Rectification of Defects. 23.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period. 23.2 The developer, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the council. 23.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.
Appears in 2 contracts
Samples: Planning Agreement, Planning Agreement
Rectification of Defects. 23.1 27.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 27.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 27.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.127.1.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 19.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 19.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 19.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.19.1
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 29.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 29.2 The developer, at its own cost, Developer is to comply with a Rectification Notice according to its the terms of the Rectification Notice and to the reasonable satisfaction of the councilCouncil.
23.3 29.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1by the Council.
Appears in 1 contract
Samples: Works in Kind Agreement
Rectification of Defects. 23.1 17.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 17.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 17.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.17.1
Appears in 1 contract
Samples: Voluntary Planning Agreement
Rectification of Defects. 23.1 15.1 The Council may give the Developer a Rectification Notice in relation to a Work during the Defects Liability Period.
23.2 15.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 15.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.115.1.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.
23.4 A Rectification Notice issued by Council in accordance with clause 23.1 may only require Work undertaken by the Developer to be completed to the standard specified and approved by Council in accordance with clause 15 of this Deed.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 20.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 20.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 20.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.20.1
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 21.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 21.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 21.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.121.1
21.4 A Rectification Notice issued by Council in accordance with clause 21.1 may only require Work undertaken by the Developer to be completed to the standard specified and approved by Council in accordance with clause 13 of this Deed.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 37.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 37.2 The developer, at its own cost, Developer is to comply with a Rectification Notice according to its the terms of the Rectification Notice and to the reasonable satisfaction of the councilCouncil.
23.3 37.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1by the Council.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 The developer, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the council.
23.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 16.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 16.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the council.
23.3 Council. The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.116.1.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 E.1 The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 E.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.
Appears in 1 contract
Samples: Planning Agreement
Rectification of Defects. 23.1 The 31.1 During the Defects Liability Period, the Council may give the Developer a Rectification Notice during the Defects Liability PeriodNotice.
23.2 The developer31.2 Subject to the resolution of a dispute in accordance with this Agreementthis Deed, at its own cost, the Developer is to comply with a Rectification Notice according to at its terms own cost and to the reasonable satisfaction of the councilCouncil.
23.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.1.
Appears in 1 contract
Samples: Environmental Lands and Services Planning Agreement
Rectification of Defects. 23.1 (a) The Council may give the Developer a Rectification Notice during the Defects Liability Period.
23.2 (b) The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 (c) The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.15.6(a).
Appears in 1 contract
Samples: Voluntary Planning Agreement
Rectification of Defects. 23.1 14.1 The Council may give the Developer a Rectification Notice during the Defects Liability PeriodTerm.
23.2 14.2 The developerDeveloper, at its own cost, is to comply with a Rectification Notice according to its terms and to the reasonable satisfaction of the councilCouncil.
23.3 14.3 The Council is to do such things as are reasonably necessary to enable the Developer to comply with a Rectification Notice that has been given to it under clause 23.114.1.
Appears in 1 contract