Project Schedule; Monthly Progress Reports. (a) [Within eight (8) weeks after the Effective Date,] Contractor shall prepare and submit to Owner for approval a complete “Level 3” working level critical path based in the Initial Project Schedule in sufficient detail acceptable to Owner, including identification of particular work tasks, durations and logical ties between activities (as further defined in the Scope of Work, the “Project Schedule”). Owner’s approval of the Project Schedule, which shall not be unreasonably withheld, conditioned or delayed, shall be a condition precedent to Owner’s approval of Contractor’s initial Request for Payment. Contractor shall perform the Work in accordance with the Project Schedule.