Common use of Prolonged Suspension Clause in Contracts

Prolonged Suspension. If the suspension under sub-clause 8.8 [Suspension of Work] has continued for more than 120 days, the Contractor may request the Engineer's permission to proceed. If the Engineer-does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Engineer, treat the suspension of any part of the Works as an omission under clause 13 [Variation and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under sub-clause 16.2 [Termination by Contactor].

Appears in 5 contracts

Samples: Contract Agreement, Contract Agreement, Contract Agreement

AutoNDA by SimpleDocs

Prolonged Suspension. If the suspension under subSub-clause Clause 8.8 [Suspension of Work] has continued for more than 120 84 days, the Contractor may request the EngineerContract Awarder's permission to proceed. If the Engineer-Contract Awarder does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the EngineerContract Awarder, treat the suspension of any part of the Works as an omission under clause Clause 13 [Variation Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under subSub-clause Clause 16.2 [Termination by ContactorContractor].

Appears in 2 contracts

Samples: Contract Agreement (Renewable Fuel Corp), Contract Agreement (Renewable Fuel Corp)

Prolonged Suspension. If the suspension under subSub-clause Clause 8.8 [Suspension of Work] has continued for more than 120 that 84 days, the Contractor may request the Engineer's Engineer´s permission to proceed. If the Engineer-Engineer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Engineer, treat the suspension of any part of the Works as an omission under clause Clause 13 [Variation Variations and Adjustments] of the affected aftected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under subSub-clause Clause 16.2 [Termination by ContactorContractor].. 30 Conditions of Contract for Plant and Design-Build

Appears in 2 contracts

Samples: Contract Agreement, Contract Agreement

Prolonged Suspension. If the suspension under subSub-clause Clause 8.8 [Suspension of Work] has continued for more than 120 84 days, the Contractor may request the Engineer's ’s permission to proceed. If the Engineer-Engineer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Engineer, treat the suspension of any part of the Works as an omission under clause Clause 13 [Variation Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under subSub-clause Clause 16.2 [Termination by ContactorContractor].

Appears in 1 contract

Samples: Contract Agreement Unit Price Contract

AutoNDA by SimpleDocs

Prolonged Suspension. SAMPLE If the suspension under subSub-clause Clause 8.8 [Suspension of Work] has continued for more than 120 84 days, the Contractor may request the Engineer's ’s permission to proceed. If the Engineer-Engineer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Engineer, treat the suspension of any part of the Works as an omission under clause Clause 13 [Variation Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under subSub-clause Clause 16.2 [Termination by ContactorContractor].

Appears in 1 contract

Samples: Contract Agreement

Prolonged Suspension. If the suspension under subSub-clause Clause 8.8 [Suspension of Work] has continued for more than 120 84 days, the Contractor may request the EngineerEmployer's permission to proceed. If the Engineer-Employer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the EngineerEmployer, treat the suspension of any part of the Works as an omission under clause Clause 13 [Variation Variations and Adjustments] of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination under subSub-clause 16.2 Clause 15.10 [Termination by ContactorContractor's Rights].

Appears in 1 contract

Samples: Asia Satellite Telecommunications Holdings LTD