Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 14 contracts
Samples: Call Off Contract, Call Off Order Form and Call Off Terms, Call Off Order Form and Call Off Terms
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 13 contracts
Samples: Call Off Order Form and Call Off Terms for Services (Non Ict), Call Off Contract, Call Off Terms for Services
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractContract : it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 3 contracts
Samples: Contract Order Form and Contract Terms, Contract Order Form and Contract Terms for Goods and/or Services (Non Ict), Contract Order Form and Contract Terms
Rectification of Delay in Implementation. If the Supplier Service Provider becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 3 contracts
Samples: Call Off Terms, Call Off Terms, Call Off Terms
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (g) (Delay Payments) shall apply.
Appears in 3 contracts
Samples: Call Off Order Form, Call Off Contract, Call Off Contract
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer Contracting Authority as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the CustomerContracting Authority’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 2 contracts
Samples: Framework Agreement, Framework Agreement
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (c) (Delay Payments) shall apply.
Appears in 2 contracts
Samples: Managed Learning Services Call Off Contract, Call Off Contract
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 7.4 (Delay Payments) shall apply.
Appears in 1 contract
Samples: Call Off Contract
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.
Appears in 1 contract
Samples: Call Off Contract
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractLease Agreement: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (c) (Delay Payments) shall apply.
Appears in 1 contract
Samples: Lease Agreement
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Call-Off Contract: it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (g) (Delay Payments) shall apply.
Appears in 1 contract
Samples: Vehicle Hire Services Order Form
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractContract : it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply.the
Appears in 1 contract
Samples: Contract Order Form and Contract Terms for Goods and/or Services (Non Ict)
Rectification of Delay in Implementation. If the Supplier becomes aware that there is, or there is reasonably likely to be, a Delay under this Call Off ContractContract : it shall: notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and include in its notification an explanation of the actual or anticipated impact of the Delay; and comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (c) (Delay Payments) shall apply.
Appears in 1 contract
Samples: Contract Order Form