Punch List. (a) The Project Management Plan shall establish procedures and schedules for preparing a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions. (b) The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the Project, or shall follow such inspections. (c) Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT not less than five days’ prior notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. TxDOT may, but is not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s express permission. If Developer objects to the addition of an item by TxDOT, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this Agreement. Developer shall deliver to TxDOT a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared. (d) Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract Documents, within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.
Appears in 8 contracts
Samples: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement
Punch List. (a) 7.8.2.1 The Project Management Plan shall establish procedures and schedules for preparing preparing, for each Project Segment, a Punch List for the Project Segment and all corresponding portions of the Project between the ROW boundaries, including the applicable portions of the General Purpose Lanes and Frontage Roads, and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 7.8.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 7.8.2.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior written notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 7.8.2.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract CDA Documents, within the time period to be set forth in the Project Management Plan and in any case by the applicable Final Acceptance Deadline.
Appears in 6 contracts
Samples: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement
Punch List. (a) 9.4.1 The Project Management Plan shall establish procedures and schedules for preparing preparing, for each Project Segment, a Punch List for the Project Segment and all corresponding portions of the Project between the ROW boundaries, including the applicable portions of the General Purpose Lanes and Frontage Roads, and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 9.4.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 9.4.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 9.4.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract CDA Documents, within the time period to be set forth in the Project Management Plan and in any case by the applicable Final Acceptance Deadline.
Appears in 6 contracts
Samples: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement
Punch List. (a) 5.8.3.1 The Project Management Plan shall establish procedures and schedules for preparing a Punch List and for completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 5.8.3.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding DB Substantial Completion of the applicable Phase of the Project, or shall follow such inspectionsCompletion.
(c) 5.8.3.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT IFA not less than five (5) days’ prior notice Notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. TxDOT The Design-Build Contractor shall, and IFA may, but is not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTIFA, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile resolve the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT IFA a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 5.8.3.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract PPA Documents, the Final Design Documents and the Construction Documents within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.
Appears in 5 contracts
Samples: Public Private Agreement, Public Private Agreement, Public Private Agreement
Punch List. (a) The Project Management Plan shall establish procedures and schedules for preparing a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding DB Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT not less than five days’ prior notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. TxDOT may, but is not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s express permission. If Developer objects to the addition of an item by TxDOT, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this Agreement. Developer shall deliver to TxDOT a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract Documents, within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.
Appears in 4 contracts
Samples: Development Agreement, Development Agreement, Development Agreement
Punch List. (a) 7.8.2.1 The Project Facility Management Plan shall establish procedures and schedules for preparing for each Facility Segment a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 7.8.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 7.8.2.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior written notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 7.8.2.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract CDA Documents, within the time period to be set forth in the Project Facility Management Plan and in any case by the Final Acceptance Deadline.
Appears in 4 contracts
Samples: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement
Punch List. (a) 7.8.2.1 The Project Management Plan shall establish procedures and schedules for preparing preparing, for each Toll Segment, a Punch List for the Toll Segment and all corresponding portions of the Project between the ROW boundaries, including the applicable portions of the General Purpose Lanes and Frontage Roads, and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 7.8.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 7.8.2.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior written notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 7.8.2.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract CDA Documents, within the time period to be set forth in the Project Management Plan and in any case by the applicable Final Acceptance Deadline.
Appears in 3 contracts
Samples: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement
Punch List. (a) 7.8.2.1 The Project Facility Management Plan shall establish procedures and schedules for preparing a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 7.8.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 7.8.2.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior written notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 7.8.2.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract CDA Documents, within the time period to be set forth in the Project Facility Management Plan and in any case by the Final Acceptance Deadline.
Appears in 2 contracts
Samples: Comprehensive Development Agreement, Comprehensive Development Agreement
Punch List. (a) 7.8.2.1 The Project Facility Management Plan shall establish procedures and schedules for preparing a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 7.8.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 7.8.2.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior written notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 7.8.2.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract CDA Documents, within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.within
Appears in 1 contract
Samples: Comprehensive Development Agreement
Punch List. (a) The Project Management Plan shall establish procedures and schedules for preparing a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.:
(ba) The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(cb) Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT ADOT not less than five days’ prior notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. TxDOT ADOT may, but is not obligated to, participate in the development of the Punch List. Each participant Party shall have the right to add items to the Punch List and none List, but neither shall remove any item added by any the other Party without such otherother Party’s express permission. If Developer objects to the addition of an item by TxDOTADOT, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT ADOT a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(dc) Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract Documents, within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.
