Reconversion to Lump Sum. If the Contractor subsequently: (a) Recovers all lost time and puts the work back on schedule; and (b) Remedies all breaches of Notices of Non-Compliant Work; and (c) Supplies a proper breakdown and accounting pursuant to any Change Orders utilizing a Force Account; then the sums withheld while either or all of the events existed will be again converted to a lump sum.
Appears in 36 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Reconversion to Lump Sum. If the Contractor subsequently:
(a) Recovers all lost time and puts the work back on schedule; and
(b) Remedies all breaches of Notices of Non-Compliant Work; and
(c) Supplies a proper breakdown and accounting pursuant to any Change Orders utilizing a Force Account; then the sums withheld while either or all of the events existed will be again converted to a lump sum.;
Appears in 1 contract
Reconversion to Lump Sum. If the Contractor subsequently:
(a) : Recovers all lost time and puts the work back on schedule; and
(b) and Remedies all breaches of Notices of Non-Compliant Work; and
(c) and Supplies a proper breakdown and accounting pursuant to any Change Orders utilizing a Force Account; then the sums withheld while either or all of the events existed will be again converted to a lump sum.
Appears in 1 contract
Samples: Construction Contract