Provision and Removal of Equipment. 1. The Contractor shall provide all the Equipment necessary for the supply of the Services. The Contractor shall not deliver any Equipment nor begin any work on the Premises without obtaining prior written approval. 2. All Equipment brought onto the Premises shall be at the Contractor’s own risk. Unless otherwise agreed, Equipment brought onto the Premises will remain the property of the Contractor. The Contractor shall provide for the haulage or carriage to and the removal from the Premises of Equipment when no longer required at its sole cost. 3. The Contractor shall maintain all items of Equipment within the Premises in a safe, serviceable and clean condition. 4. The Contractor shall, at the Authority’s written request, at its own expense and as soon as reasonably possible: 4.1. remove from the Premises any Equipment which in the reasonable opinion of the Authority is either hazardous, noxious or not in accordance with the Contract; and 4.2. replace such item with a suitable substitute item of Equipment. 5. On completion of the Services the Contractor shall remove the Equipment together with any other materials used by the Contractor to supply the Services and shall leave the Premises in a clean, safe and tidy condition. The Contractor is solely responsible for making good any damage to the Premises or any objects contained thereon, other than fair wear and tear, which is caused by the Contractor or any Contractor’s Personnel.
Appears in 12 contracts
Samples: Facilities Management Agreement, Contract for the Provision of a Prison Link Support Worker, Contract for Technical Assistance
Provision and Removal of Equipment. 1. C3.1 The Contractor shall provide all the Equipment necessary for the supply of the Services. The Contractor shall not deliver any Equipment nor begin any work on the Premises without obtaining prior written approval.
2. C3.2 All Equipment brought onto the Premises shall be at the Contractor’s own risk. Unless otherwise agreed, Equipment brought onto the Premises will remain the property of the Contractor. The Contractor shall provide for the haulage or carriage to and the removal from the Premises of Equipment when no longer required at its sole cost.
3. C3.3 The Contractor shall maintain all items of Equipment within the Premises in a safe, serviceable and clean condition.
4. C3.4 The Contractor shall, at the Authority’s written request, at its own expense and as soon as reasonably possible:
4.1. 4.1 remove from the Premises any Equipment which in the reasonable opinion of the Authority is either hazardous, noxious or not in accordance with the Contract; and
4.2. 4.2 replace such item with a suitable substitute item of Equipment.
5. C3.5 On completion of the Services the Contractor shall remove the Equipment together with any other materials used by the Contractor to supply the Services and shall leave the Premises in a clean, safe and tidy condition. The Contractor is solely responsible for making good any damage to the Premises or any objects contained thereon, other than fair wear and tear, which is caused by the Contractor or any Contractor’s Personnel.
Appears in 11 contracts
Samples: Contract for the Provision of Building Services, Contract for the Provision of Building Services, Contract Letter
Provision and Removal of Equipment. 1. The Contractor 5.2.1 Unless otherwise stated in the Order Form, the Supplier shall provide all the Equipment necessary for the supply of the Services. The Contractor shall not deliver any Equipment nor begin any work on the Premises without obtaining prior written approval.
2. All Equipment brought onto the Premises shall be at the Contractor’s Supplier's own risk. Unless otherwise agreed, risk and the Customer shall have no liability for any loss of or damage to any Equipment brought onto unless and to the extent that the Supplier is able to demonstrate that such loss or damage was caused by or contributed to by the Customer's Default.
5.2.2 The Supplier shall not begin any work at the Premises will remain the property of the Contractor. The Contractor shall provide for the haulage or carriage to and the removal from the Premises of Equipment when no longer required at its sole costwithout obtaining Approval.
3. 5.2.3 The Contractor Supplier shall maintain all items of Equipment within the Premises in a safe, serviceable and clean condition.
4. The Contractor Supplier shall, at the Authority’s Customer's written request, at its own expense and as soon as reasonably possible:
4.1. practicable remove from the Premises and replace any Equipment which in the reasonable opinion of the Authority Customer is either hazardous, noxious or not in accordance with the Contract; and
4.2. replace such item with a suitable substitute item of Equipment.
5. On completion 5.2.4 Upon termination or expiry of the Services Contract, the Contractor Supplier shall remove the Equipment together with any other materials used by the Contractor Supplier to supply the Services and shall leave the Premises in a clean, safe and tidy condition. The Contractor Supplier is solely responsible for making good any damage to the Premises or any objects contained thereon, other than fair wear and tear, which is caused by the Contractor or any Contractor’s Personnel.
Appears in 2 contracts
Samples: Works Order, Order Form
Provision and Removal of Equipment. 1. The Contractor shall provide all the Equipment necessary for the supply of the Services. The Contractor shall not deliver any Equipment nor begin any work on the Premises without obtaining prior written approval.
2. All Equipment brought onto the Premises shall be at the Contractor’s own risk. Unless otherwise agreed, Equipment brought onto the Premises will remain the property of the Contractor. The Contractor shall provide for the haulage or carriage to and the removal from the Premises of Equipment when no longer required at its sole cost.
3. The Contractor shall maintain all items of Equipment within the Premises in a safe, serviceable and clean condition.
4. The Contractor shall, at the Authority’s written request, at its own expense and as soon as reasonably possible:
4.1. remove from the Premises any Equipment which in the reasonable opinion of the Authority is either hazardous, noxious or not in accordance with the ContractFramework Agreement; and
4.2. replace such item with a suitable substitute item of Equipment.
5. On completion of the Services the Contractor shall remove the Equipment together with any other materials used by the Contractor to supply the Services and shall leave the Premises in a clean, safe and tidy condition. The Contractor is solely responsible for making good any damage to the Premises or any objects contained thereon, other than fair wear and tear, which is caused by the Contractor or any Contractor’s Personnel.
Appears in 1 contract
Samples: Framework Agreement
Provision and Removal of Equipment. 1. The Contractor
5.2.1 Unless otherwise stated in the Order Form, the Supplier shall provide all the Equipment necessary for the supply of the Services. The Contractor shall not deliver any Equipment nor begin any work on the Premises without obtaining prior written approval.
2. All Equipment brought onto the Premises shall be at the Contractor’s Supplier's own risk. Unless otherwise agreed, risk and the Customer shall have no liability for any loss of or damage to any Equipment brought onto unless and to the extent that the Supplier is able to demonstrate that such loss or damage was caused by or contributed to by the Customer's Default.
5.2.2 The Supplier shall not begin any work at the Premises will remain the property of the Contractor. The Contractor shall provide for the haulage or carriage to and the removal from the Premises of Equipment when no longer required at its sole costwithout obtaining Approval.
3. 5.2.3 The Contractor Supplier shall maintain all items of Equipment within the Premises in a safe, serviceable and clean condition.
4. The Contractor Supplier shall, at the Authority’s Customer's written request, at its own expense and as soon as reasonably possible:
4.1. practicable remove from the Premises and replace any Equipment which in the reasonable opinion of the Authority Customer is either hazardous, noxious or not in accordance with the Contract; and
4.2. replace such item with a suitable substitute item of Equipment.
5. On completion 5.2.4 Upon termination or expiry of the Services Contract, the Contractor Supplier shall remove the Equipment together with any other materials used by the Contractor Supplier to supply the Services and shall leave the Premises in a clean, safe and tidy condition. The Contractor Supplier is solely responsible for making good any damage to the Premises or any objects contained thereon, other than fair wear and tear, which is caused by the Contractor or any Contractor’s Personnel.
Appears in 1 contract
Samples: Framework Agreement