Project Timing and Budgets. The Construction Manager must provide the CM Services such that, except to the extent of events reasonably outside the Construction Manager’s control, the Project will be completed: (i) not later than the applicable milestone (if any) and final completion dates; and (ii) for total costs as are within the applicable Project Construction Budget (defined in Section 4.1 herein) and applicable Project Total Budget (defined in Section 4.2 herein).
Appears in 2 contracts
Samples: Construction Management Agreement, Construction Management Services Agreement
Project Timing and Budgets. The Construction Manager must provide the CM Services such that, except to the extent of events reasonably outside the Construction Manager’s control, the Project will be completed: (i) not later than the applicable milestone (if any) and final completion dates; and (ii) for total costs as are within the applicable Project Construction Budget (defined in Section 4.1 herein) and applicable Project Total Budget (defined in Section 4.2 herein).and
Appears in 2 contracts
Samples: Construction Management Agreement, Construction Management Services Agreement