Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be a Delay under this Call Off Contract: a) it shall: (i) notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and (ii) include in its notification an explanation of the actual or anticipated impact of the Delay; and (iii) comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and (iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply Unless the Delay is deemed as resulting from Customer Cause.
Appears in 1 contract
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be be, a Delay under this Call Off ContractContract :
(a) it shall:
(i) notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and;
(ii) include in its notification an explanation of the actual or anticipated impact of the Delay; and;
(iii) comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and
(iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and
(b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply Unless the Delay is deemed as resulting from Customer Causeapply.
Appears in 1 contract
Samples: Dynamic Purchasing System Agreement
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be be, a Delay under this Call Off Contract:
(a) it shall:
(i) notify the Customer Contracting Authority as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and;
(ii) include in its notification an explanation of the actual or anticipated impact of the Delay; and;
(iii) comply with the CustomerContracting Authority’s instructions in order to address the impact of the Delay or anticipated Delay; and
(iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and
(b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply Unless the Delay is deemed as resulting from Customer Causeapply.
Appears in 1 contract
Samples: Framework Agreement
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be be, a Delay under this Call Off Contract:
(a) it shall:
(i) notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and;
(ii) include in its notification an explanation of the actual or anticipated impact of the Delay; and;
(iii) comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and
(iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and
(b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply Unless the Delay is deemed as resulting from Customer Causeapply.
Appears in 1 contract
Rectification of Delay in Implementation. 6.3.1 If the Supplier becomes aware that there is, or there is reasonably likely to be be, a Delay under this Call Off Contract:
(a) it shall:
(i) notify the Customer as soon as practically possible and no later than within two (2) Working Days from becoming aware of the Delay or anticipated Delay; and
(ii) include in its notification an explanation of the actual or anticipated impact of the DelayDelay (including the likelihood of such impact where anticipated); and
(iii) expeditiously comply with the Customer’s instructions in order to address the impact of the Delay or anticipated Delay; and
(iv) use all reasonable endeavours to eliminate or mitigate the consequences of any Delay or anticipated Delay; and
(b) if the Delay or anticipated Delay relates to a Milestone in respect which a Delay Payment has been specified in the Implementation Plan, Clause 6.4 (Delay Payments) shall apply Unless the Delay is deemed as resulting from Customer Causeapply.
Appears in 1 contract
Samples: Call Off Terms for Services