Appears in 1 contract
Samples: Design Build Maintain Agreement
Punch List. (a) 5.8.3.1 The Project Management Plan shall establish procedures and schedules for preparing a Punch List and for completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 5.8.3.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding DB Substantial Completion of the applicable Phase of the Project, or shall follow such inspectionsCompletion.
(c) 5.8.3.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT IFA not less than five (5) days’ prior notice Notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. TxDOT The Design-Build Contractor shall, and IFA may, but is not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTIFA, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile resolve the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT IFA a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 5.8.3.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract PPA Documents, the Final Design Documents and the Construction Documents within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.Deadline.
Appears in 1 contract
Samples: Public Private Agreement
Punch List. (a) 7.8.2.1 The Project Facility Management Plan shall establish procedures and schedules for preparing for each Facility Segment other than the Segment 3B Facility Segment a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 7.8.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 7.8.2.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior written notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 7.8.2.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract FA Documents, within the time period to be set forth in the Project Facility Management Plan and in any case by the applicable Final Acceptance Deadline.
7.8.2.5 The provisions of Section 7.8.2.3 shall apply, mutatis mutandis, to the Parties’ rights and obligations in connection with the TxDOT Works, with references therein to “Developer” constituting references to “TxDOT” and vice versa.
Appears in 1 contract
Samples: Facility Agreement
Punch List. (a) 7.8.2.1 The Project Facility Management Plan shall establish procedures and schedules for preparing for each Facility Segment a Punch List for the Facility Segment and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 7.8.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) 7.8.2.3 Developer shall prepare and maintain the Punch List. Developer shall deliver to TxDOT and the Independent Engineer not less than five days’ prior written notice stating the date when Developer will commence Punch List field inspections and Punch List preparation. The Independent Engineer and TxDOT may, but is are not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer objects to the addition of an item by TxDOTTxDOT or the Independent Engineer, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDispute Resolution Procedures. Developer shall deliver to TxDOT and the Independent Engineer a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) 7.8.2.4 Developer shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract CDA Documents, within the time period to be set forth in the Project Facility Management Plan and in any case by the Final Acceptance Deadline.
Appears in 1 contract
Samples: Comprehensive Development Agreement
Punch List. (a) 20.2.1 The Project Management Plan shall establish procedures and schedules for preparing a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 20.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the Projecta Location, or shall follow such inspections.
(c) Developer 20.2.3 DB Contractor shall prepare and maintain the Punch List. Developer DB Contractor shall deliver to TxDOT not less than five days’ prior written notice stating the date when Developer DB Contractor will commence Punch List field inspections and Punch List preparation. TxDOT may, but is not obligated to, participate in the development of the Punch List. Each participant shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer DB Contractor objects to the addition of an item by TxDOT, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDBC. Developer DB Contractor shall deliver to TxDOT a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) Developer 20.2.4 DB Contractor shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract DBC Documents, within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.
Appears in 1 contract
Samples: Design Build Contract
Punch List. (a) 20.2.1 The Project Management Plan shall establish procedures and schedules for preparing a Punch List and completing Punch List work. Such procedures and schedules shall conform to the following provisions.
(b) 20.2.2 The schedule for preparation of the Punch List either shall be consistent and coordinated with the inspections regarding Substantial Completion of the applicable Phase of the ProjectCompletion, or shall follow such inspections.
(c) Developer 20.2.3 DB Contractor shall prepare and maintain the Punch List. Developer DB Contractor shall deliver to TxDOT not less than five days’ prior written notice stating the date when Developer DB Contractor will commence Punch List field inspections and Punch List preparation. TxDOT TxDOT, FHWA and the Authority may, but is are not obligated to, participate in the development of the Punch List. Each participant TxDOT, FHWA and DB Contractor shall have the right to add items to the Punch List and none shall remove any item added by any other without such other’s 's express permission. If Developer DB Contractor objects to the addition of an item by TxDOTTxDOT or FHWA, the item shall be noted as included under protest, and if the Parties thereafter are unable to reconcile the protest, the Dispute shall be resolved according to the dispute resolution procedures set forth in this AgreementDBA. Developer DB Contractor shall deliver to TxDOT a true and complete copy of the Punch List, and each modification thereto, as soon as it is prepared.
(d) Developer 20.2.4 DB Contractor shall immediately commence work on the Punch List items and diligently prosecute such work to completion, consistent with the Contract DBA Documents, within the time period to be set forth in the Project Management Plan and in any case by the Final Acceptance Deadline.
Appears in 1 contract
Samples: Design Build Agreement