the basic services: .1 Land surveys and topographical drawings, and geotechnical testing. .2 Provisions of services of consultants, which have been approved in advance by the Owner, for other than the normal architectural, structural, mechanical, civil, landscaping and electrical engineering services. .3 Providing services made necessary by the material default of the Contractor, by major defects or deficiencies in the Work of the Contractor, or by significant failure of performance of the Contractor under the Contract for Construction. .4 Provision of additional services made necessary by changes in the scope of work as directed by the Owner, provided such changes are not made necessary because of Engineer’s errors or omissions. With respect to Change Orders and Construction Change Directives that are not made necessary because of the Engineer’s errors or omissions, preparation of such documents for and evaluating such Change Orders and Construction Change Directives that cumulatively are no more then 10% of the Construction Cost of the Project are included in Basic Services. .5 Preparing to serve or serving as an expert witness when requested by the Owner in connection with any public hearing or legal proceeding. .6 Providing prolonged contract administration and observation of construction should the construction time exceed 125% of the original construction time for Substantial Completion when the additional time is not due to the failure of the Engineer to provide the services required under this contract in a timely manner including additional services as described herein. This provision does not cover administration of correction of listed deficiencies at the time of final occupancy inspection. .7 Providing consultation concerning replacement of any work damaged by fire or other casualty during construction and the warranty period and furnishing services as may be required in connection with the replacement of such work. .8 Providing design related services for unforeseen conditions discovered during the course of construction. .9 Providing services in connection with evaluating more than a reasonable number of substitutions proposed by the Contractor and making subsequent revisions to Drawings, Specifications and other documentation resulting therefrom.
Appears in 5 contracts
Samples: Standard Form of Agreement Between Owner and Engineer, Standard Form of Agreement Between Owner and Engineer for Structural Engineering Services, Standard Form of Agreement Between Owner and Engineer
PROJECT REPRESENTATION BEYOND BASIC SERVICES. 3.2.1 Unless otherwise included in Basic Services, the following services are considered to be additional services and are not included in the basic services:
.1 Land surveys and topographical drawings, and geotechnical testing.
.2 Provisions of services of consultants, which have been approved in advance by the Owner, for other than the normal architectural, structural, mechanical, civil, landscaping and electrical engineering services.
.3 Providing services made necessary by the material default of the Contractor, by major defects or deficiencies in the Work of the Contractor, or by significant failure of performance of the Contractor under the Contract for Construction.
.4 Provision of additional services made necessary by changes in the scope of work as directed by the Owner, provided such changes are not made necessary because of EngineerArchitect’s errors or omissions. With respect to Change Orders and Construction Change Directives that are not made necessary because of the EngineerArchitect’s errors or omissions, preparation of such documents for and evaluating such Change Orders and Construction Change Directives that cumulatively are no more then 10% of the Construction Cost of the Project are included in Basic Services.
.5 Preparing to serve or serving as an expert witness when requested by the Owner in connection with any public hearing or legal proceeding.
.6 Providing prolonged contract administration and observation of construction should the construction time exceed 125% of the original construction time for Substantial Completion when the additional time is not due to the failure of the Engineer Architect to provide the services required under this contract in a timely manner including additional services as described herein. This provision does not cover administration of correction of listed deficiencies at the time of final occupancy inspection.
.7 Providing consultation concerning replacement of any work damaged by fire or other casualty during construction and the warranty period and furnishing services as may be required in connection with the replacement of such work.
.8 Providing design related services for unforeseen conditions discovered during the course of construction.
.9 Providing services in connection with evaluating more than a reasonable number of substitutions proposed by the Contractor and making subsequent revisions to Drawings, Specifications and other documentation resulting therefrom.
Appears in 3 contracts
Samples: Architectural Services Agreement, Standard Form of Agreement Between Owner and Architect, Standard Form of Agreement Between Owner and Architect
PROJECT REPRESENTATION BEYOND BASIC SERVICES. 3.2.1 Unless otherwise included in Basic Services, the following services are considered to be additional services and are not included in the basic services:
.1 Land surveys and topographical drawings, and geotechnical testing.
.2 Provisions of services of consultants, which have been approved in advance by the Owner, for other than the normal architectural, structural, mechanical, civil, landscaping and electrical engineering services.
.3 Providing services made necessary by the material default of the Contractor, by major defects or deficiencies in the Work of the Contractor, or by significant failure of performance of the Contractor under the Contract for Construction.performance
.4 Provision of additional services made necessary by changes in the scope of work as directed by the Owner, provided such changes are not made necessary because of Engineer’s errors or omissions. With respect to Change Orders and Construction Change Directives that are not made necessary because of the Engineer’s errors or omissions, preparation of such documents for and evaluating such Change Orders and Construction Change Directives that cumulatively are no more then 10% of the Construction Cost of the Project are included in Basic Services.
.5 Preparing to serve or serving as an expert witness when requested by the Owner in connection with any public hearing or legal proceeding.
.6 Providing prolonged contract administration and observation of construction should the construction time exceed 125% of the original construction time for Substantial Completion when the additional time is not due to the failure of the Engineer to provide the services required under this contract in a timely manner including additional services as described herein. This provision does not cover administration of correction of listed deficiencies at the time of final occupancy inspection.
.7 Providing consultation concerning replacement of any work damaged by fire or other casualty during construction and the warranty period and furnishing services as may be required in connection with the replacement of such work.
.8 Providing design related services for unforeseen conditions discovered during the course of construction.
.9 Providing services in connection with evaluating more than a reasonable number of substitutions proposed by the Contractor and making subsequent revisions to Drawings, Specifications and other documentation resulting therefrom.
Appears in 2 contracts
Samples: Standard Form of Agreement Between Owner and Engineer for Civil Engineering Services, Standard Form of Agreement Between Owner and Engineer
PROJECT REPRESENTATION BEYOND BASIC SERVICES. 3.2.1 Unless otherwise included in Basic Services, the following services are considered to be additional services and are not included in the basic services:
.1 Land surveys and topographical drawings, and geotechnical testing.
.2 Provisions of services of consultants, which have been approved in advance by the Owner, for other than the normal architectural, structural, mechanical, civil, landscaping and electrical engineering services.
.3 Providing services made necessary by the material default of the Contractor, by major defects or deficiencies in the Work of the Contractor, or by significant failure of performance of the Contractor under the Contract for Construction.
.4 Provision of additional services made necessary by changes in the scope of work as directed by the Owner, provided such changes are not made necessary because of EngineerArchitect’s errors or omissions. With respect to Change Orders and Construction Change Directives that are not made necessary because of the Engineer’s errors or omissions, preparation of such documents for and evaluating such Change Orders and Construction Change Directives that cumulatively are no more then 10% of the Construction Cost of the Project are included in Basic Services.are
.5 Preparing to serve or serving as an expert witness when requested by the Owner in connection with any public hearing or legal proceeding.
.6 Providing prolonged contract administration and observation of construction should the construction time exceed 125% of the original construction time for Substantial Completion when the additional time is not due to the failure of the Engineer Architect to provide the services required under this contract in a timely manner including additional services as described herein. This provision does not cover administration of correction of listed deficiencies at the time of final occupancy inspection.
.7 Providing consultation concerning replacement of any work damaged by fire or other casualty during construction and the warranty period and furnishing services as may be required in connection with the replacement of such work.
.8 Providing design related services for unforeseen conditions discovered during the course of construction.
.9 Providing services in connection with evaluating more than a reasonable number of substitutions proposed by the Contractor and making subsequent revisions to Drawings, Specifications and other documentation resulting therefrom.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Architect