Rectification of Defects. (a) The Developer will use its best endeavours to have rectified any reasonable defect notified to the Developer in accordance with clause 8.4 prior to the Date for Completion. (b) If the Developer has been unable to arrange the completion of any rectification work notified in accordance with clause 8.4 prior to the Date for Completion, the Buyer may not delay Completion and any unrectified defects will be completed in accordance with clause 7. (c) The submission of a defects list in accordance with clause 8.4 or the failure to submit a list of defects in accordance with clause 8.4 in no way derogates from the Buyer's rights under clause 7.
Appears in 15 contracts
Samples: Built Form Delivery Contract Lease Back (With Furniture), Built Form Delivery Contract Lease Back (With Furniture), Built Form Delivery Contract Lease Back (With Furniture)
Rectification of Defects. (a) The Developer will use its best endeavours to have rectified any reasonable defect notified to the Developer in accordance with clause 8.4 7.4 prior to the Date for Completion.
(b) If the Developer has been unable to arrange the completion of any rectification work notified in accordance with clause 8.4 7.4 prior to the Date for Completion, the Buyer may not delay Completion and any unrectified defects will be completed in accordance with clause 76.
(c) The submission of a defects list in accordance with clause 8.4 7.4 or the failure to submit a list of defects in accordance with clause 8.4 7.4 in no way derogates from the Buyer's rights under clause 76.
Appears in 2 contracts
Samples: Land Development Contract, Built Form Delivery Contract
Rectification of Defects.
(a) The Developer will use its best endeavours to have rectified any reasonable defect notified to the Developer in accordance with clause 8.4 7.4 prior to the Date for Completion.
(b) If the Developer has been unable to arrange the completion of any rectification work notified in accordance with clause 8.4 7.4 prior to the Date for Completion, the Buyer may not delay Completion and any unrectified defects will be completed in accordance with clause 76.
(c) The submission of a defects list in accordance with clause 8.4 7.4 or the failure to submit a list of defects in accordance with clause 8.4 7.4 in no way derogates from the Buyer's rights under clause 76.
Appears in 1 contract
Samples: Built Form Delivery Contract