Refund of Security. The amount provided by Seller as Contract Security will be returned or refunded to Seller by NYSERDA as follows: a. In the amount of fifty percent (50%) of the amount provided if the Bidder elects to terminate this Agreement on or before July 15, 2007. b. In its entirety if the Bid Capacity of the Bid Facility that enters Commercial Operation on or before the Commercial Operation Milestone Date is equal to or greater than the Bid Capacity of the Bid Facility described in the Bid Proposal. c. At a prorated amount if the Bid Capacity of the Bid Facility that enters Commercial Operation on or before the Commercial Operation Milestone Date is less than the Bid Capacity of the Bid Facility described in the Bid Proposal. Such amount that will be returned, expressed as a percentage of the total Contract Security, will be equal to Bid Capacity of the Bid Facility that enters Commercial Operation on or before the Commercial Operation Milestone Date divided by the Bid Capacity of the Bid Facility described in the Bid Proposal.
Appears in 8 contracts
Samples: RPS Standard Form Contract, RPS Standard Form Contract (Noble Environmental Power LLC), RPS Standard Form Contract (Noble Environmental Power LLC)
Refund of Security. The amount provided by Seller as Contract Security will be returned or refunded to Seller by NYSERDA as follows:
a. In the amount of fifty percent (50%) of the amount provided if the Bidder elects to terminate this Agreement on or before July 15October 1, 20072008.
b. In its entirety if the Bid Capacity of the Bid Facility that enters Commercial Operation on or before the Commercial Operation Milestone Date is equal to or greater than the Bid Capacity of the Bid Facility described in the Bid Proposal.
c. At a prorated amount if the Bid Capacity of the Bid Facility that enters Commercial Operation on or before the Commercial Operation Milestone Date is less than the Bid Capacity of the Bid Facility described in the Bid Proposal. Such amount that will be returned, expressed as a percentage of the total Contract Security, will be equal to Bid Capacity of the Bid Facility that enters Commercial Operation on or before the Commercial Operation Milestone Date divided by the Bid Capacity of the Bid Facility described in the Bid Proposal.
Appears in 1 contract
Samples: RPS Standard Form Contract (Noble Environmental Power LLC)